Contractor dossier
604 projects on file, including joint ventures this contractor is part of.
Total projects
604
Total budget
₱19.5B
Average progress
96.2%
Completion rate
90.2%
Average risk score
36.3
Medium risk on average, out of 100
Flagged as unusual
9
1.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 177 | ₱2.1B | 18.5 | 0 | 100.0% |
| National Capital Region | 153 | ₱3B | 38.9 | 0 | 99.1% |
| Region IV-A | 106 | ₱4.4B | 47.0 | 3 | 89.4% |
| Region XI | 69 | ₱1.6B | 32.3 | 0 | 100.0% |
| Region I | 39 | ₱2.3B | 53.1 | 1 | 89.7% |
| Region IV-B | 19 | ₱2.7B | 55.5 | 1 | 93.7% |
| Region IX | 13 | ₱1.2B | 63.6 | 0 | 86.9% |
| Region VIII | 11 | ₱991.6M | 58.1 | 2 | 83.8% |
| Region VI | 5 | ₱350M | 64.5 | 2 | 83.0% |
| Region II | 5 | ₱221.6M | 47.6 | 0 | 100.0% |
| Region VII | 2 | ₱105.8M | 52.3 | 0 | 100.0% |
| Region XII | 2 | ₱147.5M | 29.8 | 0 | 94.8% |
| Region V | 1 | ₱145.8M | 69.5 | 0 | 29.2% |
| Region X | 1 | ₱198M | 59.6 | 0 | 100.0% |
| Negros Island Region | 1 | ₱96.5M | 57.7 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 232 | ₱2.7B | 26.8 | 1 | 98.6% |
| Roads | 205 | ₱8B | 38.8 | 1 | 95.6% |
| Flood Control and Drainage | 138 | ₱7.8B | 47.2 | 3 | 93.7% |
| Bridges | 13 | ₱89.2M | 32.0 | 0 | 100.0% |
| Water Provision and Storage | 7 | ₱26.7M | 23.6 | 0 | 100.0% |
| OTHER | 6 | ₱353.8M | 70.3 | 2 | 89.0% |
| GAA 2025 OO-1 | 1 | ₱241.2M | 94.8 | 1 | 57.4% |
| GAA 2025 OO-2 | 1 | ₱119.4M | 93.7 | 1 | 85.0% |
| Bridges, Roads | 1 | ₱107.4M | 62.2 | 0 | 37.8% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25I00081NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - TACLOBAN - STA. FE - SAN MIGUEL ROAD, PACKAGE 2, LEYTE | Region VIII | Region VIII | On-Going | ₱241.2M | 57% | High risk95 | Flagged0.034 |
| 25GJ0017CONSTRUCTION OF FLOOD MITIGATION STRUCTURES - WATERWAYS REHABILITATION AND COASTAL PROTECTION, SECTION 2, ILOILO CITY, ILOILO | Region VI | Iloilo City DEO | On-Going | ₱119.4M | 85% | High risk94 | Flagged0.001 |
| 24GA0247CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG MALINAO RIVER, BARANGAY BANAYBANAY, MALINAO, AKLAN | Region VI | Aklan DEO | On-Going | ₱78.3M | 30% | High risk79 | Flagged0.057 |
| 24CC0424CONSTRUCTION OF REINFORCED CONCRETE FLOOD CONTROL STRUCTURE, BARANGAY BALUBAD, BULAKAN, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱72.4M | 100% | High risk76 | —-0.029 |
| 22DI0108REHABILITATION OF ROAD AND DRAINAGE, BINAN CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱94.7M | 79% | High risk76 | Flagged0.018 |
| 22D00106CONSTRUCTION OF SLOPE PROTECTION STRUCTURE USING ROCK NETTING ALONGLAIYA - MALABRIGO ROAD, SITIO NATUNGKAD - SITIO BIGA, BRGY. HUGOM,SAN JUAN, BATANGAS | Region IV-A | Region IV-A | Completed | ₱144.7M | 100% | High risk75 | —-0.019 |
| 25J00016CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SIOCON RIVER (UPSTREAM), PACKAGE 6, SIOCON, ZAMBOANGA DEL NORTE | Region IX | Region IX | On-Going | ₱149.5M | 41% | High risk75 | —-0.004 |
| 22J00065CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - ISABELA URBAN DRAINAGE | Region IX | Region IX | On-Going | ₱110.8M | 80% | High risk73 | —-0.001 |
| 23I00222CONSTRUCTION OF SUBANG DAKU FLOOD CONTROL, SOGOD, SOUTHERN LEYTE | Region VIII | Region VIII | On-Going | ₱94.5M | 94% | High risk72 | Flagged0.033 |
| 24JJ0008PREVENTIVE MAINTENANCE - SECONDARY ROADS, SIOCON- SIRAWAI- SIBUCO- LIMPAPA RD- K2098 + 000 - K2102 + 300 | Region IX | Zamboanga del Norte 4th DEO | On-Going | ₱118.9M | 97% | High risk71 | —-0.032 |
| 24A00042CONSTRUCTION OF MISSING LINKS/ NEW ROADS, PIDDIG-CARASI (ILOCOS NORTE) - CALANASAN (APAYAO) CONNECTING CABUGAO-CONNER (APAYAO) - TUAO (CAGAYAN) ROAD, ILOCOS NORTE (PACKAGE 5) | Region I | Region I | On-Going | ₱154.4M | 82% | High risk71 | —-0.019 |
| 22CA0083CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF NEW ROAD CURING A | Region III | Bataan 1st DEO | Completed | ₱76.5M | 100% | High risk71 | —-0.036 |
| 23AA0129CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BISLAK RIVER, BRGY. SAN RAMON, VINTAR, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱62.7M | 100% | High risk70 | —-0.063 |
| 23AA0160CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS -REHABILITATION OF DAMAGED CONCRETE BANK REVETMENT AND BRIDGE APPROACH, BISLAK RIVER REVETMENT, BARANGAY TAMDAGAN, VINTAR, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱47M | 75% | High risk70 | —-0.010 |
| 25D00122PREVENTIVE MAINTENANCE - PRIMARY ROADS MAHARLIKA HIGHWAY (MANILA SOUTH ROAD) - K0033 + 742 - K0034 + 120, K0034 + 914 - K0035 + 000 | Region IV-A | Region IV-A | On-Going | ₱55M | 16% | High risk70 | —-0.024 |
| 20DI0138CONCRETING OF ACCESS ROAD AND IMPROVEMENT OF DRAINAGE, BRGY. SANTO NINO AND CANLALAY, BIÑAN, LAGUNA | Region IV-A | Laguna 2nd DEO | Completed | ₱9.9M | 100% | High risk70 | —-0.042 |
| 23AA0149CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS -CONSTRUCTION OF WATERWAY STRUCTURE ALONG BANBAN RIVER, BARANGAY BANBAN AND DADAOR, BANGUI, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱19.6M | 100% | High risk70 | —-0.064 |
| 23AA0150CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BOLO RIVER, BARANGAY MALASIN TO BARANGAY NAGBALAGAN (SITIO BAGO), BANGUI, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱18.8M | 100% | High risk70 | —-0.064 |
| 23A00236REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS, MANILA NORTH RD - K0576+196-K0576+326 (RS), K0576+590-K0576+636 (RS), K0576+1137-K0576+1173 (RS) | Region I | Region I | Completed | ₱159.2M | 100% | High risk70 | —-0.055 |
| 24F00114CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF DAET-SAN VICENTE-SAN LOR | Region V | Region V | On-Going | ₱145.8M | 29% | High risk69 | —-0.028 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24GA0247CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG MALINAO RIVER, BARANGAY BANAYBANAY, MALINAO, AKLAN | Region VI | Aklan DEO | On-Going | ₱78.3M | 30% | High risk79 | Flagged0.057 |
| 25I00081NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - TACLOBAN - STA. FE - SAN MIGUEL ROAD, PACKAGE 2, LEYTE | Region VIII | Region VIII | On-Going | ₱241.2M | 57% | High risk95 | Flagged0.034 |
| 18DI0139NETWORK DEVELOPMENT PROGRAM -CONSTRUCTION OF BY- PASS AND DIVERSION ROADS, SAN JOSE -BUCAL DIVERSION ROAD, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱23.3M | 55% | High risk69 | Flagged0.033 |
| 23I00222CONSTRUCTION OF SUBANG DAKU FLOOD CONTROL, SOGOD, SOUTHERN LEYTE | Region VIII | Region VIII | On-Going | ₱94.5M | 94% | High risk72 | Flagged0.033 |
| 22DI0108REHABILITATION OF ROAD AND DRAINAGE, BINAN CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱94.7M | 79% | High risk76 | Flagged0.018 |
| 24DK0180CAPITAL OUTLAY - CSSP - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING ... - CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE, BARANGAY DAPDAP, TAYABAS CITY, QUEZON | Region IV-A | Quezon 1st DEO | On-Going | ₱47.3M | 19% | Medium risk54 | Flagged0.013 |
| 22E00072CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURES IN SUPPORT OF NATIONAL SECURITY (TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM - TIKAS)- CONST. OF PNP BUILDING, MAMBURAO, OCCIDENTAL MINDORO | Region IV-B | Region IV-B | On-Going | ₱37.5M | 56% | High risk65 | Flagged0.005 |
| 25GJ0017CONSTRUCTION OF FLOOD MITIGATION STRUCTURES - WATERWAYS REHABILITATION AND COASTAL PROTECTION, SECTION 2, ILOILO CITY, ILOILO | Region VI | Iloilo City DEO | On-Going | ₱119.4M | 85% | High risk94 | Flagged0.001 |
| 25A00094CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SANTOL-SAN GABRIEL-KAPANGAN ROAD, MALUYO RIVER, BARANGAY MANGAAN, SANTOL LA UNION | Region I | Region I | On-Going | ₱146.3M | 35% | High risk62 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 451 | 18LA0174CONSTRUCTION OF MPB (BRGY. HALL), KIOKMAY, LAAK, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱4.4M | 100% | Low risk16 | —-0.087 |
| 452 | 19LA0376CONSTRUCTION OF MPB, MAINIT, MACO, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱3.4M | 100% | Low risk16 | —-0.088 |
| 453 | 18DO0028LOCAL PROGRAM-LOCAL INFRASTRUCTURE PROGRAM-BUILDING AND OTHER STRUCTURES-MULTI-PURPOSE/FACILTIES-CONSTRUCTION/REHABILITATION OF MULTI-PURPOSE BUILDING, SITIO TANAUAN, BRGY. PALAYPALAY, JALAJALA, RIZAL | Region IV-A | Rizal 2nd DEO | Completed | ₱970K | 100% | Low risk15 | —-0.100 |
| 454 | 20LA0167IMPROVEMENT OF MULTI-PURPOSE BUILDING (BRGY. GYM) KALIGUTAN, LAAK, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱2.9M | 100% | Low risk15 | —-0.089 |
| 455 | 18LA0170CONSTRUCTION OF GYM AT KAO NHS, NABUNTURAN, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱2.9M | 100% | Low risk15 | —-0.086 |
| 456 | 19LA0367COMPLETION OF MAWAB TRIBAL CENTER, NUEVO ILOCO, MAWAB, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱2.9M | 100% | Low risk15 | —-0.088 |
| 457 | 20CD0161RAIN WATER COLLECTORS IN PUBLIC FACILITIES REGION III | Region III | Bulacan 2nd DEO | Completed | ₱3.9M | 100% | Low risk15 | —-0.069 |
| 458 | 19LA0455CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. MATIAO, PANTUKAN, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱3.4M | 100% | Low risk15 | —-0.087 |
| 459 | 19CC0050UPGRADING OF ROAD AND DRAINAGE CANAL TALABAHAN, MATUNGAO, BULAKAN, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱2.9M | 100% | Low risk15 | —-0.105 |
| 460 | 19CD0356CONSTRUCTION/REHABILITATION OF WATER SUPPLY / RAINWATER COLLECTORS IN REGION III | Region III | Bulacan 2nd DEO | Completed | ₱3.5M | 100% | Low risk15 | —-0.069 |
| 461 | 18LA0172CONSTRUCTION OF MPB AT PINDASAN ES, MABINI, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱2.9M | 100% | Low risk15 | —-0.091 |
| 462 | 21CD0052CONSTRUCTION OF MULTI-PURPOSE BUILDING, MARUNGKO, ANGAT, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱3.8M | 100% | Low risk14 | —-0.107 |
| 463 | 19CD0114CONSTRUCTION OF MULTI-PURPOSE BUILDING, SAN MANUEL ELEMENTARY SCHOOL, SAN JOSE DEL MONTE CITY, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱2.9M | 100% | Low risk14 | —-0.107 |
| 464 | 19CD0115CONSTRUCTION OF MULTI-PURPOSE BUILDING, STO. CRISTO NATIONAL HIGH SCHOOL, SAN JOSE DEL MONTE CITY, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱2.9M | 100% | Low risk14 | —-0.107 |
| 465 | 21CD0028CONSTRUCTION OF DRAINAGE CANAL, BARANGAY MAHABANG PARANG, STA. MARIA, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱1.9M | 100% | Low risk14 | —-0.089 |
| 466 | 18LA0210COMPLETION OF SENIOR CITIZEN BLDG., POBLACION, LAAK, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱2.4M | 100% | Low risk14 | —-0.089 |
| 467 | 19CD0068ASSET PRESERVATION REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS EASTERN BULACAN ROAD K0070 + 000 - K0070 + 152 | Region III | Bulacan 2nd DEO | Completed | ₱4M | 100% | Low risk14 | —-0.103 |
| 468 | 18LA0169CONSTRUCTION OF MPB SITIO ALAUYA, BRGY. BINUANGAN, MACO, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱2.4M | 100% | Low risk14 | —-0.091 |
| 469 | 20LA0223IMPROVEMENT OF MPB (GYM) NEW SIBUNGA ES, NABUNTURAN, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱2.5M | 100% | Low risk14 | —-0.087 |
| 470 | 19CC0135CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) BRGY. BALITE, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱3.8M | 100% | Low risk14 | —-0.107 |
| 471 | 20CD0089REHABILITATION OF SAN ILDEFONSO NATIONAL HIGH SCHOOL-BULACAN AGRICULTURAL STATE COLLEGE ROAD, POBLACION & PINAOD, SAN ILDEFONSO, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱4.2M | 100% | Low risk14 | —-0.106 |
| 472 | 21CD0009CONCRETING OF ROAD, BINAGBAG, ANGAT, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱2.9M | 100% | Low risk14 | —-0.104 |
| 473 | 19LA0304CONSTRUCTION OF MULTI-PURPOSE BUILDING (MINI GYM), OGAO ES, NABUNTURAN, COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱2M | 100% | Low risk14 | —-0.088 |
| 474 | 19CC0206CONSTRUCTION OF DRAINAGE CANAL BRGY. BOLACAN, BOCAUE, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱1.9M | 100% | Low risk14 | —-0.090 |
| 475 | 19CD0278CONSTRUCTION OF DRAINAGE CANAL 600 METERS AT SEA, BRGY. PRENZA I, MARILAO, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱1.9M | 100% | Low risk14 | —-0.091 |