163 projects on file, including joint ventures this contractor is part of.
Total projects
163
Total budget
₱1.1B
Average progress
99.4%
Completion rate
98.2%
Average risk score
19.4
Low risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 163 | ₱1.1B | 19.4 | 0 | 99.4% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 88 | ₱395.7M | 15.3 | 0 | 98.9% |
| Roads | 67 | ₱571M | 23.8 | 0 | 100.0% |
| Bridges | 7 | ₱58.5M | 27.1 | 0 | 100.0% |
| Flood Control and Drainage | 1 | ₱91.6M | 41.2 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Nothing to report.
No high-risk projects here.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 101 | 18CG0102LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION OF SAN JUAN MULTI-PURPOSE BUILDING (COVERED COURT), SAN SIMON, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱3.8M | 100% | Low risk12 | —-0.106 |
| 102 | 18CG0247LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION OF BARANGAY STA. CRUZ PAMBILOG E/S MULTI PURPOSE BUILDING (COVERED COURT), SAN LUIS, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱3.8M | 100% | Low risk12 | —-0.106 |
| 103 | 19CG0039LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION OF MULTI - PURPOSE BUILDING (COVERED COURT), BRGY. STA. CATALINA, SAN LUIS PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱3.8M | 100% | Low risk12 | —-0.106 |
| 104 | 19CG0037LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION OF MULTI - PURPOSE BUILDING (STA. CRUZ POBLACION COVERED COURT), BRGY. STA. CRUZ POBLACION, SAN LUIS, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱3.8M | 100% | Low risk12 | —-0.106 |
| 105 | 18CG0039LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION OF SAN ROQUE MULTI-PURPOSE COVERED COURT, SAN ROQUE, SAN LUIS, PAMPANGA, SAN LUIS, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱3.7M | 100% | Low risk12 | —-0.107 |
| 106 | 18CG0313LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION OF SAN ROQUE H/S MULTI-PURPOSE BUILDING (COVERED COURT), SAN LUIS, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱3.8M | 100% | Low risk12 | —-0.107 |
| 107 | 18CG0163LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION OF SAN CARLOS COVERED COURT, SAN LUIS, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱3.8M | 100% | Low risk12 | —-0.106 |
| 108 | 18CG0226LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION OF COVERED COURT, STA. MARIA HIGH SCHOOL, BRGY. STA. MARIA, MINALIN, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱3.8M | 100% | Low risk12 | —-0.104 |
| 109 | 18CG0297LOCAL INFRASTRUCTURE PROGRAM - REHABILITATION / IMPROVEMENT / COMPLETION OF PALIGUI MULTI-PURPOSE BUILDING (COVERED COURT), CANDABA, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱3.3M | 100% | Low risk12 | —-0.107 |
| 110 | 18CG0077CONSTRUCTION OF MULTI-PURPOSE BUILDING, SAN NICOLAS, STA. ANA, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱3.3M | 100% | Low risk12 | —-0.104 |
| 111 | 21CG0154LOCAL INFRASTRUCTURE PROGRAM: BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/ FACILITIES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY STA. CRUZ PAMBILOG, SAN LUIS,PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱3.3M | 100% | Low risk12 | —-0.106 |
| 112 | 19CG0079REHABILITATION /REPAIR / IMPROVEMENT OF MULTI-PURPOSE BUILDING (TULAOC COVERED COURT) BARANGAY SAN AGUSTIN, SAN SIMON, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱3.3M | 100% | Low risk12 | —-0.107 |
| 113 | 19CG0119REHABILITATION OF PANSINAO BRIDGE AND APPROACHES, CANDABA, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱1.9M | 100% | Low risk11 | —-0.066 |
| 114 | 22CG0115BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION (REHABILITATION) OF SAN ISIDRO MULTI-PURPOSE BUILDING, BARANGAY SAN ISIDRO, SAN LUIS, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱2.8M | 100% | Low risk11 | —-0.104 |
| 115 | 20CG0175LOCAL INFRASTRUCTURE PROGRAM: BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/ FACILITIES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SAN JOSE, SAN LUIS, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱2.8M | 100% | Low risk11 | —-0.105 |
| 116 | 24CG0160BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SAN NICOLAS, MASANTOL, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱2.8M | 100% | Low risk11 | —-0.104 |
| 117 | 18CG0128REHABILITATION/IMPROVEMENT OF THE MULTI-PURPOSE CENTER AT KALSADANG BAYU, BARANGAY SAN NICOLAS, MASANTOL, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱2.8M | 100% | Low risk11 | —-0.104 |
| 118 | 22CG0243SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - REHABILITATION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY STO. ROSARIO PAU, STO. TOMAS, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱2.8M | 100% | Low risk11 | —-0.104 |
| 119 | 20CG0276LOCAL INFRASTRUCTURE PROGRAM: MULTIPURPOSE/FACILITIES- CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. SAN MATIAS, SANTO TOMAS, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱2.8M | 100% | Low risk11 | —-0.104 |
| 120 | 22CG0228SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - REHABILITATION (COMPLETION) OF MULTI-PURPOSE BUILDING (SAN MATIAS ELEMENTARY SCHOOL), BARANGAY SAN MATIAS, STO. TOMAS, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱2.8M | 100% | Low risk11 | —-0.104 |
| 121 | 21CG0148LOCAL INFRASTRUCTURE PROGRAM: BUILDING AND OTHER STRUCTURES: MULTIPURPOSE/ FACILITIES - CONSTRUCTION/ REHABILITATION OF MULTI-PURPOSE BUILDING AT BARANGAY MORAS DELA PAZ, STO. TOMAS, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱2.8M | 100% | Low risk11 | —-0.104 |
| 122 | 22CG0116BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION (REHABILITATION) OF POBLACION MULTI-PURPOSE BUILDING, BRGY. POBLACION, STO. TOMAS, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱2.8M | 100% | Low risk11 | —-0.104 |
| 123 | 21CG0092LOCAL INFRASTRUCTURE PROGRAM: BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/ FACILITIES - CONSTRUCTION/ REHABILITATION OF MULTI-PURPOSE BUILDING AT BARANGAY SAN BARTOLOME, STO, TOMAS, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱2.8M | 100% | Low risk11 | —-0.106 |
| 124 | 22CG0242SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - REHABILITATION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MORAS DELA PAZ, STO. TOMAS, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱2.8M | 100% | Low risk11 | —-0.107 |
| 125 | 19CG0049CONSTRUCTION/ REHABILITATION OF COVERED COURT, SAN NICOLAS, STA. ANA, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱2.4M | 100% | Low risk11 | —-0.104 |