Contractor dossier
6 projects on file, including joint ventures this contractor is part of.
Total projects
6
Total budget
₱205.4M
Average progress
85.0%
Completion rate
66.7%
Below 70%
Average risk score
53.7
Medium risk on average, out of 100
Flagged as unusual
1
16.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 4 | ₱145M | 53.3 | 1 | 77.5% |
| Region V | 2 | ₱60.4M | 54.7 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 3 | ₱93.2M | 49.5 | 0 | 100.0% |
| Roads | 2 | ₱64.3M | 51.5 | 0 | 78.5% |
| OTHER | 1 | ₱47.9M | 70.9 | 1 | 52.9% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24DI0068CONSTRUCTION OF ROAD AND DRAINAGE ALONG ESPLANADE ROAD, BARANGAY DELA PAZ, BINAN CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱47.9M | 53% | High risk71 | Flagged0.005 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24DI0068CONSTRUCTION OF ROAD AND DRAINAGE ALONG ESPLANADE ROAD, BARANGAY DELA PAZ, BINAN CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱47.9M | 53% | High risk71 | Flagged0.005 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 24DI0068CONSTRUCTION OF ROAD AND DRAINAGE ALONG ESPLANADE ROAD, BARANGAY DELA PAZ, BINAN CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱47.9M | 53% | High risk71 | Flagged0.005 |
| 2 | 18FE0042CONSTRUCTION OF MULTI PURPOSE BUILDING MOTORPOOL AND IMPROVEMENT OF DPWH CAMARINES SUR 2ND DISTRICT ENGINEERING OFFICE BUILDING AND COMPOUND | Region V | Camarines Sur 3rd DEO | Completed | ₱44M | 100% | Medium risk58 | —-0.093 |
| 3 | 18FE0031ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM ASSET PRESERVATION PROGRAM CONSTRUCTION/ UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS PRIMARY ROADS DAANG MAHARLIKA (LZ) KO454 +674- KO455 + 013 | Region V | Camarines Sur 3rd DEO | Completed | ₱16.5M | 100% | Medium risk52 | —-0.100 |
| 4 | 24DI0031CONSTRUCTION OF ROAD AND DRAINAGE ALONG CASILE-MALABAN ROAD, BINAN CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱47.8M | 57% | Medium risk51 | —-0.052 |
| 5 | 18DI0158CONSTRUCTION OF 4 STOREY 8 CLASSROOMS AT JACOBO Z. GONZALES MEMORIAL NATIONAL HIGH SCHOOL, BIÑAN CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱24.3M | 100% | Medium risk46 | —-0.054 |
| 6 | 18DI0157CONSTRUCTION OF 4 STOREY 8 CLASSROOMS AT JACOBO Z. GONZALES MEMORIAL NATIONAL HIGH SCHOOL, BIÑAN CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱24.9M | 100% | Medium risk45 | —-0.056 |