Opening the dossier…
Opening the dossier…
Contractor dossier
186 projects on file, including joint ventures this contractor is part of.
Total projects
186
Total budget
₱2.1B
Average progress
99.2%
Completion rate
86.0%
Average risk score
35.4
Medium risk on average, out of 100
Flagged as unusual
4
2.2% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region X | 186 | ₱2.1B | 35.4 | 4 | 99.2% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 88 | ₱931.2M | 36.6 | 1 | 99.8% |
| Buildings and Facilities | 54 | ₱244.1M | 18.3 | 0 | 98.7% |
| Flood Control and Drainage | 28 | ₱740.5M | 44.8 | 0 | 99.2% |
| Water Provision and Storage | 6 | ₱81.3M | 39.5 | 0 | 100.0% |
| GAA 2025 SSP | 5 | ₱47.2M | 94.5 | 0 | 97.4% |
| OTHER | 4 | ₱57.4M | 82.1 | 3 | 95.9% |
| GAA 2025 OO-1 | 1 | ₱24.8M | 91.2 | 0 | 94.1% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25KE0018CONSTRUCTION OF QUIBORO-QUIPASA ROAD,BARANGAY POBLACION,MAMBAJAO,CAMIGUIN | Region X | Camiguin DEO | On-Going | ₱11.5M | 97% | High risk95 | —-0.004 |
| 25KE0020CONSTRUCTION OF ROADS, BARANGAY MAINIT AND BARANGAY PANGHIAWAN, CATARMAN, CAMIGUIN | Region X | Camiguin DEO | On-Going | ₱11.6M | 94% | High risk95 | —-0.005 |
| 25KE0025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) BARANGAY BONBON,SAGAY, CAMIGUIN | Region X | Camiguin DEO | On-Going | ₱9.6M | 98% | High risk94 | —-0.004 |
| 25KE0022CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY BAYLAO, MAMBAJAO, CAMIGUIN | Region X | Camiguin DEO | On-Going | ₱9.6M | 100% | High risk94 | —-0.005 |
| 25KE0023REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) BARANGAY POBLACION,MAMBAJAO,CAMIGUIN | Region X | Camiguin DEO | On-Going | ₱4.8M | 98% | High risk94 | —-0.003 |
| 25KE0048ROAD WIDENING - SECONDARY ROADS CAMIGUIN CIRCUMFERENTIAL ROAD - K0011 + 402 - K0011 + 857, K0011 + 857 - K0011 + 883.50, K0027 + 320 - K0027 + 473, K0027 + 473 - K0027 + 852 | Region X | Camiguin DEO | On-Going | ₱24.8M | 94% | High risk91 | —-0.015 |
| 25KE0049CONCRETING OF SITIO KANDIIS TO MAAMBOG, BRGY.BURA FMR, CATARMAN, CAMIGUIN | Region X | Camiguin DEO | On-Going | ₱14.8M | 95% | High risk86 | Flagged0.031 |
| 25KE0044CONCRETING OF PUROK 2, 3, 4, BARANGAY PANGHIAWAN FMR, CATARMAN, CAMIGUIN | Region X | Camiguin DEO | On-Going | ₱14.7M | 90% | High risk86 | Flagged0.034 |
| 24KE0113CONSTRUCTION OF ROAD, SITIO LOWER COGON TO SITIO DAL-AS, BARANGAY AGOHO, MAMBAJAO, CAMIGUIN | Region X | Camiguin DEO | On-Going | ₱9.4M | 98% | High risk84 | Flagged0.029 |
| 18KE0001CONSTRUCTION OF RUBBLE CONCRETE DIKE ALONG SAN ROQUE RIVER CONTROL/DRAINAGE SYSTEM ALONG CCR LUTAO BRIDGE | Region X | Camiguin DEO | Completed | ₱18.6M | 100% | High risk73 | —-0.041 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25KE0044CONCRETING OF PUROK 2, 3, 4, BARANGAY PANGHIAWAN FMR, CATARMAN, CAMIGUIN | Region X | Camiguin DEO | On-Going | ₱14.7M | 90% | High risk86 | Flagged0.034 |
| 25KE0049CONCRETING OF SITIO KANDIIS TO MAAMBOG, BRGY.BURA FMR, CATARMAN, CAMIGUIN | Region X | Camiguin DEO | On-Going | ₱14.8M | 95% | High risk86 | Flagged0.031 |
| 24KE0113CONSTRUCTION OF ROAD, SITIO LOWER COGON TO SITIO DAL-AS, BARANGAY AGOHO, MAMBAJAO, CAMIGUIN | Region X | Camiguin DEO | On-Going | ₱9.4M | 98% | High risk84 | Flagged0.029 |
| 24KE0108CONCRETING OF SITIO PASANAN, BRGY. MANDUAO TO SITIO TUBOS, BRGY. LILOAN FMR, BRGY. MANDUAO AND BRGY. LILOAN, CATARMAN, CAMIGUIN | Region X | Camiguin DEO | On-Going | ₱48.2M | 100% | Medium risk52 | Flagged0.005 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 24KE0103CONCRETING OF SITIO ABU BAYLAO TO SITIO BINUNSARAN, POBLACION FMR, MAMBAJAO, CAMIGUIN | Region X | Camiguin DEO | Completed | ₱14.5M | 100% | Medium risk45 | —-0.041 |
| 27 | 18KE0033CONSTRUCTION/IMPROVEMENT OF LUMAD ROAD LEADING TO SAAY WATER SPRING,MAMBAJAO,CAMIGUIN | Region X | Camiguin DEO | Completed | ₱23.5M | 100% | Medium risk45 | —-0.094 |
| 28 | 23KE0009SERVICE ROAD TO BINANGAWAN FALLS ,SAGAY, CAMIGUIN | Region X | Camiguin DEO | Completed | ₱19.6M | 100% | Medium risk45 | —-0.095 |
| 29 | 23KE0029CONSTRUCTION OF ROAD BRGY. BENONI,MAHINOG,CAMIGUIN | Region X | Camiguin DEO | Completed | ₱19.6M | 100% | Medium risk45 | —-0.095 |
| 30 | 22KE0033SERVICE ROAD TO BINANGAWAN FALLS, SAGAY, CAMIGUIN | Region X | Camiguin DEO | Completed | ₱18.8M | 100% | Medium risk45 | —-0.095 |
| 31 | 22KE0002NAASAG-YUMBING-AGOHO ROAD IN SUPPORT OF AGRI-BUSINESS INDUSTRIES (COCONUT,ABACA AND BAMBOO), MAMBAJAO, CAMIGUIN | Region X | Camiguin DEO | Completed | ₱18.7M | 100% | Medium risk45 | —-0.095 |
| 32 | 24KE0020CONSTRUCTION OF ROAD TO NIGHTSCAPE MT. TIMPOONG-HIBOK-HIBOK NATURAL MONUMENT,MAMBAJAO,CAMIGUIN | Region X | Camiguin DEO | On-Going | ₱14M | 100% | Medium risk45 | —-0.053 |
| 33 | 24KE0109CONCRETING OF BRGY. MAAC, GUINSILIBAN TO BRGY. SAN MIGUEL, MAHINOG FMR, BRGY. MAAC, GUINSILIBAN AND BRGY. SAN MIGUEL, MAHINOG, CAMIGUIN | Region X | Camiguin DEO | On-Going | ₱14.5M | 100% | Medium risk45 | —-0.002 |
| 34 | 23KE0064CONCRETING OF BRGY. MAAC GUINSILIBAN TO BRGY. SAN MIGUEL,MAHINOG,FMR,BRGY. MAAC GUINSILIBAN AND BRGY. SAN MIGUEL,MAHINOG, CAMIGUIN | Region X | Camiguin DEO | Completed | ₱14.5M | 100% | Medium risk45 | —-0.039 |
| 35 | 24KE0052CONSTRUCTION OF RIVER CONTROL ALONG LOOC BRIDGE, CATARMAN, CAMIGUIN | Region X | Camiguin DEO | On-Going | ₱28.5M | 97% | Medium risk45 | —-0.041 |
| 36 | 24KE0068CONSTRUCTION OF SLOPE PROTECTION ALONG MAGTING - TUPSAN ALTERNATE ROAD, MAMBAJAO, CAMIGUIN | Region X | Camiguin DEO | On-Going | ₱28.6M | 100% | Medium risk45 | —-0.045 |
| 37 | 22KE0037CONSTRUCTION OF DINANGGASAN RIVER CONTROL | Region X | Camiguin DEO | Completed | ₱29.4M | 100% | Medium risk45 | —-0.079 |
| 38 | 23KE0042CONSTRUCTION OF RIVER CONTROL ALONG AGOHO BOX CULVERT BARANGAY AGOHO MAMBAJAO,CAMIGUIN | Region X | Camiguin DEO | Completed | ₱10.8M | 100% | Medium risk45 | —-0.079 |
| 39 | 22KE0038CONSTRUCTION OF RIVER CONTROL ALONG ALANGILAN BOX CULVERT | Region X | Camiguin DEO | Completed | ₱43.2M | 100% | Medium risk45 | —-0.077 |
| 40 | 20KE0040CONCRETING OF ROAD BRGY. NAASAG,MAMBAJAO, CAMIGUIN | Region X | Camiguin DEO | Completed | ₱4.9M | 100% | Medium risk45 | —-0.093 |
| 41 | 18KE0004CONSTRUCTION OF RUBBLE CONCRETE DIKE ALONG AGURAN RIVER CONTROL/DRAINAGE SYSTEM ALONG CCR AGURAN BRIDGE | Region X | Camiguin DEO | Completed | ₱14M | 100% | Medium risk45 | —-0.079 |
| 42 | 24KE0017CONSTRUCTION OF RIVER CONTROL ALONG LUTAO BRIDGE,SAN ROQUE,MAHINOG,CAMIGUIN | Region X | Camiguin DEO | Completed | ₱19M | 100% | Medium risk45 | —-0.081 |
| 43 | 21KE0046CONSTRUCTION OF DINANGASAN RIVER CONTROL | Region X | Camiguin DEO | Completed | ₱18.6M | 100% | Medium risk45 | —-0.081 |
| 44 | 22KE0039CONSTRUCTION OF RIVER CONTROL/DRAINAGE SYSTEM AT AGOHO BOX CULVERT, K58+600- K59+020 | Region X | Camiguin DEO | Completed | ₱18.7M | 100% | Medium risk45 | —-0.081 |
| 45 | 22KE0036CONSTRUCTION OF BAYLAO RIVER CONTROL | Region X | Camiguin DEO | Completed | ₱28.1M | 100% | Medium risk45 | —-0.081 |
| 46 | 23KE0014CONSTRUCTION OF ROAD BARANGAY TAGDO-KUGUITA,MAMBAJAO,CAMIGUIN | Region X | Camiguin DEO | Completed | ₱4.9M | 100% | Medium risk45 | —-0.095 |
| 47 | 25KE0042CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) SITIO LUMAD, MAMBAJAO, CAMIGUIN | Region X | Camiguin DEO | On-Going | ₱14.6M | 32% | Medium risk44 | —-0.042 |
| 48 | 21KE0084CONSTRUCTION OF ROAD BURA,CATARMAN,CAMIGUIN | Region X | Camiguin DEO | Completed | ₱5.1M | 100% | Medium risk44 | —-0.094 |
| 49 | 21KE0081CONCRETING OF BASIAO TO VOLCAN ROAD,NAASAG,MAMBAJAO,CAMIGUIN | Region X | Camiguin DEO | Completed | ₱9.6M | 100% | Medium risk44 | —-0.095 |
| 50 | 22KE0020CONSTRUCTION OF ROAD, BARANGAY BURA, CATARMAN, CAMIGUIN | Region X | Camiguin DEO | Completed | ₱6.6M | 100% | Medium risk44 | —-0.095 |