Contractor dossier
89 projects on file, including joint ventures this contractor is part of.
Total projects
89
Total budget
₱2.6B
Average progress
93.9%
Completion rate
67.4%
Below 70%
Average risk score
43.0
Medium risk on average, out of 100
Flagged as unusual
3
3.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VI | 39 | ₱1B | 44.0 | 0 | 93.8% |
| Negros Island Region | 29 | ₱380.1M | 41.0 | 1 | 90.2% |
| Region XII | 19 | ₱919.5M | 41.7 | 2 | 99.3% |
| Region IV-B | 2 | ₱289.5M | 64.3 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 42 | ₱385.8M | 34.5 | 0 | 98.5% |
| Flood Control and Drainage | 19 | ₱1.4B | 48.0 | 0 | 91.0% |
| Roads | 19 | ₱353.3M | 43.4 | 0 | 87.3% |
| GAA 2025 OO-2 | 2 | ₱140.4M | 86.9 | 0 | 98.5% |
| OTHER | 2 | ₱75.3M | 72.1 | 1 | 72.6% |
| Water Provision and Storage | 2 | ₱14.6M | 43.3 | 0 | 100.0% |
| GAA 2025 OO-1 | 1 | ₱90.9M | 94.8 | 1 | 89.1% |
| GAA 2025 SSP | 1 | ₱86.8M | 92.4 | 1 | 100.0% |
| Bridges | 1 | ₱49M | 48.7 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25M00021CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS -MAHARLIKA HIGHWAY (MARBEL-MAKAR RD) - K1669 + 243 - K1670 + 000, POLOMOLOK, SOUTH COTABATO | Region XII | Region XII | On-Going | ₱90.9M | 89% | High risk95 | Flagged0.014 |
| 25MB0036CONSTRUCTION OF CONCRETE ROAD WITH DRAINAGE INCLUDING FACILITIES, DACERA AVENUE CONNECTING TO SILWAY 8-UPPER LABAY BYPASS ROAD, BARANGAY MABUHAY, GENERAL SANTOS CITY, SOUTH COTABATO | Region XII | South Cotabato 1st DEO | On-Going | ₱86.8M | 100% | High risk92 | Flagged0.021 |
| 25ME0026CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY LADOL, ALABEL, SARANGANI PROVINCE | Region XII | Sarangani DEO | On-Going | ₱93.6M | 97% | High risk91 | —-0.002 |
| 25M00044CONSTRUCTION OF CONCRETE REVETMENT, LOWER KINAN- MABUHAY-UPSTREAM OF LUNOK-MABUHAY BRIDGE, (SILWAY RIVER BASIN), STA 0+000 - STA 0+190, BARANGAY MABUHAY, GENERAL SANTOS CITY, SOUTH COTABATO | Region XII | Region XII | On-Going | ₱46.8M | 100% | High risk82 | —-0.015 |
| 25GL0080CONSTRUCTION OF NEGROS OCCIDENTAL 2ND DEO STAFF QUARTERS, BINALBAGAN, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | On-Going | ₱38.6M | 45% | High risk74 | Flagged0.000 |
| 24MB0075CONCRETING OF ROAD WITH DRAINAGE INCLUDING FACILITIES FROM JUNCTION ALBERT MORROW BLVD. TO SOUTH COTABATO SAN ISIDRO-MABUHAY BRIDGE, GENERAL SANTOS CITY | Region XII | South Cotabato 1st DEO | Completed | ₱36.7M | 100% | High risk70 | —-0.027 |
| 25HJ0140ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING ALONG PRIMARY ROAD-DUMAGUETE NORTH ROAD (JCT. BAIS-KABANKALAN-NEGROS OCC BDRY) K0122+869 - K0124+130, GUIHULNGAN CITY, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | On-Going | ₱57M | 31% | High risk70 | —-0.016 |
| 25GD0001CONSTRUCTION OF FLOOD MITIGATION STRUCTURES - CONSTRUCTION OF RIVER CONTROL ALONG PANAY RIVER, BARANGAY COGON, PANAY, CAPIZ | Region VI | Capiz 1st DEO | On-Going | ₱142.9M | 41% | High risk68 | —-0.008 |
| 24GD0007CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF RIVER CONTROL AT ZIBALA RIVER, BARANGAY POBLACION, PILAR, CAPIZ | Region VI | Capiz 1st DEO | On-Going | ₱94.3M | 96% | High risk65 | —-0.023 |
| 24E00174SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- CONST. OF TUBONG COASTAL ROAD (PHASE 1), BRGY. BONO-BONO SECTION, BATARAZA, PALAWAN | Region IV-B | Region IV-B | Completed | ₱144.7M | 100% | High risk64 | —-0.028 |
| 24E00205SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- CONST. OF TUBONG COASTAL ROAD (PHASE 2), BRGY. MARANGAS-BRGY. BONO-BONO SECTION, STA. 000+000-STA. 001+029.70, BATARAZA, PALAWAN | Region IV-B | Region IV-B | Completed | ₱144.7M | 100% | High risk64 | —-0.028 |
| 24GD0015CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF RIVER CONTROL ALONG PANAY RIVER AT BARANGAY COGON, PANAY, CAPIZ | Region VI | Capiz 1st DEO | On-Going | ₱92.5M | 100% | High risk62 | —-0.026 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25MB0036CONSTRUCTION OF CONCRETE ROAD WITH DRAINAGE INCLUDING FACILITIES, DACERA AVENUE CONNECTING TO SILWAY 8-UPPER LABAY BYPASS ROAD, BARANGAY MABUHAY, GENERAL SANTOS CITY, SOUTH COTABATO | Region XII | South Cotabato 1st DEO | On-Going | ₱86.8M | 100% | High risk92 | Flagged0.021 |
| 25M00021CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS -MAHARLIKA HIGHWAY (MARBEL-MAKAR RD) - K1669 + 243 - K1670 + 000, POLOMOLOK, SOUTH COTABATO | Region XII | Region XII | On-Going | ₱90.9M | 89% | High risk95 | Flagged0.014 |
| 25GL0080CONSTRUCTION OF NEGROS OCCIDENTAL 2ND DEO STAFF QUARTERS, BINALBAGAN, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | On-Going | ₱38.6M | 45% | High risk74 | Flagged0.000 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25M00021CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS -MAHARLIKA HIGHWAY (MARBEL-MAKAR RD) - K1669 + 243 - K1670 + 000, POLOMOLOK, SOUTH COTABATO | Region XII | Region XII | On-Going | ₱90.9M | 89% | High risk95 | Flagged0.014 |
| 2 | 25MB0036CONSTRUCTION OF CONCRETE ROAD WITH DRAINAGE INCLUDING FACILITIES, DACERA AVENUE CONNECTING TO SILWAY 8-UPPER LABAY BYPASS ROAD, BARANGAY MABUHAY, GENERAL SANTOS CITY, SOUTH COTABATO | Region XII | South Cotabato 1st DEO | On-Going | ₱86.8M | 100% | High risk92 | Flagged0.021 |
| 3 | 25ME0026CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY LADOL, ALABEL, SARANGANI PROVINCE | Region XII | Sarangani DEO | On-Going | ₱93.6M | 97% | High risk91 | —-0.002 |
| 4 | 25M00044CONSTRUCTION OF CONCRETE REVETMENT, LOWER KINAN- MABUHAY-UPSTREAM OF LUNOK-MABUHAY BRIDGE, (SILWAY RIVER BASIN), STA 0+000 - STA 0+190, BARANGAY MABUHAY, GENERAL SANTOS CITY, SOUTH COTABATO | Region XII | Region XII | On-Going | ₱46.8M | 100% | High risk82 | —-0.015 |
| 5 | 25GL0080CONSTRUCTION OF NEGROS OCCIDENTAL 2ND DEO STAFF QUARTERS, BINALBAGAN, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | On-Going | ₱38.6M | 45% | High risk74 | Flagged0.000 |
| 6 | 24MB0075CONCRETING OF ROAD WITH DRAINAGE INCLUDING FACILITIES FROM JUNCTION ALBERT MORROW BLVD. TO SOUTH COTABATO SAN ISIDRO-MABUHAY BRIDGE, GENERAL SANTOS CITY | Region XII | South Cotabato 1st DEO | Completed | ₱36.7M | 100% | High risk70 | —-0.027 |
| 7 | 25HJ0140ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING ALONG PRIMARY ROAD-DUMAGUETE NORTH ROAD (JCT. BAIS-KABANKALAN-NEGROS OCC BDRY) K0122+869 - K0124+130, GUIHULNGAN CITY, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | On-Going | ₱57M | 31% | High risk70 | —-0.016 |
| 8 | 25GD0001CONSTRUCTION OF FLOOD MITIGATION STRUCTURES - CONSTRUCTION OF RIVER CONTROL ALONG PANAY RIVER, BARANGAY COGON, PANAY, CAPIZ | Region VI | Capiz 1st DEO | On-Going | ₱142.9M | 41% | High risk68 | —-0.008 |
| 9 | 24GD0007CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF RIVER CONTROL AT ZIBALA RIVER, BARANGAY POBLACION, PILAR, CAPIZ | Region VI | Capiz 1st DEO | On-Going | ₱94.3M | 96% | High risk65 | —-0.023 |
| 10 | 24E00174SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- CONST. OF TUBONG COASTAL ROAD (PHASE 1), BRGY. BONO-BONO SECTION, BATARAZA, PALAWAN | Region IV-B | Region IV-B | Completed | ₱144.7M | 100% | High risk64 | —-0.028 |
| 11 | 24E00205SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- CONST. OF TUBONG COASTAL ROAD (PHASE 2), BRGY. MARANGAS-BRGY. BONO-BONO SECTION, STA. 000+000-STA. 001+029.70, BATARAZA, PALAWAN | Region IV-B | Region IV-B | Completed | ₱144.7M | 100% | High risk64 | —-0.028 |
| 12 | 24GD0015CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF RIVER CONTROL ALONG PANAY RIVER AT BARANGAY COGON, PANAY, CAPIZ | Region VI | Capiz 1st DEO | On-Going | ₱92.5M | 100% | High risk62 | —-0.026 |
| 13 | 23GD0025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD MITIGATING FACILITIES ALONG PANAY/MAMBUSAO RIVER BASIN, PANITAN RIVER CONTROL (DOWNSTREAM), PANITAN, CAPIZ | Region VI | Capiz 1st DEO | On-Going | ₱85.4M | 97% | Medium risk53 | —-0.014 |
| 14 | 25GD0002CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF CADIO FLOOD CONTROL STRUCTURES ALONG PANAY RIVER, BARANGAY CADIO, PANITAN, CAPIZ | Region VI | Capiz 1st DEO | On-Going | ₱57.2M | 89% | Medium risk53 | —-0.034 |
| 15 | 22GD0064BANK IMPROVEMENT OF PANAY/MAMBUSAO RIVER BASIN, PANITAN RIVER (DOWNSTREAM OF PANITAN BRIDGE I) PHASE II, PANITAN, CAPIZ | Region VI | Capiz 1st DEO | On-Going | ₱77.7M | 100% | Medium risk53 | —-0.015 |
| 16 | 21GD0069CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG PANAY/MAMBUSAO RIVER BASIN, PANITAN RIVER CONTROL (DOWNSTREAM OF PANITAN BRIDGE I), PANITAN, CAPIZ | Region VI | Capiz 1st DEO | Completed | ₱77.2M | 100% | Medium risk53 | —-0.066 |
| 17 | 22GD0028CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD MITAGATION FACILITIES ALONG PANAY/MAMBUSAO RIVER BASIN, TALASA RIVER CONTROL, BRGY. TALASA, PANAY, CAPIZ | Region VI | Capiz 1st DEO | Completed | ₱62.7M | 100% | Medium risk53 | —-0.068 |
| 18 | 22GD0010CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG PANAY/MAMBUSAO RIVER BASIN, PANITAN RIVER CONTROL (DOWNSTREAM), PANITAN, CAPIZ | Region VI | Capiz 1st DEO | Completed | ₱62.7M | 100% | Medium risk53 | —-0.068 |
| 19 | 25GD0005CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF RIVER CONTROL, ZIBALA RIVER, BARANGAY POBLACION, PILAR, CAPIZ | Region VI | Capiz 1st DEO | On-Going | ₱48.3M | 5% | Medium risk50 | —-0.013 |
| 20 | 24HJ0076NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - DUMAGUETE NORTH RD (JCT BAIS - KABANKALAN - NEGROS OCC BDRY) - K0116+689-K0118+400, GUIHULNGAN CITY, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | On-Going | ₱49.7M | 92% | Medium risk49 | —-0.055 |
| 21 | 23HJ0058ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES TAMPOCON BR. (B00511NR) ALONG DUMAGUETE NORTH RD (JCT BAIS-KABANKALAN-NEGROS OCC BDRY), AYUNGON, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱49M | 100% | Medium risk49 | —-0.044 |
| 22 | 23GD0024CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MALAG-IT, PONTEVEDRA, CAPIZ | Region VI | Capiz 1st DEO | On-Going | ₱4.9M | 100% | Medium risk48 | —-0.038 |
| 23 | 24GL0024CONSTRUCTION OF MULTI-PURPOSE BUILDING, DPWH BUILDING, NEGROS OCCIDENTAL 2ND DEO, BINALBAGAN, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱39.2M | 100% | Medium risk48 | —-0.080 |
| 24 | 21GD0099CONSTRUCTION OF MULTI-PURPOSE BUILDING - CONSTRUCTION OF MULTI-PURPOSE BUILDING/ MUNICIPAL BUILDING (ANNEX), BRGY. POBLACION, PRESIDENT ROXAS, CAPIZ | Region VI | Capiz 1st DEO | Completed | ₱9.9M | 100% | Medium risk48 | —-0.083 |
| 25 | 20GD0052CONSTRUCTION (COMPLETION) OF CAPIZ 1ST DISTRICT ENGINEERING OFFICE PLANNING AND CONSTRUCTION BUILDING, ROXAS CITY, CAPIZ | Region VI | Capiz 1st DEO | Completed | ₱10M | 100% | Medium risk48 | —-0.083 |