Contractor dossier
254 projects on file, including joint ventures this contractor is part of.
Total projects
254
Total budget
₱946.6M
Average progress
99.8%
Completion rate
99.2%
Average risk score
24.3
Low risk on average, out of 100
Flagged as unusual
2
0.8% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IX | 254 | ₱946.6M | 24.3 | 2 | 99.8% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 171 | ₱497.5M | 18.0 | 1 | 100.0% |
| Roads | 56 | ₱370.9M | 42.7 | 0 | 100.0% |
| Water Provision and Storage | 21 | ₱52.7M | 22.7 | 0 | 100.0% |
| Bridges | 3 | ₱17.1M | 38.6 | 1 | 84.6% |
| Flood Control and Drainage | 2 | ₱6.9M | 38.2 | 0 | 100.0% |
| OTHER | 1 | ₱1.5M | 33.3 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 16JB0055ASSET PRESERVATION OF NATIONAL ROAD CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS DIPOLOG-SINDANGAN- LILOY ROAD, K 1917+500-K 1917+1400. | Region IX | Zamboanga del Norte 2nd DEO | Completed | ₱6.8M | 100% | High risk64 | —-0.054 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 20JA0007WIDENING OF PERMANENT BRIDGES - JOHNSTON BR. (B01173MN) ALONG RT LIM BLVD | Region IX | Zamboanga City 2nd DEO | On-Going | ₱12.6M | 54% | Medium risk56 | Flagged0.022 |
| 17JG0169CONSTRUCTION OF ONE (1) STOREY - TWO (2) CLASSROOM SCHOOL BUILDING WITH TOILET ATTACHED AT BOLISONG ES, KUMALARANG, ZAMBOANGA DEL SUR | Region IX | Zamboanga del Sur 2nd DEO | Completed | ₱3.4M | 100% | Low risk8 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 16JB0055ASSET PRESERVATION OF NATIONAL ROAD CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS DIPOLOG-SINDANGAN- LILOY ROAD, K 1917+500-K 1917+1400. | Region IX | Zamboanga del Norte 2nd DEO | Completed | ₱6.8M | 100% | High risk64 | —-0.054 |
| 2 | 20JA0007WIDENING OF PERMANENT BRIDGES - JOHNSTON BR. (B01173MN) ALONG RT LIM BLVD | Region IX | Zamboanga City 2nd DEO | On-Going | ₱12.6M | 54% | Medium risk56 | Flagged0.022 |
| 3 | 20JC0064ROAD CONCRETING, BONGALAO, SIBUCO, ZAMBOANGA DEL NORTE | Region IX | Zamboanga del Norte 3rd DEO | Completed | ₱9.8M | 100% | Medium risk55 | —-0.079 |
| 4 | 21JC0004CONSTRUCTION OF MULTI-PURPOSE BUILDING (TRAINING AND LIVELIHOOD CENTER, SIBUCO, ZAMBOANGA DEL NORTE | Region IX | Zamboanga del Norte 3rd DEO | Completed | ₱9.9M | 100% | Medium risk53 | —-0.077 |
| 5 | 21JC0017REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD - K2115 + 280 - K2115 + 320, ZN. | Region IX | Zamboanga del Norte 3rd DEO | Completed | ₱4.9M | 100% | Medium risk53 | —-0.081 |
| 6 | 21JC0045CONCRETING OF BARANGAY ROAD, SAN JOSE, BALIGUIAN, ZAMBOANGA DEL NORTE | Region IX | Zamboanga del Norte 3rd DEO | Completed | ₱9.5M | 100% | Medium risk52 | —-0.082 |
| 7 | 20JC0073ROAD CONCRETING - FATIMA, LILOY, ZAMBOANGA DEL NORTE | Region IX | Zamboanga del Norte 3rd DEO | Completed | ₱14.9M | 100% | Medium risk51 | —-0.085 |
| 8 | 21JC0039CONSTRUCTION OF BOX CULVERT AT SANDAYONG, TAMPILISAN, ZAMBOANGA DEL NORTE | Region IX | Zamboanga del Norte 3rd DEO | Completed | ₱5M | 100% | Medium risk51 | —-0.073 |
| 9 | 21JC0035CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL - IT), SAN ROQUE-OVERVIEW ROAD IN SUPPORT TO RUBBER AND COCONUT INDUSTRIES, LILOY, Z | Region IX | Zamboanga del Norte 3rd DEO | Completed | ₱14.7M | 100% | Medium risk51 | —-0.086 |
| 10 | 21JF0008CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUTRIES AND ECONOMIC ZONES - ROAD CONNECTING JUNCTION NATIONAL HIGHWAY AT BRGY. COLORAN TO BRGY. PARUK IN SUPPORT OF RUBBER INDUSTRY, SIAY, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱7.2M | 100% | Medium risk50 | —-0.085 |
| 11 | 20JF0086IMPROVEMENT/ CONSTRUCTION/ CONCRETING OF LABASAN-CAMANGA-ROAD (PHASE III), BRGY. BAGONG SILANG, SIAY, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱9.5M | 100% | Medium risk50 | —-0.086 |
| 12 | 20JF0036CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES - ROAD CONNECTING JUNCTION NATIONAL HIGHWAY AT BRGY. MIRANGAN TO BRGY. BALUCANAN IN SUPPORT OF CALAMANSI PROCESSING, SIAY, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱8.6M | 100% | Medium risk50 | —-0.086 |
| 13 | 20JF0034CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES - ROADS CONNECTING JUNCTION NATIONAL HIGHWAY AT BRGY. COLORAN TO BRGY. PARUK IN SUPPORT OF RUBBER INDUSTRY, SIAY, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱8.5M | 100% | Medium risk50 | —-0.086 |
| 14 | 21JC0057CONSTRUCTION OF PUBLIC MARKET, SALUG, ZAMBOANGA DEL NORTE | Region IX | Zamboanga del Norte 3rd DEO | Completed | ₱19.6M | 100% | Medium risk50 | —-0.081 |
| 15 | 20JF0082CONSTRUCTION OF LOCAL ROAD PHASE II, BRGY. MALAGANDIS, TITAY, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱14.5M | 100% | Medium risk50 | —-0.085 |
| 16 | 21JF0009CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES - ROAD CONNECTING JUNCTION NATIONAL HIGHWAY AT BRGY. DACANAY TO BRGY. SUMAMA IN SUPPORT OF RUBBER AND COCONUT INTUSTRY, SIAY, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱7.2M | 100% | Medium risk50 | —-0.085 |
| 17 | 21JF0001CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - JCT. LANAO-PAGADIAN-ZAMBOANGA CITY LEADING TO LOG POND WHARF (JUMP OFF POINT TO SIAY-KABASALAN WETLANDS), SIAY, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱7.2M | 100% | Medium risk50 | —-0.085 |
| 18 | 20JF0023CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATION - JCT. LANAO-PAGADIAN-ZAMBOANGA CITY LEADING TO LOG POND WHARF (JUMP OFF POINT TO SIAY-KABASALAN WETLANDS), SIAY, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱8.5M | 100% | Medium risk50 | —-0.085 |
| 19 | 21JF0003CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - NRJ LEADING TO MANGROOVE AREAS AND BAT KINGDOM, SIAY, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱7.2M | 100% | Medium risk50 | —-0.085 |
| 20 | 20JF0028CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - NRJ LEADING TO MANGROVE AREAS AND BAT KINGDOM, SIAY, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱8.5M | 100% | Medium risk50 | —-0.086 |
| 21 | 20JF0084CONSTRUCTION OF LOCAL ROAD, TAROMA ST., BRGY. DON ANDRES, IPIL, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱9.5M | 100% | Medium risk50 | —-0.086 |
| 22 | 21JC0048CONCRETING OF BARANGAY ROAD, SITIO PIOS, MANGOP, LEON B. POSTIGO, ZAMBOANGA DEL NORTE | Region IX | Zamboanga del Norte 3rd DEO | Completed | ₱9.9M | 100% | Medium risk50 | —-0.086 |
| 23 | 19JF0115CONCRETING OF BANGCO FMR, BRGY. BANGCO, TITAY, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱4.9M | 100% | Medium risk49 | —-0.082 |
| 24 | 20JC0066ROAD CONCRETING, LIMBONGA, GODOD, ZAMBOANGA DEL NORTE | Region IX | Zamboanga del Norte 3rd DEO | Completed | ₱8.8M | 100% | Medium risk49 | —-0.086 |
| 25 | 20JC0037CONSTRUCTION OF MULTI-PURPOSE BUILDING, LILOY, ZAMBOANGA DEL NORTE | Region IX | Zamboanga del Norte 3rd DEO | Completed | ₱8.9M | 100% | Medium risk49 | —-0.082 |