Contractor dossier
30 projects on file, including joint ventures this contractor is part of.
Total projects
30
Total budget
₱2.4B
Average progress
95.8%
Completion rate
73.3%
Average risk score
53.0
Medium risk on average, out of 100
Flagged as unusual
2
6.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-B | 13 | ₱1.2B | 47.7 | 1 | 97.5% |
| Region IV-A | 11 | ₱743.6M | 57.5 | 0 | 100.0% |
| Region VI | 2 | ₱252.2M | 68.8 | 1 | 53.2% |
| Cordillera Administrative Region | 2 | ₱186.2M | 55.0 | 0 | 100.0% |
| Region I | 2 | ₱62M | 45.9 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 10 | ₱966.8M | 50.2 | 2 | 88.1% |
| Roads | 9 | ₱736.3M | 53.4 | 0 | 99.2% |
| Buildings and Facilities | 6 | ₱395.9M | 53.3 | 0 | 100.0% |
| OTHER | 2 | ₱48.2M | 68.4 | 0 | 100.0% |
| Bridges | 2 | ₱58.6M | 41.7 | 0 | 100.0% |
| Bridges, Roads | 1 | ₱196.4M | 68.2 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 17G00003REHAB./RECONST./UPGRADING OF ILOILO-ANTIQUE ROAD, K0015+870 - K0016+409, K0020+190 - K0020+767, K002 | Region VI | Region VI | Completed | ₱110.4M | 100% | High risk71 | —-0.037 |
| 22DF0214CONVERGENCE AND SPECIAL SUPPORT PROGRAMSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIESCONSTRUCTION OF WAWA-JULUGAN BRID | Region IV-A | Cavite 1st DEO | Terminated | ₱33.6M | 100% | High risk69 | —-0.014 |
| 20D00052FY 2020 DPWH INFRA. PROGRAM ORGANIZATIONAL OUTCOME 1:ENSURE SAFE 7 RELIABLE NAT'L. ROAD SYSTEM, NETWORK DEV'T. PROGRAM CONSTRUCTION OF MISSING LINKS / NEW ROADS GENERAL AGUINALDO-MAGALLANES-NASUGBU ROAD (EAST-WEST ROAD), INDANG SECTION, PACKAGE A, CAVITE | Region IV-A | Region IV-A | Terminated | ₱196.4M | 100% | High risk68 | —-0.018 |
| 21DF0167LOCAL PROGRAMLOCAL INFRASTRUCTURE PROGRAMLOCAL ROADS AND BRIDGESLOCAL ROADSCONSTRUCTION OF LOCAL ROAD, BARANGAY JULUGAN I, BANGKEROHAN TO ROSARIO, TANZA, CAVITE | Region IV-A | Cavite 1st DEO | Terminated | ₱14.6M | 100% | High risk68 | —-0.013 |
| 24E00005BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF BUENAVISTA SHORE PROTECTION, BUENAVISTA, MARINDUQUE | Region IV-B | Region IV-B | On-Going | ₱238.9M | 87% | High risk67 | —-0.000 |
| 22G00056REHABILITATION OF DRAINAGE SYSTEM, CITY PROPER, SILAY CITY, NEGROS OCCIDENTAL | Region VI | Region VI | On-Going | ₱141.9M | 6% | High risk67 | Flagged0.029 |
| 24E00003FLOOD MANAGEMENT PROGRAM- CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONST. OF GASAN SHORE PROTECTION/BOULEVARD, GASAN, MARINDUQUE | Region IV-B | Region IV-B | On-Going | ₱241.2M | 87% | High risk66 | Flagged0.000 |
| 17P00042NETWORK DEVELOPMENT - OFF CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE, BANAUE - MAYOYAO - A. LISTA - ISABELA BDRY ROAD, K0426+092 - K0429+547, K0429+609 - K0441+187 | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱141.2M | 100% | High risk64 | —-0.030 |
| 18D00082CONSTRUCTION OF AGRONOMY, SOILS AND HORTICULTURE BUILDING CROP PROTECTIONWING, UP LOS BAÑOS | Region IV-A | Region IV-A | Completed | ₱98.5M | 100% | High risk61 | —-0.019 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 22G00056REHABILITATION OF DRAINAGE SYSTEM, CITY PROPER, SILAY CITY, NEGROS OCCIDENTAL | Region VI | Region VI | On-Going | ₱141.9M | 6% | High risk67 | Flagged0.029 |
| 24E00003FLOOD MANAGEMENT PROGRAM- CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONST. OF GASAN SHORE PROTECTION/BOULEVARD, GASAN, MARINDUQUE | Region IV-B | Region IV-B | On-Going | ₱241.2M | 87% | High risk66 | Flagged0.000 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 17G00003REHAB./RECONST./UPGRADING OF ILOILO-ANTIQUE ROAD, K0015+870 - K0016+409, K0020+190 - K0020+767, K002 | Region VI | Region VI | Completed | ₱110.4M | 100% | High risk71 | —-0.037 |
| 2 | 22DF0214CONVERGENCE AND SPECIAL SUPPORT PROGRAMSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIESCONSTRUCTION OF WAWA-JULUGAN BRID | Region IV-A | Cavite 1st DEO | Terminated | ₱33.6M | 100% | High risk69 | —-0.014 |
| 3 | 20D00052FY 2020 DPWH INFRA. PROGRAM ORGANIZATIONAL OUTCOME 1:ENSURE SAFE 7 RELIABLE NAT'L. ROAD SYSTEM, NETWORK DEV'T. PROGRAM CONSTRUCTION OF MISSING LINKS / NEW ROADS GENERAL AGUINALDO-MAGALLANES-NASUGBU ROAD (EAST-WEST ROAD), INDANG SECTION, PACKAGE A, CAVITE | Region IV-A | Region IV-A | Terminated | ₱196.4M | 100% | High risk68 | —-0.018 |
| 4 | 21DF0167LOCAL PROGRAMLOCAL INFRASTRUCTURE PROGRAMLOCAL ROADS AND BRIDGESLOCAL ROADSCONSTRUCTION OF LOCAL ROAD, BARANGAY JULUGAN I, BANGKEROHAN TO ROSARIO, TANZA, CAVITE | Region IV-A | Cavite 1st DEO | Terminated | ₱14.6M | 100% | High risk68 | —-0.013 |
| 5 | 24E00005BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF BUENAVISTA SHORE PROTECTION, BUENAVISTA, MARINDUQUE | Region IV-B | Region IV-B | On-Going | ₱238.9M | 87% | High risk67 | —-0.000 |
| 6 | 22G00056REHABILITATION OF DRAINAGE SYSTEM, CITY PROPER, SILAY CITY, NEGROS OCCIDENTAL | Region VI | Region VI | On-Going | ₱141.9M | 6% | High risk67 | Flagged0.029 |
| 7 | 24E00003FLOOD MANAGEMENT PROGRAM- CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONST. OF GASAN SHORE PROTECTION/BOULEVARD, GASAN, MARINDUQUE | Region IV-B | Region IV-B | On-Going | ₱241.2M | 87% | High risk66 | Flagged0.000 |
| 8 | 17P00042NETWORK DEVELOPMENT - OFF CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE, BANAUE - MAYOYAO - A. LISTA - ISABELA BDRY ROAD, K0426+092 - K0429+547, K0429+609 - K0441+187 | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱141.2M | 100% | High risk64 | —-0.030 |
| 9 | 18D00082CONSTRUCTION OF AGRONOMY, SOILS AND HORTICULTURE BUILDING CROP PROTECTIONWING, UP LOS BAÑOS | Region IV-A | Region IV-A | Completed | ₱98.5M | 100% | High risk61 | —-0.019 |
| 10 | 18EA0216CONSTRUCTION OF FOUR (4) STOREY, 28 CLASSROOM SCHOOL BUILDING AT MARINDUQUE NATIONAL HIGH SCHOOL | Region IV-B | Marinduque DEO | Completed | ₱94.8M | 100% | Medium risk54 | —-0.013 |
| 11 | 20DF0123LOCAL PROGRAM-CONSTRUCTION/ REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, LOCAL ROADS AND BRIDGES, LOCAL ROADS REHABILITATION OF CONCHU RD., AMADEO SECTION, PHASE 2, STA. 7+200 - STA. 9+600, AMADEO, CAVITE | Region IV-A | Cavite 1st DEO | Completed | ₱59.8M | 100% | Medium risk54 | —-0.104 |
| 12 | 20DF0124LOCAL PROGRAM - CONSTRUCTION/ REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, LOCAL ROADS AND BRIDGES, LOCAL ROADS REHABILITATION OF CONCHU RD., TRECE STATION, PHASE 1, STA. 0+000 - STA., AMADEO, CAVITE | Region IV-A | Cavite 1st DEO | Completed | ₱59.8M | 100% | Medium risk54 | —-0.103 |
| 13 | 19D00041PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS FLOOD MANAGEMENT PROGRAM CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION / IMPROVEMENT OF SAN PEDRO RIVER CONTROL, BRGY. CALENDOLA, SAN PEDRO, LAGUNA | Region IV-A | Region IV-A | Completed | ₱78.2M | 100% | Medium risk53 | —-0.078 |
| 14 | 22EA0144CONSTRUCTION OF BALOGO-KILO-KILO ROAD, STA. CRUZ, MARINDUQUE, (PHASE 4) | Region IV-B | Marinduque DEO | Completed | ₱96.7M | 100% | Medium risk53 | —-0.078 |
| 15 | 19DQ0123CONSTRUCTION OF 4STY20CL, LALAAN CS, SILANG, CAVITE | Region IV-A | Region IV-A | Completed | ₱54.7M | 100% | Medium risk52 | —-0.040 |
| 16 | 19DQ0122CONSTRUCTION OF 4STY20CL, SILANG WEST ES, SILANG, CAVITE | Region IV-A | Region IV-A | Completed | ₱53.3M | 100% | Medium risk52 | —-0.042 |
| 17 | 18DQ0123CONSTRUCTION OF FOUR (4) STOREY TWENTY (20) CLASSROOMS SCHOOL BUILDING AT SILANG CENTRAL SCHOOL, SILANG, CAVITE | Region IV-A | Region IV-A | Completed | ₱53.9M | 100% | Medium risk52 | —-0.046 |
| 18 | 24EA0026REHABILITATION OF IHATUB - MANSIWAT - ISOK ROAD, BOAC, MARINDUQUE | Region IV-B | Marinduque DEO | On-Going | ₱91.1M | 92% | Medium risk49 | —-0.049 |
| 19 | 18DQ0121CONSTRUCTION OF FOUR (4) STOREY TWELVE (12) CLASSROOM SCHOOL BUILDING AT SILANG WEST ELEMENTARY SCHOOL, SILANG, CAVITE | Region IV-A | Region IV-A | Completed | ₱40.7M | 100% | Medium risk49 | —-0.051 |
| 20 | 19AH0264REHAB./REPAIR OF AGNO RIVER BASIN F/C PROJ.ALONG BRGY. GUESET BUGALLON,PANG.STA.0+000-STA.0+478 | Region I | Pangasinan 2nd DEO | Completed | ₱37M | 100% | Medium risk47 | —-0.009 |
| 21 | 21EA0086CONSTRUCTION OF TALAWAN-SABONG ROAD, TORRIJOS/BOAC, MARINDUQUE | Region IV-B | Marinduque DEO | Completed | ₱72.8M | 100% | Medium risk47 | —-0.084 |
| 22 | 19EA0018NETWORK DEVELOPMENT-ROAD WIDENING-SECONDARY ROADS, MARINDUQUE CIRCUMFERENTIAL ROAD-K0054+000-K0055+833 | Region IV-B | Marinduque DEO | Completed | ₱55.4M | 100% | Medium risk46 | —-0.085 |
| 23 | 18PD0031BRIDGE: WIDENING OF PERMANENT BRIDGES-KENNON BR. 2 (B00919LZ) ALONG KENNON RD. INCL. ROW | Cordillera Administrative Region | Baguio City DEO | Completed | ₱45M | 100% | Medium risk46 | —-0.042 |
| 24 | 22EA0086CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF TAWIRAN FLOOD CONTROL, STA. 0+000 - STA. 0+900, STA. CRUZ, MARINDUQUE | Region IV-B | Marinduque DEO | Completed | ₱84.9M | 100% | Medium risk46 | —-0.058 |
| 25 | 18AH0114CONSTRUCTION OF RIVERBANK PROJ.,AGNO RIVER BASIN FLOOD CONTROL PROJ.BRGY.BAYAOAS AND BUER,AGUILAR,PA | Region I | Pangasinan 2nd DEO | Completed | ₱25M | 100% | Medium risk45 | —-0.072 |