Contractor dossier
26 projects on file, including joint ventures this contractor is part of.
Total projects
26
Total budget
₱1.5B
Average progress
78.2%
Completion rate
42.3%
Below 70%
Average risk score
56.2
Medium risk on average, out of 100
Flagged as unusual
10
38.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Cordillera Administrative Region | 25 | ₱1.4B | 56.3 | 10 | 81.3% |
| National Capital Region | 1 | ₱80.2M | 52.7 | 0 | 0.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 6 | ₱273M | 51.2 | 3 | 74.1% |
| Flood Control and Drainage | 5 | ₱299.3M | 51.9 | 0 | 80.0% |
| OTHER | 4 | ₱250.6M | 84.8 | 4 | 59.1% |
| Roads | 4 | ₱407.7M | 45.3 | 1 | 87.8% |
| Water Provision and Storage | 3 | ₱9.7M | 29.7 | 0 | 100.0% |
| Bridges | 2 | ₱77.3M | 48.9 | 0 | 91.0% |
| GAA 2025 OO-1 | 1 | ₱65.2M | 93.6 | 1 | 50.8% |
| GAA 2025 OO-2 | 1 | ₱96.5M | 92.3 | 1 | 66.6% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25PE0049RECONSTRUCTION TO CONCRETE PAVEMENT - BAGUIO-BONTOC RD (S00367LZ) - K0254+279-K0255+250, LA TRINIDAD, BENGUET | Cordillera Administrative Region | Benguet 1st DEO | On-Going | ₱65.2M | 51% | High risk94 | Flagged0.007 |
| 25PE0005CONSTRUCTION OF FLOOD MITIGATION STRUCTURE WITHIN AGNO RIVER BASIN: ALONG AGNO RIVER, SECTION 11 (AMBALANGA RIVER SECTION), ITOGON, BENGUET | Cordillera Administrative Region | Benguet 1st DEO | On-Going | ₱96.5M | 67% | High risk92 | Flagged0.006 |
| 25PE0064CONSTRUCTION OF SCHOOL BUILDING, TUBA CENTRAL NATIONAL HIGH SCHOOL, BARANGAY POBLACION, TUBA, BENGUET | Cordillera Administrative Region | Benguet 1st DEO | On-Going | ₱19.9M | 2% | High risk88 | Flagged0.072 |
| 24PF0078CONSTRUCTION OF 4-STOREY 8-CLASSROOM SCHOOL BUILDING IN LOO NATIONAL HIGH SCHOOL, BARANGAY, LOO, BUGUIAS, BENGUET | Cordillera Administrative Region | Benguet 2nd DEO | On-Going | ₱39.8M | 80% | High risk87 | Flagged0.051 |
| 24PF0079CONSTRUCTION OF 3-STOREY 15-CLASSROOM AT FRANKLIN GUY HAIGHT NATIONAL HIGHSCHOOL, ATOK, BENGUET | Cordillera Administrative Region | Benguet 2nd DEO | On-Going | ₱43.3M | 90% | High risk86 | Flagged0.052 |
| 24P00014CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL ALONG AGNO RIVER, SITIO BANAO AND SITIO ADONOT, BARANGAY AMBUKLAO, BOKOD, BENGUET | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱147.6M | 65% | High risk78 | Flagged0.028 |
| 21PA0221CONSTRUCTION OF PULOT-KIWAS FLOOD CONTROL, LAGAYAN, ABRA | Cordillera Administrative Region | Abra DEO | Completed | ₱96.5M | 100% | High risk63 | —-0.053 |
| 24PF0086CONSTRUCTION OF PROPER GADANG-LAO-ANGAN ROAD, KAPANGAN, BENGUET | Cordillera Administrative Region | Benguet 2nd DEO | On-Going | ₱95.4M | 51% | High risk61 | Flagged0.023 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25PE0064CONSTRUCTION OF SCHOOL BUILDING, TUBA CENTRAL NATIONAL HIGH SCHOOL, BARANGAY POBLACION, TUBA, BENGUET | Cordillera Administrative Region | Benguet 1st DEO | On-Going | ₱19.9M | 2% | High risk88 | Flagged0.072 |
| 24PF0079CONSTRUCTION OF 3-STOREY 15-CLASSROOM AT FRANKLIN GUY HAIGHT NATIONAL HIGHSCHOOL, ATOK, BENGUET | Cordillera Administrative Region | Benguet 2nd DEO | On-Going | ₱43.3M | 90% | High risk86 | Flagged0.052 |
| 24PF0078CONSTRUCTION OF 4-STOREY 8-CLASSROOM SCHOOL BUILDING IN LOO NATIONAL HIGH SCHOOL, BARANGAY, LOO, BUGUIAS, BENGUET | Cordillera Administrative Region | Benguet 2nd DEO | On-Going | ₱39.8M | 80% | High risk87 | Flagged0.051 |
| 24P00014CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL ALONG AGNO RIVER, SITIO BANAO AND SITIO ADONOT, BARANGAY AMBUKLAO, BOKOD, BENGUET | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱147.6M | 65% | High risk78 | Flagged0.028 |
| 24PF0086CONSTRUCTION OF PROPER GADANG-LAO-ANGAN ROAD, KAPANGAN, BENGUET | Cordillera Administrative Region | Benguet 2nd DEO | On-Going | ₱95.4M | 51% | High risk61 | Flagged0.023 |
| 24PF0077CONSTRUCTION OF 3 STOREY 15 CLASSROOM SCHOOL BUILDING IN GOV. BADO DANGWA AGRO INDUSTRIAL SCHOOL, KAPANGAN, BENGUET | Cordillera Administrative Region | Benguet 2nd DEO | On-Going | ₱39.8M | 56% | Medium risk47 | Flagged0.018 |
| 23PE0050CONSTRUCTION OF 4STY10CL WITH SCIENCE LABORATORY, AMBIONG NATIONAL HIGH SCHOOL, LA TRINIDAD, BENGUET | Cordillera Administrative Region | Benguet 1st DEO | On-Going | ₱47.1M | 89% | Medium risk51 | Flagged0.013 |
| 25PE0049RECONSTRUCTION TO CONCRETE PAVEMENT - BAGUIO-BONTOC RD (S00367LZ) - K0254+279-K0255+250, LA TRINIDAD, BENGUET | Cordillera Administrative Region | Benguet 1st DEO | On-Going | ₱65.2M | 51% | High risk94 | Flagged0.007 |
| 25PE0005CONSTRUCTION OF FLOOD MITIGATION STRUCTURE WITHIN AGNO RIVER BASIN: ALONG AGNO RIVER, SECTION 11 (AMBALANGA RIVER SECTION), ITOGON, BENGUET | Cordillera Administrative Region | Benguet 1st DEO | On-Going | ₱96.5M | 67% | High risk92 | Flagged0.006 |
| 24PE0077CONSTRUCTION OF 3-STOREY 13-CLASSROOM SCHOOL BUILDING WITH SCIENCE LABORATORY ROOM IN AMBANGEG NATIONAL HIGH SCHOOL, BARANGAY DAKLAN, BOKOD, BENGUET | Cordillera Administrative Region | Benguet 1st DEO | On-Going | ₱39.8M | 89% | Medium risk49 | Flagged0.005 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25PE0049RECONSTRUCTION TO CONCRETE PAVEMENT - BAGUIO-BONTOC RD (S00367LZ) - K0254+279-K0255+250, LA TRINIDAD, BENGUET | Cordillera Administrative Region | Benguet 1st DEO | On-Going | ₱65.2M | 51% | High risk94 | Flagged0.007 |
| 2 | 25PE0005CONSTRUCTION OF FLOOD MITIGATION STRUCTURE WITHIN AGNO RIVER BASIN: ALONG AGNO RIVER, SECTION 11 (AMBALANGA RIVER SECTION), ITOGON, BENGUET | Cordillera Administrative Region | Benguet 1st DEO | On-Going | ₱96.5M | 67% | High risk92 | Flagged0.006 |
| 3 | 25PE0064CONSTRUCTION OF SCHOOL BUILDING, TUBA CENTRAL NATIONAL HIGH SCHOOL, BARANGAY POBLACION, TUBA, BENGUET | Cordillera Administrative Region | Benguet 1st DEO | On-Going | ₱19.9M | 2% | High risk88 | Flagged0.072 |
| 4 | 24PF0078CONSTRUCTION OF 4-STOREY 8-CLASSROOM SCHOOL BUILDING IN LOO NATIONAL HIGH SCHOOL, BARANGAY, LOO, BUGUIAS, BENGUET | Cordillera Administrative Region | Benguet 2nd DEO | On-Going | ₱39.8M | 80% | High risk87 | Flagged0.051 |
| 5 | 24PF0079CONSTRUCTION OF 3-STOREY 15-CLASSROOM AT FRANKLIN GUY HAIGHT NATIONAL HIGHSCHOOL, ATOK, BENGUET | Cordillera Administrative Region | Benguet 2nd DEO | On-Going | ₱43.3M | 90% | High risk86 | Flagged0.052 |
| 6 | 24P00014CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL ALONG AGNO RIVER, SITIO BANAO AND SITIO ADONOT, BARANGAY AMBUKLAO, BOKOD, BENGUET | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱147.6M | 65% | High risk78 | Flagged0.028 |
| 7 | 21PA0221CONSTRUCTION OF PULOT-KIWAS FLOOD CONTROL, LAGAYAN, ABRA | Cordillera Administrative Region | Abra DEO | Completed | ₱96.5M | 100% | High risk63 | —-0.053 |
| 8 | 24PF0086CONSTRUCTION OF PROPER GADANG-LAO-ANGAN ROAD, KAPANGAN, BENGUET | Cordillera Administrative Region | Benguet 2nd DEO | On-Going | ₱95.4M | 51% | High risk61 | Flagged0.023 |
| 9 | 22P00040CONSTRUCTION OF ROAD, ANOVANG DOMOLPOS ITOGON - KAYAPA, NUEVA VIZCAYA, ITOGON BENGUETANOVANG, DOMOLPOS, ITOGON, BENGUET | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱297M | 100% | Medium risk58 | —-0.038 |
| 10 | 23PE0046CONSTRUCTION OF DPWH BENGUET 1ST DISTRICT ENGINEERING OFFICE MAIN BUILDING, BENGUET | Cordillera Administrative Region | Benguet 1st DEO | On-Going | ₱48.3M | 100% | Medium risk54 | —-0.038 |
| 11 | 25PE0017CONSTRUCTION OF DPWH BENGUET 1ST DISTRICT ENGINEERING OFFICE MAIN BUILDING, BENGUET (PHASE IV), LA TRINIDAD, BENGUET | Cordillera Administrative Region | Benguet 1st DEO | On-Going | ₱49M | 36% | Medium risk53 | —-0.024 |
| 12 | 24PE0059CONSTRUCTION OF DPWH BENGUET 1ST DISTRICT ENGINEERING OFFICE MAIN BUILDING, BENGUET (PHASE III) | Cordillera Administrative Region | Benguet 1st DEO | On-Going | ₱49M | 74% | Medium risk53 | —-0.029 |
| 13 | 25OE0049CONSTRUCTION OF DRAINAGE ALONG TAYUMAN ST., MANILA CITY | National Capital Region | North Manila DEO | On-Going | ₱80.2M | 0% | Medium risk53 | —-0.025 |
| 14 | 23P00008BAGUIO-LA TRINIDAD-ITOGON-SABLAN-TUBA AND TUBLAY, GUISSET-BINGA-BALOY-TINONGDAN (SECTION 5 OF BLISTT OUTER RING CIRCUMFERENTIAL ROAD), PACKAGE 2, BENGUET | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱67.6M | 82% | Medium risk52 | —-0.003 |
| 15 | 23PE0050CONSTRUCTION OF 4STY10CL WITH SCIENCE LABORATORY, AMBIONG NATIONAL HIGH SCHOOL, LA TRINIDAD, BENGUET | Cordillera Administrative Region | Benguet 1st DEO | On-Going | ₱47.1M | 89% | Medium risk51 | Flagged0.013 |
| 16 | 22PA0053BASIC INFRASTRUCTURE PROGRAM (BIP) FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/ FACILITIES CONSTRUCTION OF PULOT FLOOD CONTROL STRUCTURE (PHASE 2), BARANGAY PULOT, LAGAYAN, ABRA | Cordillera Administrative Region | Abra DEO | Completed | ₱49.5M | 100% | Medium risk50 | —-0.064 |
| 17 | 22PA0075BASIC INFRASTRUCTURE PROGRAM (BIP) FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/ FACILITIES, CONSTRUCTION OF LUSUAC FLOOD CONTROL STRUCTURE, BARANGAY POBLACION, LAGAYAN, ABRA | Cordillera Administrative Region | Abra DEO | Completed | ₱49M | 100% | Medium risk50 | —-0.064 |
| 18 | 24PE0077CONSTRUCTION OF 3-STOREY 13-CLASSROOM SCHOOL BUILDING WITH SCIENCE LABORATORY ROOM IN AMBANGEG NATIONAL HIGH SCHOOL, BARANGAY DAKLAN, BOKOD, BENGUET | Cordillera Administrative Region | Benguet 1st DEO | On-Going | ₱39.8M | 89% | Medium risk49 | Flagged0.005 |
| 19 | 24PF0077CONSTRUCTION OF 3 STOREY 15 CLASSROOM SCHOOL BUILDING IN GOV. BADO DANGWA AGRO INDUSTRIAL SCHOOL, KAPANGAN, BENGUET | Cordillera Administrative Region | Benguet 2nd DEO | On-Going | ₱39.8M | 56% | Medium risk47 | Flagged0.018 |
| 20 | 22PE0087CONSTRUCTION OF BANAO CANTINA WATER SUPPLY SYSTEM, AMBUKLAO, BOKOD, BENGUET | Cordillera Administrative Region | Benguet 1st DEO | Completed | ₱4.8M | 100% | Medium risk46 | —-0.049 |
| 21 | 22PE0023STRENGTHENING/RETROFITTING OF PERMANENT BRIDGES: ITOGON BRIDGE (B02165LZ) ALONG BAGUIO-ITOGON RD, ITOGON, BENGUET | Cordillera Administrative Region | Benguet 1st DEO | Completed | ₱9.8M | 100% | Medium risk45 | —-0.046 |
| 22 | 22PE0005CONSTRUCTION OF FLOOD MITIGATION STRUCTURE WITHIN ARINGAY RIVER BASIN: ALONG ARINGAY RIVER MAIN STREAM (COPLO AND NANGALISAN PROPER), TUBA, BENGUET | Cordillera Administrative Region | Benguet 1st DEO | Completed | ₱24.1M | 100% | Medium risk44 | —-0.067 |
| 23 | 22PE0048CONCRETING OF SITIO PERIL, BRGY. ALAPANG FMR, BRGY. ALAPANG, LA TRINIDAD, BENGUET | Cordillera Administrative Region | Benguet 1st DEO | Completed | ₱12.4M | 100% | Medium risk40 | —-0.033 |
| 24 | 22PE0132REHABILITATION (COMPLETION) OF TAROY LIGAY ROAD, CAMP 1, TUBA, BENGUET | Cordillera Administrative Region | Benguet 1st DEO | Completed | ₱2.9M | 100% | Low risk23 | —-0.082 |
| 25 | 22PF0155CONSTRUCTION (COMPLETION) OF WATER SUPPLY AT CAMP 30, BARANGAY CALIKING, ATOK, BENGUET | Cordillera Administrative Region | Benguet 2nd DEO | Completed | ₱2.9M | 100% | Low risk23 | —-0.045 |