Contractor dossier
32 projects on file, including joint ventures this contractor is part of.
Total projects
32
Total budget
₱220.4M
Average progress
97.2%
Completion rate
87.5%
Average risk score
34.3
Medium risk on average, out of 100
Flagged as unusual
2
6.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region V | 23 | ₱173.1M | 33.8 | 1 | 96.1% |
| Region VII | 8 | ₱44.4M | 37.2 | 1 | 100.0% |
| National Capital Region | 1 | ₱2.9M | 23.9 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 15 | ₱56.8M | 28.8 | 0 | 100.0% |
| Roads | 10 | ₱79.1M | 35.5 | 1 | 97.5% |
| Flood Control and Drainage | 4 | ₱15.6M | 29.3 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱19.5M | 94.6 | 1 | 35.3% |
| OTHER | 1 | ₱48.4M | 78.8 | 0 | 100.0% |
| Water Provision and Storage | 1 | ₱959.9K | 20.4 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25FF0050BIP;ACCESS ROADS &/OR BRIDGES FROM THE NATL. ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES-ROAD CONCRETING,BRGY. BIGAAS-SITIO BIGONG CALABANGA CAMARINES SUR | Region V | Camarines Sur 3rd DEO | On-Going | ₱19.5M | 35% | High risk95 | Flagged0.016 |
| 23FF0030002:FLOOD MANAGEMENT PROGRAM CONST. /MAINT. OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEM CONST. OF BOMBON FLOOD CONTROL BOMBON CAMARINES SUR | Region V | Camarines Sur 3rd DEO | On-Going | ₱48.4M | 100% | High risk79 | —-0.000 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25FF0050BIP;ACCESS ROADS &/OR BRIDGES FROM THE NATL. ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES-ROAD CONCRETING,BRGY. BIGAAS-SITIO BIGONG CALABANGA CAMARINES SUR | Region V | Camarines Sur 3rd DEO | On-Going | ₱19.5M | 35% | High risk95 | Flagged0.016 |
| 24HH0105CONCRETING OF BRGY. LUSARAN FMR, BRGY. LUSARAN, CEBU CITY | Region VII | Cebu City DEO | On-Going | ₱14.9M | 100% | Medium risk47 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 18FN0022CONCRETING OF BARANGAY ROAD, BARANGAY STA. CRUZ, CABUSAO, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱940.5K | 100% | Low risk20 | —-0.093 |
| 27 | 20FD0030CONCRETING OF BARANGAY ROAD, CASTILLO, CABUSAO, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱1.9M | 100% | Low risk19 | —-0.100 |
| 28 | 19FN0018REBLOCKING OF ROAD, BRGY. NEW POBLACION, CABUSAO, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱1.9M | 100% | Low risk19 | —-0.097 |
| 29 | 21HH0172LOCAL PROGRAM: LOCAL INFRASTRUCTURE PROGRAM -BUILDINGS AND OTHER STRUCTURES - MULTI PURPOSE / FACILITIES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LUZ, CEBU CITY | Region VII | Cebu City DEO | Completed | ₱2.5M | 100% | Low risk19 | —-0.096 |
| 30 | 19FF0119CY-2019 LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION OF MULTI-PURPOSE BUILDINGBARANGAY MINORO, SAN JOSE, CAMARINES SUR | Region V | Camarines Sur 4th DEO | Completed | ₱1.4M | 100% | Low risk17 | —-0.097 |
| 31 | 19FF0125CY-2019 LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION OF MULTI-PURPOSE BUILDINGBARANGAY PANAGAN, TIGAON, CAMARINES SUR | Region V | Camarines Sur 4th DEO | Completed | ₱469.4K | 100% | Low risk17 | —-0.093 |
| 32 | 19FE0056EXTENSION OF MULTI-PURPOSE BUILDING (COVERED COURT) BRGY. BONOT-STA. ROSA, CALABANGA, CAMARINES SUR | Region V | Camarines Sur 3rd DEO | Completed | ₱940K | 100% | Low risk14 | —-0.095 |