Opening the dossier…
Opening the dossier…
Contractor dossier
101 projects on file, including joint ventures this contractor is part of.
Total projects
101
Total budget
₱1.3B
Average progress
99.3%
Completion rate
91.1%
Average risk score
37.5
Medium risk on average, out of 100
Flagged as unusual
3
3.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VI | 101 | ₱1.3B | 37.5 | 3 | 99.3% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 40 | ₱138.3M | 25.4 | 0 | 100.0% |
| Roads | 34 | ₱718.7M | 42.3 | 0 | 99.9% |
| Bridges | 12 | ₱172.6M | 46.7 | 0 | 100.0% |
| Water Provision and Storage | 6 | ₱26.3M | 32.9 | 0 | 100.0% |
| OTHER | 3 | ₱60.4M | 71.3 | 2 | 81.9% |
| Flood Control and Drainage | 3 | ₱61.9M | 46.0 | 0 | 98.4% |
| GAA 2025 SSP | 1 | ₱4.9M | 90.3 | 1 | 100.0% |
| GAA 2025 OO-1 | 1 | ₱19.9M | 87.9 | 0 | 100.0% |
| Bridges, Roads | 1 | ₱50.8M | 50.4 | 0 | 94.1% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25GB0020CONSTRUCTION OF MULTI-PURPOSE BUILDING, MUNICIPAL GROUNDS, BARANGAY POBLACION, BELISON, ANTIQUE | Region VI | Antique DEO | On-Going | ₱4.9M | 100% | High risk90 | Flagged0.012 |
| 25GB0003RECONSTRUCTION TO CONCRETE PAVEMENT - ILOILO-ANTIQUE RD, K0084+500 - K0085+596, K0086+217 - K0086+544, HAMTIC, ANTIQUE | Region VI | Antique DEO | Completed | ₱19.9M | 100% | High risk88 | —-0.034 |
| 25GB0126CONSTRUCTION OF SCHOOL BUILDING, PITAC ELEMENTARY SCHOOL, PITAC, MUNICIPALITY OF TIBIAO, ANTIQUE | Region VI | Antique DEO | On-Going | ₱5M | 85% | High risk88 | Flagged0.050 |
| 23GB0046SAN JOSE PORT RD - K0096 + (-079) - K0096 +864 | Region VI | Antique DEO | On-Going | ₱16.8M | 60% | High risk78 | Flagged0.025 |
| 17GB0081WIDENING OF ILOILO -ANTIQUE ROAD, K0110+000-K0111+996, ANTIQUE | Region VI | Antique DEO | Completed | ₱34M | 100% | High risk65 | —-0.054 |
| 17GB0003CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROAD-ILOILO-ANTIQUE ROAD, K0111+000 | Region VI | Antique DEO | Completed | ₱32.3M | 100% | High risk65 | —-0.054 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25GB0126CONSTRUCTION OF SCHOOL BUILDING, PITAC ELEMENTARY SCHOOL, PITAC, MUNICIPALITY OF TIBIAO, ANTIQUE | Region VI | Antique DEO | On-Going | ₱5M | 85% | High risk88 | Flagged0.050 |
| 23GB0046SAN JOSE PORT RD - K0096 + (-079) - K0096 +864 | Region VI | Antique DEO | On-Going | ₱16.8M | 60% | High risk78 | Flagged0.025 |
| 25GB0020CONSTRUCTION OF MULTI-PURPOSE BUILDING, MUNICIPAL GROUNDS, BARANGAY POBLACION, BELISON, ANTIQUE | Region VI | Antique DEO | On-Going | ₱4.9M | 100% | High risk90 | Flagged0.012 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25GB0020CONSTRUCTION OF MULTI-PURPOSE BUILDING, MUNICIPAL GROUNDS, BARANGAY POBLACION, BELISON, ANTIQUE | Region VI | Antique DEO | On-Going | ₱4.9M | 100% | High risk90 | Flagged0.012 |
| 2 | 25GB0003RECONSTRUCTION TO CONCRETE PAVEMENT - ILOILO-ANTIQUE RD, K0084+500 - K0085+596, K0086+217 - K0086+544, HAMTIC, ANTIQUE | Region VI | Antique DEO | Completed | ₱19.9M | 100% | High risk88 | —-0.034 |
| 3 | 25GB0126CONSTRUCTION OF SCHOOL BUILDING, PITAC ELEMENTARY SCHOOL, PITAC, MUNICIPALITY OF TIBIAO, ANTIQUE | Region VI | Antique DEO | On-Going | ₱5M | 85% | High risk88 | Flagged0.050 |
| 4 | 23GB0046SAN JOSE PORT RD - K0096 + (-079) - K0096 +864 | Region VI | Antique DEO | On-Going | ₱16.8M | 60% | High risk78 | Flagged0.025 |
| 5 | 17GB0081WIDENING OF ILOILO -ANTIQUE ROAD, K0110+000-K0111+996, ANTIQUE | Region VI | Antique DEO | Completed | ₱34M | 100% | High risk65 | —-0.054 |
| 6 | 17GB0003CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROAD-ILOILO-ANTIQUE ROAD, K0111+000 | Region VI | Antique DEO | Completed | ₱32.3M | 100% | High risk65 | —-0.054 |
| 7 | 16GB0222CONSTRUCTION OF 2 STOREY SIX(6) CLASSROOM SCHOOL BUILDING AT GIDEON CABIGUNDA MS, SAN REMIGIO, ANTIQ | Region VI | Antique DEO | Completed | ₱8.1M | 100% | Medium risk56 | —-0.022 |
| 8 | 23GB0123CONCRETING OF BRGY. IGCABUAD TO BRGY. IGTUBAS FMR TOBIAS FORNIER, ANTIQUE | Region VI | Antique DEO | Completed | ₱49.6M | 100% | Medium risk53 | —-0.023 |
| 9 | 24GB0147REHABILITATION OF FARM-TO-MARKET ROAD IN SITIO MALAWMAWAN, LINDERO-LIBERATO, LAUA-AN, ANTIQUE | Region VI | Antique DEO | On-Going | ₱55.5M | 100% | Medium risk52 | —-0.052 |
| 10 | 16GB0246CONSTRUCTION OF 2 STOREY TEN(10) CLASSROOM SCHOOL BUILDING AT PIS-ANAN NATIONAL HIGH SCHOOL, SIBALOM | Region VI | Antique DEO | Completed | ₱12.6M | 100% | Medium risk51 | —-0.015 |
| 11 | 24GB0093EGANA BR. (B00083PN) ALONG HAMTIC-BIA-AN-EGANA- SIBALOM RD, ANTIQUE | Region VI | Antique DEO | On-Going | ₱50.8M | 94% | Medium risk50 | —-0.035 |
| 12 | 16GB0257CONSTRUCTION OF 2 STOREY TEN(10) CLASSROOM SCHOOL BUILDING AT PANGPANG NHS, SIBALOM, ANTIQUE | Region VI | Antique DEO | Completed | ₱12.6M | 100% | Medium risk49 | —-0.018 |
| 13 | 16GB0225CONSTRUCTION OF 2 STOREY FOUR(4) CLASSROOM SCHOOL BUILDING AT SAN PEDRO NHS, SAN JOSE(CAPITAL), ANTI | Region VI | Antique DEO | Completed | ₱6.1M | 100% | Medium risk49 | —-0.021 |
| 14 | 22GB0037CONSTRUCTION OF BRIDGE BARANGAY IGCOCOC, SIBALOM, ANTIQUE | Region VI | Antique DEO | Completed | ₱38.6M | 100% | Medium risk48 | —-0.051 |
| 15 | 20GB0018NAURING BRIDGE (B00377PN) ALONG PANDAN-LIBERTAD-AKLAN BOUNDARY ROAD PANDAN, ANTIQUE | Region VI | Antique DEO | Completed | ₱14.4M | 100% | Medium risk47 | —-0.051 |
| 16 | 24GB0074CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, MUNICIPALITY OF SEBASTE, ANTIQUE | Region VI | Antique DEO | Completed | ₱4.9M | 100% | Medium risk47 | —-0.083 |
| 17 | 20GB0017CABILAWAN BR. (B00375PN) ALONG ILOILO-ANTIQUE RD, PANDAN, ANTIQUE | Region VI | Antique DEO | Completed | ₱14.2M | 100% | Medium risk47 | —-0.050 |
| 18 | 23GB0065CONSTRUCTION OF BRIDGE, IGOT RIVER | Region VI | Antique DEO | Completed | ₱4.9M | 100% | Medium risk47 | —-0.052 |
| 19 | 23GB0018SAN ROQUE BR. (B00383PN) ALONG PANDAN-LIBERTAD-AKLAN BOUNDARY RD LIBERTAD, ANTIQUE | Region VI | Antique DEO | Completed | ₱9.7M | 100% | Medium risk47 | —-0.052 |
| 20 | 23GB0017SAN ANDRES BR. (B00373PN) ALONG ILOILO-ANTIQUE RD PANDAN, ANTIQUE | Region VI | Antique DEO | Completed | ₱9.7M | 100% | Medium risk47 | —-0.053 |
| 21 | 20GB0058NAULING BRIDGE (B00376PN) ALONG ILOILO-ANTIQUE ROAD PANDAN, ANTIQUE | Region VI | Antique DEO | Completed | ₱11.6M | 100% | Medium risk47 | —-0.053 |
| 22 | 16GB0219CONSTRUCTION OF 2 STOREY SIX(6) CLASSROOM SCHOOL BUILDING AT GEN. LEANDRO FULLON NS, HAMTIC, ANTIQUE | Region VI | Antique DEO | Completed | ₱8.2M | 100% | Medium risk47 | —-0.014 |
| 23 | 21GB0052CONSTRUCTION OF CIRCUMFERENTIAL ROAD BARANGAY CAMANCIJAN, TOMAO,BUENAVISTA, SAN JUAN AND BAGACAY IN | Region VI | Antique DEO | Completed | ₱46.4M | 100% | Medium risk47 | —-0.085 |
| 24 | 24GB0078CONCRETING OF CIRCUMFERENCIAL ROAD POBLACION, CALUYA, ANTIQUE PHASE III | Region VI | Antique DEO | Completed | ₱31.6M | 100% | Medium risk47 | —-0.085 |
| 25 | 21GB0050CONSTRUCTION OF CONCRETE BRIDGE, BARANGAY TAMAYOC, MUNICIPALITY OF PATNONGON | Region VI | Antique DEO | Completed | ₱29.3M | 100% | Medium risk47 | —-0.052 |