Contractor dossier
22 projects on file, including joint ventures this contractor is part of.
Total projects
22
Total budget
₱1.5B
Average progress
85.2%
Completion rate
63.6%
Below 70%
Average risk score
54.9
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 20 | ₱1.1B | 53.9 | 0 | 83.7% |
| Region IV-B | 2 | ₱337.4M | 64.7 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 16 | ₱922.7M | 52.8 | 0 | 81.2% |
| Flood Control and Drainage | 4 | ₱403.4M | 63.1 | 0 | 98.0% |
| OTHER | 1 | ₱91.7M | 62.2 | 0 | 83.3% |
| Bridges | 1 | ₱45.7M | 48.2 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23DQ0158CONSTRUCTION/REHABILITATION OF ROAD WITH DRAINAGE, BRGY. BILUSO, SILANG, CAVITE | Region IV-A | Cavite 3rd DEO | Completed | ₱95.5M | 100% | High risk73 | —-0.006 |
| 23DQ0160CONSTRUCTION OF SLOPE AND FLOOD PROTECTION STRUCTURE ALONG CARMONA RIVER, PHASE 2, CARMONA, CAVITE | Region IV-A | Cavite 3rd DEO | Completed | ₱33.6M | 100% | High risk68 | —-0.055 |
| 23E00152SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF FLOOD CONTROL STRUCTURE ALONG NAGAPI RIVER, MALPALON SECTION, OCC. MINDORO | Region IV-B | Region IV-B | Completed | ₱193M | 100% | High risk67 | —-0.042 |
| 23D00159CONSTRUCTION OF REVETMENT ALONG RIO GRANDE RIVER, BRGY. SANTIAGO, GENERAL TRIAS CITY, CAVITE | Region IV-A | Region IV-A | On-Going | ₱99.6M | 92% | High risk65 | —-0.024 |
| 23DQ0103CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD FROM PALIGAWAN MA | Region IV-A | Cavite 3rd DEO | On-Going | ₱91.7M | 83% | High risk62 | —-0.009 |
| 19E00003CONST. OF MISSING LINK/NEW ROADS, MINDORO ISLAND CIRCUMFERENTIAL ROAD (PUERTO GALERA - ABRA DE ILOG), KO453+438.00 - KO454+893.00, OCC. MINDORO | Region IV-B | Region IV-B | Completed | ₱144.4M | 100% | High risk62 | —-0.057 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 23DQ0158CONSTRUCTION/REHABILITATION OF ROAD WITH DRAINAGE, BRGY. BILUSO, SILANG, CAVITE | Region IV-A | Cavite 3rd DEO | Completed | ₱95.5M | 100% | High risk73 | —-0.006 |
| 2 | 23DQ0160CONSTRUCTION OF SLOPE AND FLOOD PROTECTION STRUCTURE ALONG CARMONA RIVER, PHASE 2, CARMONA, CAVITE | Region IV-A | Cavite 3rd DEO | Completed | ₱33.6M | 100% | High risk68 | —-0.055 |
| 3 | 23E00152SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF FLOOD CONTROL STRUCTURE ALONG NAGAPI RIVER, MALPALON SECTION, OCC. MINDORO | Region IV-B | Region IV-B | Completed | ₱193M | 100% | High risk67 | —-0.042 |
| 4 | 23D00159CONSTRUCTION OF REVETMENT ALONG RIO GRANDE RIVER, BRGY. SANTIAGO, GENERAL TRIAS CITY, CAVITE | Region IV-A | Region IV-A | On-Going | ₱99.6M | 92% | High risk65 | —-0.024 |
| 5 | 23DQ0103CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD FROM PALIGAWAN MA | Region IV-A | Cavite 3rd DEO | On-Going | ₱91.7M | 83% | High risk62 | —-0.009 |
| 6 | 19E00003CONST. OF MISSING LINK/NEW ROADS, MINDORO ISLAND CIRCUMFERENTIAL ROAD (PUERTO GALERA - ABRA DE ILOG), KO453+438.00 - KO454+893.00, OCC. MINDORO | Region IV-B | Region IV-B | Completed | ₱144.4M | 100% | High risk62 | —-0.057 |
| 7 | 25DQ0076CONSTRUCTION OF ROAD LEADING TO THE NEW CARMONA CITY HALL, CARMONA CITY, CAVITE | Region IV-A | Cavite 3rd DEO | On-Going | ₱89.6M | 24% | Medium risk57 | —-0.046 |
| 8 | 23D00036CONSTRUCTION OF DASMARIÑAS - GENERAL MARIANO ALVAREZ - CARMONA BYPASS ROAD, CARMONA, CAVITE | Region IV-A | Region IV-A | On-Going | ₱56.7M | 0% | Medium risk54 | —-0.028 |
| 9 | 24D00090CONSTRUCTION OF CARMONA - BIÑAN EXTENSION ROAD, CAVITE | Region IV-A | Region IV-A | On-Going | ₱56.5M | 65% | Medium risk54 | —-0.055 |
| 10 | 24DQ0013PREVENTIVE MAINTENANCE - SECONDARY ROADS - CARMONA DIV RD - K0048 + 153.30 - K0048 + 462 AND ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE PRIMARY ROADS - JUANITO R. REMUL | Region IV-A | Cavite 3rd DEO | On-Going | ₱59.7M | 100% | Medium risk54 | —-0.064 |
| 11 | 23DQ0003PREVENTIVE MAINTENANCE SECONDARY ROADS - CARMONA DIV RD - K0047 + (-774) - K0047 + (-744), K0047 + (-804) - K0047 + (-774), K0047 + 528 - K0048 + 156 AND STA ROSA-ULAT-TAGAYTAY RD - K0061 + (-020) - K0062 + 479, K0063 + 196 - K0063 + 801, K0063+ 931 - K | Region IV-A | Cavite 3rd DEO | Completed | ₱82.2M | 100% | Medium risk54 | —-0.101 |
| 12 | 20DQ0028ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SLOPE PROTECTION ALONG CARMONA RIVER, PHASE IV, WEST S | Region IV-A | Cavite 3rd DEO | Completed | ₱77.2M | 100% | Medium risk53 | —-0.080 |
| 13 | 23D00127CONSTRUCTION OF BY-PASS AND DIVERSION ROADSCARMONA-BIÑAN DIVERSION ROAD, CARMONA, CAVITE | Region IV-A | Region IV-A | On-Going | ₱52M | 100% | Medium risk52 | —-0.062 |
| 14 | 23DQ0010ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - JUANITO R. REMULLA, SR. RD - K0044 + 271 - K0045 + 370 | Region IV-A | Cavite 3rd DEO | Completed | ₱49.2M | 100% | Medium risk51 | —-0.099 |
| 15 | 21DQ0036ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED-PAVED ROADS - SECONDARY ROADS - CAVITE - BATANGAS RD. - K0045 + (-200) - K0045 + 500, K0046 + 000 - | Region IV-A | Cavite 3rd DEO | Completed | ₱49M | 100% | Medium risk51 | —-0.102 |
| 16 | 19D00032ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF MISSING LINKS / NEW ROADS GENERAL AGUINALDO-MAGALLANES- NASUGBU ROAD (EAST-WEST ROAD), SILANG SECTION, CAVITE | Region IV-A | Region IV-A | Completed | ₱45.7M | 100% | Medium risk48 | —-0.051 |
| 17 | 25DQ0046CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CARMONA-SILANG DIVERSION ROAD (VIA SUGAR ROAD-DAVILAN-MAGUYAM ROAD), CAVITE | Region IV-A | Cavite 3rd DEO | On-Going | ₱42.7M | 10% | Medium risk48 | —-0.044 |
| 18 | 22D00030CONSTRUCTION OF DASMARIÑAS - GENERAL MARIANO ALVAREZ - CARMONA BYPASS ROAD, CARMONA, CAVITE | Region IV-A | Region IV-A | Completed | ₱43.8M | 100% | Medium risk48 | —-0.092 |
| 19 | 23DQ0009REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - CAVITE-BATANGAS RD - K0039 + 864 - K0040 + 258 | Region IV-A | Cavite 3rd DEO | Completed | ₱39M | 100% | Medium risk48 | —-0.107 |
| 20 | 20DQ0054ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - TERTIARY ROADS - SILANG BY-PASS RD - K0042 + (-097) - K0042 + 847, K0042 + (- | Region IV-A | Cavite 3rd DEO | Completed | ₱28.5M | 100% | Medium risk47 | —-0.108 |
| 21 | 20DQ0024ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - JUANITO R. REMULLA, SR. RD - K0045 + 493 - K0045 + 922.5 | Region IV-A | Cavite 3rd DEO | Completed | ₱16.3M | 100% | Medium risk47 | —-0.106 |
| 22 | 20DK0001ASSET PRESERVATION MAINTENANCE-SECONDARY ROADS LUCENA-TAYABAS-LUCBAN-SAMPALOC-MAUBAN PORT ROAD, K0131+915-K0132+330 | Region IV-A | Quezon 1st DEO | Completed | ₱17.6M | 100% | Medium risk46 | —-0.106 |