904 projects on file, including joint ventures this contractor is part of.
Total projects
904
Total budget
₱22.9B
Average progress
97.5%
Completion rate
88.8%
Average risk score
41.6
Medium risk on average, out of 100
Flagged as unusual
30
3.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IX | 536 | ₱15.6B | 47.0 | 24 | 96.6% |
| Region VII | 252 | ₱3.6B | 30.4 | 4 | 99.4% |
| Region X | 110 | ₱3.6B | 41.5 | 2 | 97.1% |
| Region XI | 5 | ₱19.6M | 26.4 | 0 | 100.0% |
| Region XIII | 1 | ₱120.6M | 50.1 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 371 | ₱3.3B | 24.9 | 5 | 99.5% |
| Roads | 326 | ₱10.4B | 51.0 | 3 | 97.4% |
| Flood Control and Drainage | 116 | ₱5.3B | 52.6 | 2 | 98.3% |
| Bridges | 37 | ₱1.3B | 52.7 | 2 | 89.6% |
| OTHER | 19 | ₱1.4B | 78.6 | 7 | 98.0% |
| Water Provision and Storage | 19 | ₱154.6M | 36.9 | 0 | 100.0% |
| GAA 2025 OO-1 | 9 | ₱493.7M | 93.2 | 7 | 40.4% |
| GAA 2025 OO-2 | 4 | ₱352M | 90.8 | 1 | 80.4% |
| GAA 2025 SSP | 3 | ₱225.2M | 95.4 | 3 | 89.8% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25J00021PREVENTIVE MAINTENANCE - PRIMARY ROADS ALONG MAHARLIKA HIGHWAY (LANAO - PAGADIAN - ZAMBOANGA CITY RD) K1651+060.00 - K1653+244.03 | Region IX | Region IX | On-Going | ₱109.1M | 83% | High risk96 | Flagged0.026 |
| 25HC0060CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS-ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF ROAD, BRGY. HUMAY-HUMAY TO | Region VII | Bohol 2nd DEO | On-Going | ₱48.2M | 93% | High risk95 | Flagged0.012 |
| 25HG0082BIP - COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES, CONSTRUCTION OF CAUSEWAY AT BOGO PANTALAN, BOGO, CEBU | Region VII | Cebu 4th DEO | On-Going | ₱67.9M | 94% | High risk95 | Flagged0.012 |
| 25KG0047REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG LINAMON-ZAMBOANGA ROAD (S00914MN), K1556+961-K1557+000, K1558+464-K1560+096, K1560+134-K1561+014, K1590+408-K1591+531, LANAO DEL NORTE | Region X | Lanao del Norte 1st DEO | On-Going | ₱96.1M | 48% | High risk95 | Flagged0.009 |
| 25J00243PREVENTIVE MAINTENANCE - PRIMARY ROADS - MAHARLIKA HIGHWAY (PAGADIAN CITY - ZAMBOANGA CITY RD) | Region IX | Region IX | On-Going | ₱72.1M | 91% | High risk94 | —-0.000 |
| 25KG0052REHAB/RECONST/UPGRADING OF DAMAGED PAVED ROADS ALONG LINAMON-ZAMBOANGA ROAD (S00914MN), K1580+691-K1580+896, K1580+910-K1580+933, K1582+000-K1582+386, K1582+441-K1583+137, K1583+503-K1583+655, K1583+788-K1584+293, K1585+871-K1586+000, K1588+225-K1588+813, | Region X | Lanao del Norte 1st DEO | On-Going | ₱96.1M | 20% | High risk94 | Flagged0.017 |
| 25J00248PREVENTIVE MAINTENANCE - PRIMARY ROADS - MAHARLIKA HIGH-WAY (LANAO - PAGADIAN - ZAMBOANGA CITY RD) | Region IX | Region IX | On-Going | ₱93.8M | 31% | High risk94 | Flagged0.018 |
| 25JI0028PREVENTIVE MAINTENANCE - TERTIARY ROADS - IMELDA-PAYAO-SIAY RD - K1761+000 - K1762+693 | Region IX | Zamboanga Sibugay 1st DEO | On-Going | ₱47.5M | 95% | High risk93 | —-0.003 |
| 25J00128CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BOGAYO RIVER, KUMALARANG BR. 1 SECTION (B00549MN) ALONG PAGADIAN CITY-ZAMBOANGA CITY RD (S01453MN), PACKAGE 2, BARANGAY BOGAYO, KUMA | Region IX | Region IX | On-Going | ₱142.6M | 53% | High risk93 | Flagged0.009 |
| 25HN0104OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION RIVERBANK FACILITIES ALONG JAGOBIAO CREEK, PACKAGE I, BARANGAY SACSAC, CONSOLACION, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱135M | 99% | High risk93 | —-0.006 |
| 25J00114REPLACEMENT OF PERMANENT WEAK BRIDGES - BAYAO BR. (B01201MN), ALONG MAHARLIKA HIGHWAY (LANAO - PAGADIAN - ZAMBOANGA CITY) | Region IX | Region IX | On-Going | ₱28.1M | 2% | High risk93 | Flagged0.021 |
| 25JB0020WIDENING OF PERMANENT BRIDGES GUINLES PARALLEL BRIDGE ALONG DIPOLOG-POLANCO-PIÑAN-JCT. OROQUIETA ROAD | Region IX | Zamboanga del Norte 1st DEO | On-Going | ₱34.7M | 59% | High risk93 | Flagged0.005 |
| 25J00122REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - MAHARLIKA HIGHWAY (PAGADIAN CITY-ZAMBOANGA CITY RD) | Region IX | Region IX | On-Going | ₱14M | 17% | High risk92 | Flagged0.015 |
| 25J00121REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS/ SLOPE COLLAPSE AND LANDSLIDE - PRIMARY ROADS - MAHARLIKA HIGHWAY (PAGADIAN CITY - ZAMBOANGA CITY RD) | Region IX | Region IX | On-Going | ₱11.2M | 2% | High risk91 | Flagged0.019 |
| 25KG0021CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG SAGADAN BRIDGE (B00960MN), PACKAGE 2, TUBOD, LANAO DEL NORTE | Region X | Lanao del Norte 1st DEO | On-Going | ₱59.7M | 70% | High risk90 | —-0.017 |
| 24HN0229CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - IMPROVEMENT OF ROAD, BARANGAY TAYUD, CONSOLACION, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱47.2M | 82% | High risk87 | Flagged0.053 |
| 25JB0038CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION OF RIVER BANK PROTECTION WORKS LAPAYAN BAJA CIS, POLANCO, ZAMBOANGA DEL NORTE | Region IX | Zamboanga del Norte 1st DEO | On-Going | ₱14.7M | 100% | High risk87 | —-0.019 |
| 24J00172PREVENTIVE MAINTENANCE - PRIMARY ROADS - LANAO - PAGADIAN - ZAMBOANGA CITY ROAD (SO1112MN) | Region IX | Region IX | On-Going | ₱144.6M | 99% | High risk82 | Flagged0.020 |
| 21J00038CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL ALONG IMELDA - BAYOG - KUMALARANG - LAPUYAN - MARGOSATUBIG ROAD, PART OF SIBUGUEY RIVER, BARANGAY PARADISE, DIPLAHAN, ZAMBOANGA SIBUGAY | Region IX | Region IX | On-Going | ₱129.1M | 100% | High risk82 | Flagged0.034 |
| 23J00088CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - NRJ BALUCOT-LOWER USUGAN-TUNGAWAN ROAD, ZAMBOANGA DEL SUR | Region IX | Region IX | On-Going | ₱96.1M | 86% | High risk82 | Flagged0.024 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24HN0229CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - IMPROVEMENT OF ROAD, BARANGAY TAYUD, CONSOLACION, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱47.2M | 82% | High risk87 | Flagged0.053 |
| 21J00038CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL ALONG IMELDA - BAYOG - KUMALARANG - LAPUYAN - MARGOSATUBIG ROAD, PART OF SIBUGUEY RIVER, BARANGAY PARADISE, DIPLAHAN, ZAMBOANGA SIBUGAY | Region IX | Region IX | On-Going | ₱129.1M | 100% | High risk82 | Flagged0.034 |
| 24HC0167FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM, CONSTRUCTION OF FLOOD MITIGATION STRUCTURES, INABANGA, BOHOL | Region VII | Bohol 2nd DEO | On-Going | ₱48.2M | 79% | Medium risk56 | Flagged0.027 |
| 25J00021PREVENTIVE MAINTENANCE - PRIMARY ROADS ALONG MAHARLIKA HIGHWAY (LANAO - PAGADIAN - ZAMBOANGA CITY RD) K1651+060.00 - K1653+244.03 | Region IX | Region IX | On-Going | ₱109.1M | 83% | High risk96 | Flagged0.026 |
| 23J00088CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - NRJ BALUCOT-LOWER USUGAN-TUNGAWAN ROAD, ZAMBOANGA DEL SUR | Region IX | Region IX | On-Going | ₱96.1M | 86% | High risk82 | Flagged0.024 |
| 16JC0026CONSTRUCTION OF FOUR (4) UNITS TWO (2) STOREY TEN (10) CLASSROOM SCHOOL BUILDING AT SALUG NHS, SALUG, ZAMBOANGA DEL NORTE | Region IX | Zamboanga del Norte 3rd DEO | Terminated | ₱25.3M | 100% | Medium risk39 | Flagged0.022 |
| 24JI0118PREVENTIVE MAINTENANCE-TERTIARY ROAD - JCT. IMELDA-ALICIA RD (S01114MN) - K1765+005.50 - K1765+550, K1765+550 - K1766+052, K1766+052 - K1766+525, K1766+561 - K1767+755.50 | Region IX | Zamboanga Sibugay 1st DEO | On-Going | ₱144.7M | 97% | High risk70 | Flagged0.021 |
| 24J00054PREVENTIVE MAINTENANCE - PRIMARY ROADS - LANAO -PAGADIAN - ZAMBOANGA CITY ROAD | Region IX | Region IX | On-Going | ₱139.7M | 100% | High risk82 | Flagged0.021 |
| 25J00114REPLACEMENT OF PERMANENT WEAK BRIDGES - BAYAO BR. (B01201MN), ALONG MAHARLIKA HIGHWAY (LANAO - PAGADIAN - ZAMBOANGA CITY) | Region IX | Region IX | On-Going | ₱28.1M | 2% | High risk93 | Flagged0.021 |
| 24J00172PREVENTIVE MAINTENANCE - PRIMARY ROADS - LANAO - PAGADIAN - ZAMBOANGA CITY ROAD (SO1112MN) | Region IX | Region IX | On-Going | ₱144.6M | 99% | High risk82 | Flagged0.020 |
| 25J00121REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS/ SLOPE COLLAPSE AND LANDSLIDE - PRIMARY ROADS - MAHARLIKA HIGHWAY (PAGADIAN CITY - ZAMBOANGA CITY RD) | Region IX | Region IX | On-Going | ₱11.2M | 2% | High risk91 | Flagged0.019 |
| 25J00248PREVENTIVE MAINTENANCE - PRIMARY ROADS - MAHARLIKA HIGH-WAY (LANAO - PAGADIAN - ZAMBOANGA CITY RD) | Region IX | Region IX | On-Going | ₱93.8M | 31% | High risk94 | Flagged0.018 |
| 25JE0058CONSTRUCTION OF BY-PASS AND DIVERSION ROADS NRJ POBLACION-TAMBULIG-TUNGAWAN-KAUSWAGAN ROAD (BALUGO BRIDGE), ZAMBOANGA DEL SUR, TAMBULIG, ZAMBOANGA DEL SUR | Region IX | Zamboanga del Sur 1st DEO | On-Going | ₱77.2M | 25% | High risk66 | Flagged0.017 |
| 25KG0052REHAB/RECONST/UPGRADING OF DAMAGED PAVED ROADS ALONG LINAMON-ZAMBOANGA ROAD (S00914MN), K1580+691-K1580+896, K1580+910-K1580+933, K1582+000-K1582+386, K1582+441-K1583+137, K1583+503-K1583+655, K1583+788-K1584+293, K1585+871-K1586+000, K1588+225-K1588+813, | Region X | Lanao del Norte 1st DEO | On-Going | ₱96.1M | 20% | High risk94 | Flagged0.017 |
| 25J00122REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - MAHARLIKA HIGHWAY (PAGADIAN CITY-ZAMBOANGA CITY RD) | Region IX | Region IX | On-Going | ₱14M | 17% | High risk92 | Flagged0.015 |
| 25HG0082BIP - COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES, CONSTRUCTION OF CAUSEWAY AT BOGO PANTALAN, BOGO, CEBU | Region VII | Cebu 4th DEO | On-Going | ₱67.9M | 94% | High risk95 | Flagged0.012 |
| 25HC0060CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS-ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF ROAD, BRGY. HUMAY-HUMAY TO | Region VII | Bohol 2nd DEO | On-Going | ₱48.2M | 93% | High risk95 | Flagged0.012 |
| 25J00128CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BOGAYO RIVER, KUMALARANG BR. 1 SECTION (B00549MN) ALONG PAGADIAN CITY-ZAMBOANGA CITY RD (S01453MN), PACKAGE 2, BARANGAY BOGAYO, KUMA | Region IX | Region IX | On-Going | ₱142.6M | 53% | High risk93 | Flagged0.009 |
| 25KG0047REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG LINAMON-ZAMBOANGA ROAD (S00914MN), K1556+961-K1557+000, K1558+464-K1560+096, K1560+134-K1561+014, K1590+408-K1591+531, LANAO DEL NORTE | Region X | Lanao del Norte 1st DEO | On-Going | ₱96.1M | 48% | High risk95 | Flagged0.009 |
| 23J00221CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL AT SIBUGUEY RIVER ALONG IMELDA-BAYOG-KUMALARANG-LAPUYAN-MARGOSATUBIG ROAD, BARANGAY PARADISE, DIPLAHAN, ZAMBOANGA SIB | Region IX | Region IX | On-Going | ₱48.2M | 100% | High risk79 | Flagged0.008 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 426 | 24KG0024CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG TITUNOD BRIDGE II (B00956MN), UPSTREAM (R/S), KOLAMBUGAN, LANAO DEL NORTE | Region X | Lanao del Norte 1st DEO | Completed | ₱49M | 100% | Medium risk48 | —-0.081 |
| 427 | 16KJ0091REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE BASE ON PAVEMENT MANAGEMENT SYSTEM/HIGHWAY DEVELOPMENT & MANAGEMENT-4 (HDM-4), OZAMIZ PAGADIAN ROAD K1683+809-K1683+916, K1695+000-K1695+409-K1695+551 | Region X | Misamis Occidental 2nd DEO | Completed | ₱19.9M | 100% | Medium risk47 | —-0.060 |
| 428 | 20KF0130CONSTRUCTION OF EVACUATION CENTER IN BRGY. POBLACION, LINAMON, LANAO DEL NORTE | Region X | Lanao del Norte 1st DEO | Completed | ₱34.7M | 100% | Medium risk47 | —-0.088 |
| 429 | 19HF0055CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT LANGOYON RIVER BASIN, BRGY. ALEGRIA, TUBURAN, CEBU | Region VII | Cebu 3rd DEO | Completed | ₱39.2M | 100% | Medium risk47 | —-0.079 |
| 430 | 24HN0147CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING , BARANGAY BANGBANG, CORDOVA, CEBU | Region VII | Cebu 6th DEO | Completed | ₱4.9M | 100% | Medium risk47 | —-0.096 |
| 431 | 17HA0145CONSTRUCTION OF FOUR STOREY 20 CLASSROOM SCHOOL BUILDING, DR. CECILIO PUTONG NATIONAL HIGH SCHOOL, TAGBILARAN CITY, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱47.7M | 100% | Medium risk47 | —-0.018 |
| 432 | 22HB0136CONVERGENCE AND SPECIAL SUPPORT PROGRAM -SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION OF MULTI-PURPOSE BUILDING, MUNICIPALITY OF JAGNA, BOHOL | Region VII | Bohol 3rd DEO | Completed | ₱43.1M | 100% | Medium risk47 | —-0.075 |
| 433 | 19HA0011CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF CALUNASAN FLOOD CONTROL, CALUNASAN, CALAPE, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱30.2M | 100% | Medium risk47 | —-0.077 |
| 434 | 19KF0111CONSTRUCTION OF RIVER REVETMENT ALONG ILIGAN RIVER AT BRGY. ABUNO, ILIGAN CITY | Region X | Lanao del Norte 1st DEO | Completed | ₱48.2M | 100% | Medium risk47 | —-0.081 |
| 435 | 23KM0030CONSTRUCTION OF FLOOD CONTROL STRUCTURE AND DRAINAGE SYSTEM ALONG ILIGAN RIVER (PALA-O SECTION), ILIGAN CITY | Region X | Iligan City DEO | Completed | ₱48.3M | 100% | Medium risk47 | —-0.082 |
| 436 | 19HA0012CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF MANDUAG FLOOD CONTROL, MANDAUG, CALAPE, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱30.2M | 100% | Medium risk47 | —-0.078 |
| 437 | 22JC0055CONSTRUCTION OF MULTI-PURPOSE BUILDING IN LABASON, ZAMBOANGA DEL NORTE | Region IX | Zamboanga del Norte 3rd DEO | Completed | ₱4.9M | 100% | Medium risk47 | —-0.083 |
| 438 | 18HF0114CONSTRUCTION OF REVETMENT (RUBBLE CONCRETE) AT ALEGRIA-LANGOYON RIVER BASIN, STA. 4+757.50 -STA. 5+130, BRGY. ALEGRIA, TUBURAN, CEBU | Region VII | Cebu 3rd DEO | Completed | ₱37.2M | 100% | Medium risk47 | —-0.079 |
| 439 | 19HF0002CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT CARIDAD RIVER ALONG TOLEDO-TABUELAN-SAN REMEGIO ROAD, TUBURAN, CEBU | Region VII | Cebu 3rd DEO | Completed | ₱29.4M | 100% | Medium risk47 | —-0.078 |
| 440 | 20HF0067ROAD CONCRETING, BRGY. AWIHAO (SITIO MOHON) TO BRGY. BATO, TOLEDO CITY, CEBU | Region VII | Cebu 3rd DEO | Completed | ₱14.8M | 100% | Medium risk47 | —-0.096 |
| 441 | 20KF0056WIDENING OF PERMANENT BRIDGES AT SAGADAN BRIDGE (B00961MN) ALONG LINAMON-ZAMBOANGA ROAD, BAROY, LANAO DEL NORTE | Region X | Lanao del Norte 1st DEO | Completed | ₱36.3M | 100% | Medium risk47 | —-0.061 |
| 442 | 18HD0163CONSTRUCTION OF THREE-STOREY (12 CLASSROOM) SCHOOL BUILDING, JUAN PAMPLONA NATIONAL HIGH SCHOOL, TABUELAN, CEBU | Region VII | Cebu 4th DEO | Completed | ₱30.9M | 100% | Medium risk46 | —-0.046 |
| 443 | 23JD0028CONSTRUCTION OF WATER SYSTEM, POBLACION, SALUG, ZAMBOANGA DEL NORTE | Region IX | Zamboanga del Norte 3rd DEO | Completed | ₱5M | 100% | Medium risk46 | —-0.044 |
| 444 | 20KF0045WIDENING OF PERMANENT BRIDGES AT SEGAPOD BRIDGE (B00950MN) ALONG LINAMON-ZAMBOANGA ROAD, MAIGO, LANAO DEL NORTE | Region X | Lanao del Norte 1st DEO | Completed | ₱38.4M | 100% | Medium risk46 | —-0.060 |
| 445 | 20HF0026REHABILITATION OF ROAD, JAGBUAYA-SUMON, TUBURAN, CEBU | Region VII | Cebu 3rd DEO | Completed | ₱14.8M | 100% | Medium risk46 | —-0.097 |
| 446 | 18JC0071CONSTRUCTION OF ONE (1) UNIT TWO (2) STOREY FOUR (4) CLASSROOM REGULAR WORKSHOP W/ TOILET BUILDING AT JULIAN SORIANO MEMORIAL COMPREHENSIVE HIGH SCHOOL - SENIOR HIGH, SIOCON, ZAMBOANGA DEL NORTE | Region IX | Zamboanga del Norte 3rd DEO | Completed | ₱16.7M | 100% | Medium risk46 | —-0.031 |
| 447 | 18JC0072CONSTRUCTION OF ONE (1) UNIT TWO (2) STOREY FOUR (4) CLASSROOM WORKSHOP COMBINED W/ TOILET AT JULIAN SORIANO MEMORIAL COMPREHENSIVE HIGH SCHOOL - SENIOR HIGH, SIOCON, ZAMBOANGA DEL NORTE | Region IX | Zamboanga del Norte 3rd DEO | Completed | ₱16.9M | 100% | Medium risk46 | —-0.033 |
| 448 | 19HD0011OFF-CARRIAGEWAY IMPROVEMENT, TOLEDO-TABUELAN-SAN REMIGIO ROAD, K0106+000-K0107+000, TABUELAN, CEBU | Region VII | Cebu 4th DEO | Completed | ₱18M | 100% | Medium risk46 | —-0.097 |
| 449 | 20KF0105CONSTRUCTION OF MULTI-PURPOSE BUILDING (PNP PROVINCIAL HEADQUARTERS), BRGY. PIGCARANGAN, TUBOD, LANAO DEL NORTE | Region X | Lanao del Norte 1st DEO | Completed | ₱19.8M | 100% | Medium risk46 | —-0.093 |
| 450 | 17KF0034CONCRETING OF ROAD AT PRINCESA, BAROY, LANAO DEL NORTE, K 0+000-KO 0+700.00 | Region X | Lanao del Norte 1st DEO | Completed | ₱9.6M | 100% | Medium risk46 | —-0.066 |