Opening the dossier…
Opening the dossier…
Contractor dossier
20 projects on file, including joint ventures this contractor is part of.
Total projects
20
Total budget
₱722.7M
Average progress
100.0%
Completion rate
100.0%
Average risk score
38.7
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-B | 17 | ₱650.1M | 40.0 | 0 | 100.0% |
| Region XII | 2 | ₱56.1M | 23.4 | 0 | 100.0% |
| Region VII | 1 | ₱16.6M | 46.3 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 8 | ₱293.6M | 40.7 | 0 | 100.0% |
| Flood Control and Drainage | 7 | ₱277.4M | 38.2 | 0 | 100.0% |
| Water Provision and Storage | 4 | ₱146.8M | 40.7 | 0 | 100.0% |
| Buildings and Facilities | 1 | ₱4.9M | 18.0 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Nothing to report.
No high-risk projects here.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 18EA0100CONSTRUCTION OF WATERSYSTEM (WATERWORKS), TORRIJOS, MARINDUQUE | Region IV-B | Marinduque DEO | Completed | ₱92.7M | 100% | Medium risk52 | —-0.032 |
| 2 | 18EA0079OFF-CARRIAGEWAY IMPROVEMENT OF MARINDUQUE CIRCUMFERENTIAL RD - K0003 + 264 - K0004 + 463, K0004 + 600 - K0005 + 300, K0009 + 386 - K0010 + 076 | Region IV-B | Marinduque DEO | Completed | ₱56.3M | 100% | Medium risk47 | —-0.075 |
| 3 | 18EA0040REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS OF TIGWI-DAMPULAN-LIPATA-YOOK-BUENAVI | Region IV-B | Marinduque DEO | Completed | ₱77.9M | 100% | Medium risk47 | —-0.079 |
| 4 | 22HF0042CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION /IMPROVEMENT OF ALEGRIA-BANGKITO ROAD LEADING TO KABANGKALAN COFFEE PLANTATION, BRGY. ALEGRIA-BANGKITO, TUBURAN, CEBU | Region VII | Cebu 3rd DEO | Completed | ₱16.6M | 100% | Medium risk46 | —-0.086 |
| 5 | 18EA0062CONSTRUCTION OF CONCRETE DIKE FLOOD CONTROL STRUCTURE ALONG BOAC RIVER AT BRGY. SANTOL-MURALLON SECT | Region IV-B | Marinduque DEO | Completed | ₱57M | 100% | Medium risk45 | —-0.066 |
| 6 | 21EA0066CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE (INCLUDING RECHANNELING), SANTOL-TABIGUE, BOAC, MARINDUQUE | Region IV-B | Marinduque DEO | Completed | ₱56.4M | 100% | Medium risk45 | —-0.072 |
| 7 | 18EA0086CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, BOAC-MOGPOG BYPASS ROAD, INCL. ROW, MARINDUQUE | Region IV-B | Marinduque DEO | Completed | ₱45.3M | 100% | Medium risk38 | —-0.083 |
| 8 | 18EA0085CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, BOAC, BYPASS ROAD, INCL. ROW, MARINDUQUE | Region IV-B | Marinduque DEO | Completed | ₱35.5M | 100% | Medium risk37 | —-0.082 |
| 9 | 18EA0058CONSTRUCTION OF TABI FLOOD CONTROL STRUCTURE | Region IV-B | Marinduque DEO | Completed | ₱42.1M | 100% | Medium risk37 | —-0.073 |
| 10 | 18EA0029CONSTRUCTION OF TAWIRAN FLOOD CONTROL STRUCTURE | Region IV-B | Marinduque DEO | Completed | ₱23M | 100% | Medium risk37 | —-0.072 |
| 11 | 18EA0091PACKAGE 18 - A) CONSTRUCTION OF WATER SYSTEM (WATERWORKS), BARANGAY MALINAO, TORRIJOS, MARINDUQUE, B) CONSTRUCTION OF WATER SYSTEM FROM DIVISORIA TO ESTASYON, TORRIJOS, MARINDUQUE, C) CONSTRUCTION OF WATER SYSTEM, BARANGAY MABUHAY, TORRIJOS, MARINDUQUE, | Region IV-B | Marinduque DEO | Completed | ₱18.1M | 100% | Medium risk37 | —-0.050 |
| 12 | 18EA0101PACKAGE 23- A) CONSTRUCTION OF WATER SYSTEM (WATERWORKS), BARANGAY BANGWAYIN, TORRIJOS MARINDUQUE, B | Region IV-B | Marinduque DEO | Completed | ₱19.7M | 100% | Medium risk37 | —-0.051 |
| 13 | 18EA0116PACKAGE 37-A)CONCRETING OF 1.1 LANE KM. MAKAWAYAN TO PUROK STA. ANA ROAD, BARANGAY MAKAWAYAN, TORRIJ | Region IV-B | Marinduque DEO | Completed | ₱18M | 100% | Medium risk37 | —-0.094 |
| 14 | 18EA0030CONSTRUCTION OF BOCBOC FLOOD CONTROL STRUCTURE | Region IV-B | Marinduque DEO | Completed | ₱23.8M | 100% | Medium risk37 | —-0.074 |
| 15 | 18EA0052CONSTRUCTION OF CONCRETE DIKE FLOOD CONTROL STRUCTURE ALONG BOAC RIVER AT BRGY. TANZA | Region IV-B | Marinduque DEO | Completed | ₱23.8M | 100% | Medium risk37 | —-0.074 |
| 16 | 18EA0114PACKAGE 35- A) CONCRETING OF 2.0 LANE KM MALIBAGO-MASILIG ROAD, BARANGAY MALIBAGO, TORRIJOS, MARINDU | Region IV-B | Marinduque DEO | Completed | ₱23.7M | 100% | Medium risk37 | —-0.094 |
| 17 | 18EA0102PACKAGE 24-A) CONSTRUCTION OF WATER SYSTEM (WATERWORKS), BARANGAY BAYAKBAKIN, TORRIJOS, MARINDUQUE, | Region IV-B | Marinduque DEO | Completed | ₱16.4M | 100% | Medium risk37 | —-0.051 |
| 18 | 18EA0117PACKAGE 38- A) CONCRETING OF 0.900 LANE KM. DAMPULAN-MAULAWIN ROAD, BARANGAY DAMPULAN, TORRIJOS, B) | Region IV-B | Marinduque DEO | Completed | ₱20.3M | 100% | Medium risk37 | —-0.091 |
| 19 | 23MB0080CONSTRUCTION OF CONCRETE REVETMENT, UPPER SINAWAL BRIDGE, SINAWAL RIVER, GENERAL SANTOS CITY | Region XII | South Cotabato 1st DEO | Completed | ₱51.1M | 100% | Low risk29 | —-0.069 |
| 20 | 22ME0095CONST. OF MPB BRGY. PANGYAN, GLAN, SARANGANI PROVINCE | Region XII | Sarangani DEO | Completed | ₱4.9M | 100% | Low risk18 | —-0.076 |