Contractor dossier
179 projects on file, including joint ventures this contractor is part of.
Total projects
179
Total budget
₱20.7B
Average progress
86.4%
Completion rate
67.0%
Below 70%
Average risk score
62.1
High risk on average, out of 100
Flagged as unusual
25
14.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 59 | ₱6B | 61.8 | 9 | 86.9% |
| Cordillera Administrative Region | 47 | ₱6.4B | 58.1 | 0 | 100.0% |
| Region I | 35 | ₱4B | 59.7 | 6 | 93.1% |
| Region IV-B | 32 | ₱3.8B | 69.0 | 8 | 61.1% |
| Region VII | 5 | ₱481M | 79.4 | 2 | 65.4% |
| Region XIII | 1 | ₱66.8M | 43.2 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 98 | ₱11.2B | 58.7 | 9 | 87.9% |
| Flood Control and Drainage | 64 | ₱7.7B | 60.2 | 4 | 89.7% |
| GAA 2025 OO-2 | 6 | ₱572.9M | 92.2 | 3 | 52.3% |
| GAA 2025 SSP | 5 | ₱433.3M | 95.2 | 5 | 54.6% |
| OTHER | 3 | ₱579M | 79.0 | 3 | 99.3% |
| GAA 2025 OO-1 | 2 | ₱134.7M | 92.1 | 1 | 61.5% |
| Bridges | 1 | ₱96.5M | 63.2 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25ED0041CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY CAMANSIHAN, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱96.2M | 87% | High risk95 | Flagged0.018 |
| 25ED0015CONSTRUCTION OF ROAD DIKE, BARANGAY BAGONG BUHAY, NAUJAN, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱95M | 71% | High risk95 | Flagged0.023 |
| 25ED0043CONSTRUCTION OF ROAD DIKE ALONG BAGTU RIVER, BARANGAY ARANGIN, NAUJAN, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱109.2M | 54% | High risk95 | Flagged0.032 |
| 25ED0016CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SITIO CAGUISIKAN, BARANGAY GUTAD, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱96.6M | 40% | High risk95 | Flagged0.031 |
| 25DP0083CSSP - SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR STREETLIGHTS, BARANGAY SAN LORENZO, SAN PABLO CITY, LAGUNA | Region IV-A | Laguna 3rd DEO | On-Going | ₱36.3M | 21% | High risk95 | Flagged0.017 |
| 25DK0071ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - MARIKINA-INFANTA RD K0125+500 - K0129+847 | Region IV-A | Quezon 1st DEO | On-Going | ₱96.6M | 88% | High risk94 | —-0.006 |
| 25ED0119CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SITIO AMUGUIS, BRGY. STA. RITA, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱142.7M | 4% | High risk93 | Flagged0.021 |
| 25ED0026CONSTRUCTION OF FLOOD CONTROL STRUCTURE, LONGOS BRIDGE 1ST APPROACH, DOWNSTREAM, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱95.2M | 40% | High risk93 | Flagged0.002 |
| 25HD0086ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONST/MAINT OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONST OF FLOOD MITIGATION STRUCTURE ALONG NAGA RIVER, PACKAGE 2, LUTAC - INAMOAN (LE | Region VII | Cebu 1st DEO | On-Going | ₱72.4M | 78% | High risk92 | —-0.011 |
| 25HD0087ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONST/MAINT OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONST OF FLOOD MITIGATION STRUCTURE ALONG NAGA RIVER, PACKAGE 3, LUTAC- INAMOAN (RIG | Region VII | Cebu 1st DEO | On-Going | ₱72.4M | 77% | High risk92 | —-0.011 |
| 25ED0120CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BRGY. STA. CRUZ, BACO, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱142.7M | 27% | High risk92 | Flagged0.015 |
| 25ED0121CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BRGY. LALUD, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱47.5M | 88% | High risk90 | —-0.013 |
| 25DK0062ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - MAUBAN-TIGNOAN RD K0120+790 - K0122+000 | Region IV-A | Quezon 1st DEO | On-Going | ₱38.1M | 35% | High risk90 | Flagged0.000 |
| 24A00355SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG SINUCALAN RIVER, BARANGAY TULIAO, SANTA BARBARA, PANGASINAN | Region I | Region I | Completed | ₱193M | 100% | High risk79 | Flagged0.002 |
| 24A00354SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG SINUCALAN RIVER, BARANGAY DALONGUE, SANTA BARBARA, PANGASINAN | Region I | Region I | Completed | ₱193M | 100% | High risk79 | Flagged0.003 |
| 24A00298SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BORIS RIVER, PACKAGE 1, BARANGAY PARIAN - BARANGAY TORRE 1ST, MANGATAREM, PANGASINAN | Region I | Region I | On-Going | ₱193M | 98% | High risk79 | Flagged0.022 |
| 24A00518SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SITIO PARATONG, BARANGAY POBLACION, BACNOTAN, LA UNION | Region I | Region I | On-Going | ₱144.7M | 73% | High risk77 | Flagged0.015 |
| 24HA0160CONSTRUCTION OF FLOOD MITIGATION STRUCTURES AT BARANGAY MALAYO NORTE TO BARANGAY LORETO ALONG ABATAN RIVER, CORTES, BOHOL | Region VII | Bohol 1st DEO | On-Going | ₱96M | 35% | High risk73 | Flagged0.046 |
| 24HA0161CONSTRUCTION OF FLOOD MITIGATION STRUCTURES AND DRAINANGE SYSTEM CONSTRUCTION IF VIGA FLOOD CONTROL STRUCTURE PHASE 2, ANTEQUERA, BOHOL | Region VII | Bohol 1st DEO | On-Going | ₱96M | 37% | High risk73 | Flagged0.045 |
| 24DK0185ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - LUCENA- TAYABAS-LUCBAN-SAMPALOC-MAUBAN PORT RD - K0133+085 - K0138+502, K0138+760 - K0141+120 | Region IV-A | Quezon 1st DEO | On-Going | ₱144.7M | 87% | High risk73 | Flagged0.033 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24HA0160CONSTRUCTION OF FLOOD MITIGATION STRUCTURES AT BARANGAY MALAYO NORTE TO BARANGAY LORETO ALONG ABATAN RIVER, CORTES, BOHOL | Region VII | Bohol 1st DEO | On-Going | ₱96M | 35% | High risk73 | Flagged0.046 |
| 24HA0161CONSTRUCTION OF FLOOD MITIGATION STRUCTURES AND DRAINANGE SYSTEM CONSTRUCTION IF VIGA FLOOD CONTROL STRUCTURE PHASE 2, ANTEQUERA, BOHOL | Region VII | Bohol 1st DEO | On-Going | ₱96M | 37% | High risk73 | Flagged0.045 |
| 24DK0186CSSP - SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF ROAD SAFETY DEVICES, JCT. MSR-OLD ZIGZAG RD - K0153+(-579) - K0153+(-502) (LS)...K0154+000 - K0154+348 (LS) | Region IV-A | Quezon 1st DEO | On-Going | ₱117M | 40% | High risk72 | Flagged0.041 |
| 24DK0185ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - LUCENA- TAYABAS-LUCBAN-SAMPALOC-MAUBAN PORT RD - K0133+085 - K0138+502, K0138+760 - K0141+120 | Region IV-A | Quezon 1st DEO | On-Going | ₱144.7M | 87% | High risk73 | Flagged0.033 |
| 25ED0043CONSTRUCTION OF ROAD DIKE ALONG BAGTU RIVER, BARANGAY ARANGIN, NAUJAN, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱109.2M | 54% | High risk95 | Flagged0.032 |
| 24A00654CONSTRUCTION OF MISSING LINKS/ NEW ROADS, PANGASINAN-NUEVA VIZCAYA ROAD - K0213+700 - K0214+140, K0214+380 - K0214+520, K0214+710 - K0215+460, K0216+865 - K0217+160 | Region I | Region I | On-Going | ₱168.5M | 70% | High risk64 | Flagged0.032 |
| 25ED0016CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SITIO CAGUISIKAN, BARANGAY GUTAD, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱96.6M | 40% | High risk95 | Flagged0.031 |
| 24A00653CONSTRUCTION OF MISSING LINKS/ NEW ROADS, PANGASINAN-NUEVA VIZCAYA ROAD, K0212+240 - K0213+580 | Region I | Region I | On-Going | ₱159.2M | 70% | High risk64 | Flagged0.029 |
| 24DK0182ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - MAUBAN-TIGNOAN RD - K0167 + 630 - K0169 + 830 | Region IV-A | Quezon 1st DEO | On-Going | ₱93.6M | 0% | High risk65 | Flagged0.025 |
| 25ED0015CONSTRUCTION OF ROAD DIKE, BARANGAY BAGONG BUHAY, NAUJAN, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱95M | 71% | High risk95 | Flagged0.023 |
| 24A00298SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BORIS RIVER, PACKAGE 1, BARANGAY PARIAN - BARANGAY TORRE 1ST, MANGATAREM, PANGASINAN | Region I | Region I | On-Going | ₱193M | 98% | High risk79 | Flagged0.022 |
| 25ED0119CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SITIO AMUGUIS, BRGY. STA. RITA, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱142.7M | 4% | High risk93 | Flagged0.021 |
| 25ED0041CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY CAMANSIHAN, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱96.2M | 87% | High risk95 | Flagged0.018 |
| 25DP0083CSSP - SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR STREETLIGHTS, BARANGAY SAN LORENZO, SAN PABLO CITY, LAGUNA | Region IV-A | Laguna 3rd DEO | On-Going | ₱36.3M | 21% | High risk95 | Flagged0.017 |
| 24A00518SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SITIO PARATONG, BARANGAY POBLACION, BACNOTAN, LA UNION | Region I | Region I | On-Going | ₱144.7M | 73% | High risk77 | Flagged0.015 |
| 25ED0120CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BRGY. STA. CRUZ, BACO, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱142.7M | 27% | High risk92 | Flagged0.015 |
| 25E00202BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE/ESPLANADFE ALONG PATRICK RIVER (UPSTREAM), BRGY. SAN FRANCISCO-BRGY. PAETAN SECTION, STA. 000+668.34-STA. 001+000 ( | Region IV-B | Region IV-B | On-Going | ₱236.9M | 9% | High risk69 | Flagged0.013 |
| 24DK0184ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - MAUBAN-TIGNOAN RD - K0164 + 430 - K0167 + 630 | Region IV-A | Quezon 1st DEO | On-Going | ₱140.4M | 94% | High risk69 | Flagged0.011 |
| 24DK0188ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - MAUBAN-TIGNOAN RD - K0161 + 230 - K0164 + 430 | Region IV-A | Quezon 1st DEO | On-Going | ₱140.4M | 93% | High risk69 | Flagged0.011 |
| 24DK0187ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - MAUBAN-TIGNOAN RD - K0159 + (-966) - K0161 + 230 | Region IV-A | Quezon 1st DEO | On-Going | ₱140.4M | 87% | High risk69 | Flagged0.010 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 151 | 23DK0032ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - MARIKINA-INFANTA RD - K0095 + 200 - K0095 + 280 | Region IV-A | Quezon 1st DEO | Completed | ₱72.4M | 100% | Medium risk54 | —-0.100 |
| 152 | 23DK0010ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION-REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDES-SECONDARY ROADS-FAMY-REAL-INFANTA DINAHICAN PORT RD - K0122+390 - K0112+430 | Region IV-A | Quezon 1st DEO | Completed | ₱57.9M | 100% | Medium risk54 | —-0.102 |
| 153 | 23DL0172ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE, PRIMARY ROADS 2. DAANG MAHARLIKA (LZ) K0154+858 - K0155+000, BRGY. MAL | Region IV-A | Quezon 4th DEO | Completed | ₱57.9M | 100% | Medium risk54 | —-0.102 |
| 154 | 23AF0203CONST/REHAB OF FLOOD MITIGATION FACILITIES W/IN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONST. OF FLOOD CONTROL STRUC. ALONG ARINGAY RIVER BASIN, BRGY. SAN SIMON WEST, ARINGAY, LA UNION | Region I | La Union 2nd DEO | Completed | ₱77.2M | 100% | Medium risk53 | —-0.007 |
| 155 | 24AF0111CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BAUANG RIVER BASIN (PACKAGE 4), BAUANG, LA UNION | Region I | La Union 2nd DEO | Completed | ₱89.7M | 100% | Medium risk52 | —-0.056 |
| 156 | 23AF0207CONST/REHAB OF FLOOD MITIGATION FACILITIES W/IN MAJOR BASINS AND PRINCIPAL RIVERS - CONST OF FLOOD CONTROL STRUCTURE ALONG BAUANG RIVER BASIN, BRGY. GUESSET, NAGUILIAN, LA UNION | Region I | La Union 2nd DEO | Completed | ₱72.4M | 100% | Medium risk52 | —-0.008 |
| 157 | 24AF0113CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BAUANG RIVER BASIN (PACKAGE 6), BAUANG, LA UNION | Region I | La Union 2nd DEO | Completed | ₱89.7M | 100% | Medium risk52 | —-0.056 |
| 158 | 24AF0110CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BAUANG RIVER BASIN (PACKAGE 3), BAUANG, LA UNION | Region I | La Union 2nd DEO | Completed | ₱89.7M | 100% | Medium risk52 | —-0.056 |
| 159 | 24AF0112CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BAUANG RIVER BASIN (PACKAGE 5), BAUANG, LA UNION | Region I | La Union 2nd DEO | Completed | ₱89.7M | 100% | Medium risk52 | —-0.056 |
| 160 | 24AF0109CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BAUANG RIVER BASIN (PACKAGE 2), BAUANG, LA UNION | Region I | La Union 2nd DEO | Completed | ₱89.7M | 100% | Medium risk52 | —-0.057 |
| 161 | 24AF0108CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BAUANG RIVER BASIN (PACKAGE 1), BAUANG, LA UNION | Region I | La Union 2nd DEO | Completed | ₱89.7M | 100% | Medium risk52 | —-0.057 |
| 162 | 25DK0069OO 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - FAMY-REAL-INFANTA- DINAHICAN PORT RD - K0130+500 - K0132+500, QUEZON | Region IV-A | Quezon 1st DEO | On-Going | ₱48.4M | 35% | Medium risk51 | —-0.057 |
| 163 | 24D00124REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - PRIMARY ROADS DAANG MAHARLIKA (L/Z) - K0156+815 - K0156+862.53 | Region IV-A | Region IV-A | On-Going | ₱49.5M | 100% | Medium risk51 | —-0.073 |
| 164 | 23A00268CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG THE PRINCIPE RIVER, AGOO, LA UNION (PACKAGE 1) | Region I | Region I | Completed | ₱72.4M | 100% | Medium risk50 | —-0.063 |
| 165 | 23A00269CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG THE PRINCIPE RIVER, AGOO, LA UNION (PACKAGE 2) | Region I | Region I | Completed | ₱72.4M | 100% | Medium risk50 | —-0.063 |
| 166 | 23AF0101CONST. OF FLOOD CONTROL STRUCTURES ALONG THE ARINGAY RIVER BASIN, ARINGAY,LA UNION (PACKAGE 2), ARINGAY, LA UNION | Region I | La Union 2nd DEO | Completed | ₱72.3M | 100% | Medium risk50 | —-0.064 |
| 167 | 23AF0103CONST. OF FLOOD CONTROL STRUCTURES ALONG THE ARINGAY RIVER BASIN, ARINGAY,LA UNION (PACKAGE 4), ARINGAY, LA UNION | Region I | La Union 2nd DEO | Completed | ₱72.3M | 100% | Medium risk50 | —-0.064 |
| 168 | 23AF0100CONST. OF FLOOD CONTROL STRUCTURE ALONG THE ARINGAY RIVER BASIN, ARINGAY,LA UNION (PACKAGE 1), ARINGAY, LA UNION | Region I | La Union 2nd DEO | Completed | ₱72.3M | 100% | Medium risk50 | —-0.064 |
| 169 | 23AF0102CONST. OF FLOOD CONTROL STRUCTURES ALONG THE ARINGAY RIVER BASIN, ARINGAY,LA UNION (PACKAGE 3), ARINGAY, LA UNION | Region I | La Union 2nd DEO | Completed | ₱72.3M | 100% | Medium risk50 | —-0.064 |
| 170 | 22P00125ORGANIZATIONAL OTCOME 1: ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS MARCOS HIGHWAY, KO272+800 - KO272+909TUBA, BENGUET | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱48.3M | 100% | Medium risk48 | —-0.080 |
| 171 | 24DK0057ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE -TERTIARY ROADS-LUCBAN-MAJAYJAY ROAD, K0124+080-K0124+600, LUCBAN, QUEZON | Region IV-A | Quezon 1st DEO | Completed | ₱28.9M | 100% | Medium risk47 | —-0.106 |
| 172 | 24DK0056ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-TERTIARY ROADS LUCBAN-MAJAYJAY ROAD, K0123+570-K0124+080, LUCBAN, QUEZON | Region IV-A | Quezon 1st DEO | Completed | ₱28.9M | 100% | Medium risk47 | —-0.106 |
| 173 | 23DL0171ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE, PRIMARY ROADS 3. DAANG MAHARLIKA (LZ) K0154+000 - K0154+040, BRGY. MAL | Region IV-A | Quezon 4th DEO | Completed | ₱39.2M | 100% | Medium risk47 | —-0.106 |
| 174 | 23DJ0056CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROAD AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, REHABILITATION OF SLOPE PROTECTION STRUCTUR | Region IV-A | Quezon 2nd DEO | Completed | ₱24.5M | 100% | Medium risk46 | —-0.109 |
| 175 | 25ED0017CONSTRUCTION OF SEAWALL STRUCTURE, SITIO PROPER, BARANGAY NAVOTAS, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱66.5M | 29% | Medium risk46 | —-0.021 |