Contractor dossier
2 projects on file, including joint ventures this contractor is part of.
Total projects
2
Total budget
₱138.8M
Average progress
100.0%
Completion rate
100.0%
Average risk score
61.8
High risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Central Office | 1 | ₱53.5M | 70.8 | 0 | 100.0% |
| National Capital Region | 1 | ₱85.3M | 52.7 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 2 | ₱138.8M | 61.8 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 22O00082CONSTRUCTION OF FLOOD CONTROL STRUCTURE AND TRIBUTARIES, BRGY. COMMONWEALTH, QUEZON CITY | Central Office | Flood Control Management Cluster | Completed | ₱53.5M | 100% | High risk71 | —-0.078 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 22O00082CONSTRUCTION OF FLOOD CONTROL STRUCTURE AND TRIBUTARIES, BRGY. COMMONWEALTH, QUEZON CITY | Central Office | Flood Control Management Cluster | Completed | ₱53.5M | 100% | High risk71 | —-0.078 |
| 2 | 22OC0006CONSTRUCTION OF GROUNDSILL/REVETMENT WALL ALONG CALATAGAN CREEK, BRGY. PALANANMAKATI CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | Completed | ₱85.3M | 100% | Medium risk53 | —-0.078 |