Contractor dossier
16 projects on file, including joint ventures this contractor is part of.
Total projects
16
Total budget
₱815.7M
Average progress
97.9%
Completion rate
93.8%
Average risk score
51.5
Medium risk on average, out of 100
Flagged as unusual
1
6.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 16 | ₱815.7M | 51.5 | 1 | 97.9% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Bridges | 10 | ₱284.8M | 49.0 | 0 | 100.0% |
| Roads | 5 | ₱250.5M | 50.8 | 0 | 100.0% |
| OTHER | 1 | ₱280.4M | 79.1 | 1 | 66.2% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24D00070CONSTRUCTION OF BY-PASS AND DIVERSION ROADS TAGKAWAYAN-LABO DIVERSION ROAD, (TAGKAWAYAN SECTION), QUEZON | Region IV-A | Region IV-A | On-Going | ₱280.4M | 66% | High risk79 | Flagged0.030 |
| 23D00046CONSTRUCTION OF BY-PASS AND DIVERSION ROADSTAGKAWAYAN-LABO DIVERSION ROAD (TAGKAWAYAN SECTION), QUEZON | Region IV-A | Region IV-A | Completed | ₱95.1M | 100% | High risk64 | —-0.044 |
| 22D00075FY 2022 DPWH INFRASTRUCTURE PROGRAMORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMNETWORK DEVELOPMENT PROGRAMCONSTRUCTION OF BYPASS AND DIVERSION ROADS TAGKAWAYAN-LABO DIVERSION ROAD (TAGKAWAYAN SECTION), QUEZON | Region IV-A | Region IV-A | Completed | ₱98M | 100% | High risk60 | —-0.090 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24D00070CONSTRUCTION OF BY-PASS AND DIVERSION ROADS TAGKAWAYAN-LABO DIVERSION ROAD, (TAGKAWAYAN SECTION), QUEZON | Region IV-A | Region IV-A | On-Going | ₱280.4M | 66% | High risk79 | Flagged0.030 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 24D00070CONSTRUCTION OF BY-PASS AND DIVERSION ROADS TAGKAWAYAN-LABO DIVERSION ROAD, (TAGKAWAYAN SECTION), QUEZON | Region IV-A | Region IV-A | On-Going | ₱280.4M | 66% | High risk79 | Flagged0.030 |
| 2 | 23D00046CONSTRUCTION OF BY-PASS AND DIVERSION ROADSTAGKAWAYAN-LABO DIVERSION ROAD (TAGKAWAYAN SECTION), QUEZON | Region IV-A | Region IV-A | Completed | ₱95.1M | 100% | High risk64 | —-0.044 |
| 3 | 22D00075FY 2022 DPWH INFRASTRUCTURE PROGRAMORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMNETWORK DEVELOPMENT PROGRAMCONSTRUCTION OF BYPASS AND DIVERSION ROADS TAGKAWAYAN-LABO DIVERSION ROAD (TAGKAWAYAN SECTION), QUEZON | Region IV-A | Region IV-A | Completed | ₱98M | 100% | High risk60 | —-0.090 |
| 4 | 19DL0103A. ORGANIZATIONAL OUTCOME 1. ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM 2. NETWORK DEVELOPMENT PROGRAM A. CONSTRUCTION OF BY-PASS AND DIVERSION ROADS 5. LOPEZ BY-PASS ROAD, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱69.1M | 100% | Medium risk54 | —-0.098 |
| 5 | 19DL0095D. LOCAL PROGRAM 2. CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS A. LOCAL ROADS AND BRIDGES 1. LOCAL BRIDGE 2. CONSTRUCTION OF DANLAGAN BRIDGE AND APPROACHES, GUINAYANGAN, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱39.5M | 100% | Medium risk48 | —-0.063 |
| 6 | 19DL0160D. LOCAL PROGRAM 2. CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS A. LOCAL ROADS AND BRIDGES 1. LOCAL BRIDGE 3. CONSTRUCTION OF DUNGAWAN BRIDGE AND APPROACHES, GUINAYANGAN, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱45.6M | 100% | Medium risk48 | —-0.062 |
| 7 | 19DL0096D. LOCAL PROGRAM 2. CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS A. LOCAL ROADS AND BRIDGES 1. LOCAL BRIDGE 5. CONSTRUCTION OF MALITUKO BRIDGE AND APPROACHES ALONG BARANGAY HINABAAN, GUINAYANGAN, | Region IV-A | Quezon 4th DEO | Completed | ₱28.2M | 100% | Medium risk48 | —-0.064 |
| 8 | 22DC0001ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, BANAY-BANAY-MOJON-CUENCA RD. | Region IV-A | Batangas 3rd DEO | Completed | ₱44.1M | 100% | Medium risk47 | —-0.106 |
| 9 | 23DL0087CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES 8. CONSTRUCTION OF BRGY. TUNTON-MAGUIBUAY | Region IV-A | Quezon 4th DEO | Completed | ₱17.6M | 100% | Medium risk47 | —-0.065 |
| 10 | 22DL0117SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS ANDOR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS FACILITIES, CONSTRUCTION OF BRGY. TUNTON-MAGUIBUAY BRIDGE AND APPROACHES, TAGKAWAYAN, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱14.7M | 100% | Medium risk47 | —-0.063 |
| 11 | 22DL0116SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS FACILITIES, CONSTRUCTION OF BRGY. SINTONES-LIGPIT BANTAYAN BRIDGE AND APPROACHES, GUINAYANGAN, QU | Region IV-A | Quezon 4th DEO | Completed | ₱14.7M | 100% | Medium risk47 | —-0.064 |
| 12 | 22DL0115SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS ANDOR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS FACILITIES, CONSTRUCTION OF ALIJI-MAHINTA BRIDGE AND APPROACHES, TAGKAWAYAN, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱9.8M | 100% | Medium risk47 | —-0.064 |
| 13 | 22DL0114SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR / STRATEGIC PUBLIC BUILDINGS / FACILITIES, CONSTRUCTION OF ALIJI BRIDGE AND APPROACHES, TAGKAWAYAN, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱9.8M | 100% | Medium risk47 | —-0.064 |
| 14 | 22DL0118SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS ANDOR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS FACILITIES, CONSTRUCTION OF VILLA ESPINA BRIDGE AND APPROACHES, LOPEZ, QUEZON | Region IV-A | Quezon 4th DEO | Completed | ₱9.8M | 100% | Medium risk47 | —-0.062 |
| 15 | 24DL0124CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239, REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS ALONG QUIRINO H-WAY - K0262 + 088 - K0262 + 360, K0264 + 650 - K0264 + 800, | Region IV-A | Quezon 4th DEO | Completed | ₱30.2M | 100% | Medium risk47 | —-0.105 |
| 16 | 24DL0120ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, PREVENTIVE MAINTENANCE - PRIMARY ROADS 1. QUIRINO H-WAY - K0261 + 000 - K0261 + 250, K0262 + 050 - K0262 + 088 | Region IV-A | Quezon 4th DEO | Completed | ₱9.1M | 100% | Medium risk46 | —-0.107 |