Opening the dossier…
Opening the dossier…
Contractor dossier
89 projects on file, including joint ventures this contractor is part of.
Total projects
89
Total budget
₱979.4M
Average progress
97.0%
Completion rate
88.8%
Average risk score
36.4
Medium risk on average, out of 100
Flagged as unusual
2
2.2% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VII | 89 | ₱979.4M | 36.4 | 2 | 97.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 45 | ₱565.7M | 38.3 | 0 | 97.2% |
| Buildings and Facilities | 33 | ₱204.1M | 28.6 | 0 | 99.6% |
| Bridges | 4 | ₱52.9M | 39.6 | 0 | 90.9% |
| Water Provision and Storage | 3 | ₱62.5M | 44.7 | 0 | 100.0% |
| Flood Control and Drainage | 2 | ₱62.9M | 47.2 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱11.8M | 94.1 | 1 | 41.1% |
| GAA 2025 OO-1 | 1 | ₱19.6M | 90.6 | 1 | 70.6% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25HA0051CONSTRUCTION OF FATIMA BRIDGE, BARANGAY FATIMA, CORTES, BOHOL | Region VII | Bohol 1st DEO | On-Going | ₱11.8M | 41% | High risk94 | Flagged0.026 |
| 25HC0053ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- BRIDGE PROGRAM- WIDENING OF PERMANENT BRIDGES - BACANI BR. (B00216BH) ALONG THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL RD, CLARIN, BOHOL | Region VII | Bohol 2nd DEO | On-Going | ₱19.6M | 71% | High risk91 | Flagged0.010 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25HA0051CONSTRUCTION OF FATIMA BRIDGE, BARANGAY FATIMA, CORTES, BOHOL | Region VII | Bohol 1st DEO | On-Going | ₱11.8M | 41% | High risk94 | Flagged0.026 |
| 25HC0053ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- BRIDGE PROGRAM- WIDENING OF PERMANENT BRIDGES - BACANI BR. (B00216BH) ALONG THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL RD, CLARIN, BOHOL | Region VII | Bohol 2nd DEO | On-Going | ₱19.6M | 71% | High risk91 | Flagged0.010 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 19HC0012BUILDING AND OTHER STRUCTURES- MULTIPURPOSE/FACILITIES- NATIONAL BUILDING PROGRAM: CONSTRUCTION OF DPWH STAFF HOUSE INCLUDING OTHER FACILITIES, AT DPWH-BOHOL 2ND DISTRICT ENGINEERING OFFICE, UBAY, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱13.9M | 100% | Medium risk43 | —-0.092 |
| 52 | 20HC0043CONSTRUCTION OF BOHOL 2ND DISTRICT ENGINEERING OFFICE FACILITIES, BOOD, UBAY, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱9.7M | 100% | Medium risk42 | —-0.093 |
| 53 | 22HA0184CONSTRUCTION OF 1STY-2CL, DE LA PAZ HIGH SCHOOL, CORTES, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱7.1M | 100% | Medium risk42 | —-0.052 |
| 54 | 22HA0021CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY LORETO, CORTES, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱4.7M | 100% | Medium risk41 | —-0.095 |
| 55 | 23HA0105CONCRETING OF BRGY. LOURDES FMR, BRGY. LOURDES, CORTES, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱11.9M | 100% | Medium risk41 | —-0.042 |
| 56 | 18HC0163MODIFIED STANDARD DPWH-DEPED TWO (2) STOREY TEN (10) CLASSROOM SCHOOL BUILDING (REGULAR WORKSHOP) AT SAN AGUSTIN NHS, SAGBAYAN (BORJA), BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱20.6M | 100% | Medium risk41 | —-0.049 |
| 57 | 22HC0038SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD AT BARANGAY CANMANO, SAGBAYAN, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱4.7M | 100% | Medium risk41 | —-0.097 |
| 58 | 22HC0013CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS- ACCESS ROAD LEADING TO TUNTONAN HIGHLAND, BRGY. TONTUNAN, CLARIN, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱4.7M | 100% | Medium risk40 | —-0.098 |
| 59 | 21HC0049CONVERGENCE AND SPECIAL SUPPORT PROGRAM- CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES- LUBANG-NUEVA MONTANA-BUNGA ROAD CONNECTING TAGBILARAN NORTH ROAD TO DANAO-GETAFE ROAD, BUENAVISTA, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱4.7M | 100% | Medium risk40 | —-0.097 |
| 60 | 18HC0152MODIFIED STANDARD DPWH-DEPED TWO (2) STOREY (4) CLASSROOM SCHOOL BUILDING (SCIENCE LABORATORY & ICT LABORATORY) ATSAN AGUSTIN NHS, SAGBAYAN (BORJA), BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱10.2M | 100% | Medium risk40 | —-0.053 |
| 61 | 18HC0161MODIFIED STANDARD DPWH-DEPED TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING (REGULAR WORKSHOP) AT SAN AGUSTIN NHS, SAGBAYAN (BORJA), BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱10.2M | 100% | Medium risk40 | —-0.053 |
| 62 | 23HB0127CONCRETING OF BRGY. ILAUD TO BRGY. LUMBAY FMR, BRGY. ILAUD AND BRGY. LUMBAY, PILAR, BOHOL STA.0+000.00-STA.0+640.00, | Region VII | Bohol 3rd DEO | Completed | ₱11.9M | 100% | Medium risk39 | —-0.041 |
| 63 | 19HC0195CONCRETING OF BRGY. LA ESPERANZA- BRGY. CANOLING FMR, BRGY. LA ESPERANZA AND BRGY CANOLING, DAGOHOY, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱4.7M | 100% | Medium risk34 | —-0.043 |
| 64 | 24HA0021REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - JCT (TNR) CORTES-BALILIHAN-CATIGBIAN-MACAAS RD - K0012 + 521 - K0012 + 710, K0045 + 655 - K00455 + 666, K0045 + 745 - K0045 + 752 | Region VII | Bohol 1st DEO | Completed | ₱3.2M | 100% | Low risk22 | —-0.096 |
| 65 | 19HC0017001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE-REHABILITATION/MAJOR REPAIR OF PERMANENTBRIDGES-CANSUA-OB BR. (B00046BH) ALONG SAGBAYAN-DANAO ROAD, INABANGA, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱4.6M | 100% | Low risk22 | —-0.058 |
| 66 | 23HA0012CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES - LA PAZ (CORTES)-CABAGUAN-LOURDES-ANISLAG (CORELLA) ROAD IN SUPPORT OF THE AGRIBUSINESS INDUSTRY, CORTES, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱2.4M | 100% | Low risk21 | —-0.094 |
| 67 | 20HC0049CONSTRUCTION OF ROAD, BRGY. POBLACION, SAGBAYAN, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱3.7M | 100% | Low risk20 | —-0.095 |
| 68 | 21HC0013ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT- ROAD WIDENING- SECONDARY ROADS: JCT(LIR) CARMEN-SAGBAYAN-BACANI RD - K0179+100 - K0179+350, SAGBAYAN BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱3.5M | 100% | Low risk20 | —-0.097 |
| 69 | 21HC0009ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- ASSET PRESERVATION PROGRAM- REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS- TERTIARY ROADS- SAGBAYAN-DANAO RD- K0094+630-K0094+713, K0097+390-K0097+484, DANAO, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱3.5M | 100% | Low risk20 | —-0.097 |
| 70 | 25HB0034ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS - JCT. DAT-AN-CARMEN-SIERRA BULLONES-PILAR-ALICIA RD - K0069+971 - K0070+000 | Region VII | Bohol 3rd DEO | On-Going | ₱1.1M | 36% | Low risk19 | —-0.042 |
| 71 | 18HC0011ASSET PRESERVATION-SLAB REPLACEMENT/ CONCRETE REBLOCKING AT JCT (LIR) BUENAVISTA-CARMEN-DANAO-GETAFE ROAD, K0173+039-K0173+289, DANAO, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱1.9M | 100% | Low risk18 | —-0.092 |
| 72 | 19HC0002001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- ASSET PRESERVATION OF NATIONAL ROADS: ASSET PRESERVATION- PREVENTIVE MAINTENANCE-TERTIARY ROADS JCT. (LIR) BUENAVISTA, CARMEN-DANAO-JETAFE ROAD,K0201+030-K0201+131, JETAFE BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱948K | 100% | Low risk18 | —-0.092 |
| 73 | 20HC0007001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- ASSET PRESERVATION PROGRAM- REHABILITATION/ RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS, SAGBAYAN- DANAO RD K0077+(-050) - K007 | Region VII | Bohol 2nd DEO | Completed | ₱1.9M | 100% | Low risk16 | —-0.096 |
| 74 | 18HC0088CONSTRUCTION OF ROADS, BARANGAY SAGBAYAN SUR, SAGBAYAN, BOHOL STA.000+000-STA.000+263 | Region VII | Bohol 2nd DEO | Completed | ₱1.9M | 100% | Low risk16 | —-0.094 |
| 75 | 21HC0158CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. POBLACION, SAGBAYAN, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱2.9M | 100% | Low risk16 | —-0.095 |