Opening the dossier…
Opening the dossier…
Contractor dossier
85 projects on file, including joint ventures this contractor is part of.
Total projects
85
Total budget
₱2.5B
Average progress
92.6%
Completion rate
76.5%
Average risk score
51.3
Medium risk on average, out of 100
Flagged as unusual
3
3.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region V | 81 | ₱2.5B | 51.6 | 3 | 92.3% |
| Region IV-A | 4 | ₱51.3M | 45.7 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 39 | ₱1.6B | 51.5 | 0 | 90.2% |
| Buildings and Facilities | 30 | ₱300.7M | 48.1 | 0 | 96.3% |
| Flood Control and Drainage | 8 | ₱467.8M | 51.2 | 0 | 99.2% |
| Water Provision and Storage | 3 | ₱21.9M | 43.0 | 0 | 100.0% |
| OTHER | 2 | ₱68.8M | 85.9 | 2 | 73.5% |
| Bridges | 2 | ₱43M | 51.6 | 0 | 97.2% |
| GAA 2025 OO-1 | 1 | ₱35.3M | 93.2 | 1 | 31.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25F00211ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-OFF-CARRIAGEWAY IMPROVEMENT-PRIMARY ROADS-MAHARLIKA HIGHWAY-K0402+874-K0404+000, K0404+202-K0404+352, K0404+586-K0405+856, LIBMANAN, CAMARINES SUR (2ND LE | Region V | Region V | On-Going | ₱35.3M | 31% | High risk93 | Flagged0.007 |
| 24F00437CAPITAL OUTLAY-DOH HEALTH FACILITIES ENHANCEMENT PROGRAM (HFEP)-LGU HOSPITALS-EASTERN BICOL MEDICAL CENTER, CATANDUANES, VIRAC, CATANDUANES (LONE DISTRICT) | Region V | Region V | On-Going | ₱29.4M | 47% | High risk87 | Flagged0.051 |
| 24FN0093REHABILITATION OF DISASTER-RELATED INFRASTRACTURE AND OTHER FACILITIES - RELEASE OF FUNDS FOR THE REPAIR/REHABILITATION AND MAINTENANCE OF NABUA-BALATAN ROAD, ROAD SLIP K0489+000 - K0489+200 (R/S) | Region V | Camarines Sur 5th DEO | Completed | ₱39.4M | 100% | High risk85 | Flagged0.010 |
| 20F00060LOCAL PROGRAM-FLOOD CONTROL AND DRAINAGE-FLOOD CONTROL STRUCTURES/FACILITIES-CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-CONSTRUCTION/IMPROVEMENT OF MANAPO RIVER FLOOD MITIGATION STRUCTURES (SALVACION- | Region V | Region V | On-Going | ₱140.8M | 93% | High risk70 | —-0.008 |
| 20F00018OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CAMARINES SUR EXPRESSWAY PROJECT(SAN FERNANDO-PILI), PACKAGE 3, CAMARINES SUR, MANAPAO-MATAOROC, MINALABAC, CAMARINES SUR (2ND LEGI | Region V | Region V | Completed | ₱193M | 100% | High risk69 | —-0.059 |
| 22F00051OO1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-CAMARINES SUR EXPRESSWAY (PACKAGE 5), PILI, CAMARINES SUR (3RD LEGISLATIVE DISTRICT) | Region V | Region V | Completed | ₱193M | 100% | High risk69 | —-0.060 |
| 22F00050OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-CAMARINES SUR EXPRESSWAY (PACKAGE 4), SAN FERNANDO-MINALABAC, CAMARINES SUR(2ND LEGISLATIVE DISTRICT) | Region V | Region V | Completed | ₱482.5M | 100% | High risk68 | —-0.052 |
| 24F00131ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS-DAANG MAHARLIKA (LZ)-K0476+979-K0477+097, BATO, CAMARINES SUR (5TH LEGISLATIVE DISTRICT) | Region V | Region V | On-Going | ₱5.4M | 0% | High risk67 | —-0.008 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24F00437CAPITAL OUTLAY-DOH HEALTH FACILITIES ENHANCEMENT PROGRAM (HFEP)-LGU HOSPITALS-EASTERN BICOL MEDICAL CENTER, CATANDUANES, VIRAC, CATANDUANES (LONE DISTRICT) | Region V | Region V | On-Going | ₱29.4M | 47% | High risk87 | Flagged0.051 |
| 24FN0093REHABILITATION OF DISASTER-RELATED INFRASTRACTURE AND OTHER FACILITIES - RELEASE OF FUNDS FOR THE REPAIR/REHABILITATION AND MAINTENANCE OF NABUA-BALATAN ROAD, ROAD SLIP K0489+000 - K0489+200 (R/S) | Region V | Camarines Sur 5th DEO | Completed | ₱39.4M | 100% | High risk85 | Flagged0.010 |
| 25F00211ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-OFF-CARRIAGEWAY IMPROVEMENT-PRIMARY ROADS-MAHARLIKA HIGHWAY-K0402+874-K0404+000, K0404+202-K0404+352, K0404+586-K0405+856, LIBMANAN, CAMARINES SUR (2ND LE | Region V | Region V | On-Going | ₱35.3M | 31% | High risk93 | Flagged0.007 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25F00211ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-OFF-CARRIAGEWAY IMPROVEMENT-PRIMARY ROADS-MAHARLIKA HIGHWAY-K0402+874-K0404+000, K0404+202-K0404+352, K0404+586-K0405+856, LIBMANAN, CAMARINES SUR (2ND LE | Region V | Region V | On-Going | ₱35.3M | 31% | High risk93 | Flagged0.007 |
| 2 | 24F00437CAPITAL OUTLAY-DOH HEALTH FACILITIES ENHANCEMENT PROGRAM (HFEP)-LGU HOSPITALS-EASTERN BICOL MEDICAL CENTER, CATANDUANES, VIRAC, CATANDUANES (LONE DISTRICT) | Region V | Region V | On-Going | ₱29.4M | 47% | High risk87 | Flagged0.051 |
| 3 | 24FN0093REHABILITATION OF DISASTER-RELATED INFRASTRACTURE AND OTHER FACILITIES - RELEASE OF FUNDS FOR THE REPAIR/REHABILITATION AND MAINTENANCE OF NABUA-BALATAN ROAD, ROAD SLIP K0489+000 - K0489+200 (R/S) | Region V | Camarines Sur 5th DEO | Completed | ₱39.4M | 100% | High risk85 | Flagged0.010 |
| 4 | 20F00060LOCAL PROGRAM-FLOOD CONTROL AND DRAINAGE-FLOOD CONTROL STRUCTURES/FACILITIES-CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-CONSTRUCTION/IMPROVEMENT OF MANAPO RIVER FLOOD MITIGATION STRUCTURES (SALVACION- | Region V | Region V | On-Going | ₱140.8M | 93% | High risk70 | —-0.008 |
| 5 | 20F00018OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CAMARINES SUR EXPRESSWAY PROJECT(SAN FERNANDO-PILI), PACKAGE 3, CAMARINES SUR, MANAPAO-MATAOROC, MINALABAC, CAMARINES SUR (2ND LEGI | Region V | Region V | Completed | ₱193M | 100% | High risk69 | —-0.059 |
| 6 | 22F00051OO1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-CAMARINES SUR EXPRESSWAY (PACKAGE 5), PILI, CAMARINES SUR (3RD LEGISLATIVE DISTRICT) | Region V | Region V | Completed | ₱193M | 100% | High risk69 | —-0.060 |
| 7 | 22F00050OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-CAMARINES SUR EXPRESSWAY (PACKAGE 4), SAN FERNANDO-MINALABAC, CAMARINES SUR(2ND LEGISLATIVE DISTRICT) | Region V | Region V | Completed | ₱482.5M | 100% | High risk68 | —-0.052 |
| 8 | 24F00131ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS-DAANG MAHARLIKA (LZ)-K0476+979-K0477+097, BATO, CAMARINES SUR (5TH LEGISLATIVE DISTRICT) | Region V | Region V | On-Going | ₱5.4M | 0% | High risk67 | —-0.008 |
| 9 | 23F00131LOCAL PROGRAM - NATIONAL BUILDING PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES - IMPROVEMENT OF QAHD BUILDING, DPWH REGIONAL OFFICE V (PHASE I), REGIONAL GOVERNMENT CENTER, LEGAZPI CITY, ALBAY, REGIONAL GOVERNMENT CENTER, LEGAZPI CIT | Region V | Region V | On-Going | ₱5.8M | 95% | Medium risk60 | —-0.056 |
| 10 | 25F00201ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-MAHARLIKA HIGHWAY-K0478+956-K0479+243, K0479+582-K0479+840,K0479+866-K0479+995, BATO, CAMARINES SUR (5TH LEGISLATIVE DISTRICT) | Region V | Region V | On-Going | ₱30.3M | 24% | Medium risk58 | —-0.051 |
| 11 | 24FE0067CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), DPWH CAMARINES SUR 2ND DEO, SAN GABRIEL, PAMPLONA, CAMARINES SUR | Region V | Camarines Sur 2nd DEO | On-Going | ₱47.8M | 100% | Medium risk57 | —-0.014 |
| 12 | 25FD0005REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS ALONG ROLANDO R. ANDAYA HIGHWAY - K0282 + (-916) - K0282 + (-660), K0282 + (-531) - K0282 + (-458), K0282 + (-406) - K0282 + (-365), K0282 + (-203) - K0282 + (-139), K0282 + | Region V | Camarines Sur 1st DEO | On-Going | ₱47.4M | 23% | Medium risk57 | —-0.052 |
| 13 | 25FE0012LP: NATIONAL BUILDING PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE / FACILITIES - CONSTRUCTION (PHASE 2) OF DPWH OFFICE BUILDING, CAMARINES SUR 2ND DEO, SAN GABRIEL, PAMPLONA, CAMARINES SUR | Region V | Camarines Sur 2nd DEO | On-Going | ₱29.2M | 58% | Medium risk56 | —-0.049 |
| 14 | 25FD0004REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS ALONG ROLANDO R. ANDAYA HIGHWAY - K0283 + 000 - K0283 + 109, K0283 + 480 - K0283 + 671, K0284 + 000 - K0284 + 214, K0284 + 493 - K0284 + 787, DEL GALLEGO, CAMARINES SUR | Region V | Camarines Sur 1st DEO | On-Going | ₱41M | 95% | Medium risk55 | —-0.072 |
| 15 | 25FD0022REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS ALONG ROLANDO R. ANDAYA HIGHWAY - K0322 + 682 - K0323 + 448, RAGAY, CAMARINES SUR | Region V | Camarines Sur 1st DEO | On-Going | ₱39.2M | 78% | Medium risk55 | —-0.069 |
| 16 | 25F00002ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-MAHARLIKA HIGHWAY-K0415+360-K0415+780, PAMPLONA, CAMARINES SUR (2ND LEGISLATIVE DISTRICT) | Region V | Region V | On-Going | ₱42.4M | 21% | Medium risk54 | —-0.051 |
| 17 | 22FE0060CSSP: SUSTAINABLE INFRA PROJ ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NAT'L ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONST OF DRAINAGE STRUCTURE ALONG MILAOR BYPASS ROAD, BRGY. SAN JOSE & TARUSANAN, MILAOR | Region V | Camarines Sur 2nd DEO | Completed | ₱28.8M | 100% | Medium risk54 | —-0.100 |
| 18 | 21FE0006OO1: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - MILAOR-PILI BYPASS ROAD, CAMARINES SUR | Region V | Camarines Sur 2nd DEO | Completed | ₱28.5M | 100% | Medium risk54 | —-0.100 |
| 19 | 22FE0029CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF BOCAL ROAD, BRGY. BOCAL, SAN FERNANDO, CAMARINES SUR | Region V | Camarines Sur 2nd DEO | Completed | ₱28.8M | 100% | Medium risk54 | —-0.100 |
| 20 | 22FE0063CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF HUBO ROAD, BRGY. HUBO, PASACAO, CAMARINES SUR | Region V | Camarines Sur 2nd DEO | Completed | ₱28.8M | 100% | Medium risk54 | —-0.100 |
| 21 | 23F00268CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-EVACUATION CENTERS/QUARANTINE FACILITIES/PUBLIC HEALTH FACILITIES-CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), BRGY. QUEZON, BAGAMANOC, CATANDUANES, BRGY. QUEZON, BA | Region V | Region V | On-Going | ₱14.6M | 91% | Medium risk54 | —-0.047 |
| 22 | 21FE0013(CLUSTERED PROJECTS) LP: LOCAL INFRASTRUCTURE PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE / FACILITIES - A. CONSTRUCTION (COMPLETION) (PHASE 2) OF MULTI-PURPOSE BUILDING (COVERED COURT), GAINZA CENTRAL SCHOOL, POBLACION, GAINZA, CAMARINES SUR, | Region V | Camarines Sur 2nd DEO | Completed | ₱27M | 100% | Medium risk53 | —-0.096 |
| 23 | 24FE0011CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF LIBMANAN CABUSAO PUMP IRRIGATION SYSTEM (LCPIS) MAIN CANAL | Region V | Camarines Sur 2nd DEO | Completed | ₱29.4M | 100% | Medium risk53 | —-0.100 |
| 24 | 23FD0013CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG KILBAY RIVER, DEL GALLEGO, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱72.4M | 100% | Medium risk53 | —-0.081 |
| 25 | 23FD0003ROAD WIDENING- PRIMARY ROADS, DAANG MAHARLIKA (LZ) - K0388+391 - K0388+990 | Region V | Camarines Sur 1st DEO | Completed | ₱23.5M | 100% | Medium risk53 | —-0.099 |