Contractor dossier
22 projects on file, including joint ventures this contractor is part of.
Total projects
22
Total budget
₱164.8M
Average progress
99.3%
Completion rate
90.9%
Average risk score
23.7
Low risk on average, out of 100
Flagged as unusual
1
4.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 22 | ₱164.8M | 23.7 | 1 | 99.3% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 15 | ₱71.2M | 18.7 | 0 | 100.0% |
| Roads | 4 | ₱31.3M | 22.8 | 0 | 100.0% |
| Flood Control and Drainage | 2 | ₱55.8M | 28.7 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱6.6M | 92.5 | 1 | 85.2% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CG0100BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI PURPOSE BUILDING, SAN PEDRO CUTUD, CITY OF SAN FERNANDO, PAMPANGA | Region III | Pampanga 1st DEO | On-Going | ₱6.6M | 85% | High risk92 | Flagged0.001 |
| 25CG0163BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, ACLI ES, MEXICO, PAMPANGA | Region III | Pampanga 1st DEO | On-Going | ₱6.6M | 100% | High risk71 | —-0.045 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CG0100BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI PURPOSE BUILDING, SAN PEDRO CUTUD, CITY OF SAN FERNANDO, PAMPANGA | Region III | Pampanga 1st DEO | On-Going | ₱6.6M | 85% | High risk92 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25CG0100BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI PURPOSE BUILDING, SAN PEDRO CUTUD, CITY OF SAN FERNANDO, PAMPANGA | Region III | Pampanga 1st DEO | On-Going | ₱6.6M | 85% | High risk92 | Flagged0.001 |
| 2 | 25CG0163BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, ACLI ES, MEXICO, PAMPANGA | Region III | Pampanga 1st DEO | On-Going | ₱6.6M | 100% | High risk71 | —-0.045 |
| 3 | 23CD0134CONSTRUCTION OF MULTI-PURPOSE BUILDING, SAN ROQUE, MDRRMO, ANGAT, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱9.9M | 100% | Medium risk35 | —-0.107 |
| 4 | 23CG0267SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (DAR REGIONAL OFFICE BUILDING), CITY OF SAN FERNANDO, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱13.9M | 100% | Medium risk32 | —-0.104 |
| 5 | 23CG0144SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - REHABILITATION OF ROADS INCLUDING DRAINAGE SYSTEMS, DEL ROSARIO AND SAN JUAN, CIT | Region III | Pampanga 1st DEO | Completed | ₱11.1M | 100% | Low risk30 | —-0.103 |
| 6 | 19CG0015CONSTRUCTION/ REHABILITATION OF MESALIPIT CREEK, BACOLOR, PAMPANGA (R.A. 9506- BACOLOR REHABILITATION ACT) | Region III | Pampanga 1st DEO | Completed | ₱18.5M | 100% | Low risk29 | —-0.092 |
| 7 | 22CG0028SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/ FACILITIES - CONSTRUCTION OF DRAINAGE SYSTEM AT DOLORES, CONCEPCION AND MALIWALU, BACOLOR, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱37.2M | 100% | Low risk29 | —-0.090 |
| 8 | 23CG0304SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF MAGLIMAN ROAD, CITY OF SAN FERNANDO, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱10.5M | 100% | Low risk24 | —-0.045 |
| 9 | 19CH0162CONCRETING OF PUROK 2 LAMBINGAN BRGY. GUTAD FMR, BRGY. GUTAD, FLORIDABLANCA, PAMPANGA | Region III | Pampanga 2nd DEO | Completed | ₱5M | 100% | Low risk24 | —-0.042 |
| 10 | 20CG0147LOCAL INFRASTRUCTURE PROGRAM: MULTIPURPOSE/ FACILITIES - REHABILITATION/ IMPROVEMENT OF MULTI - PURPOSE BUILDING (COVERED COURT) BULAON RESETTLEMENT CENTER, BRGY. BULAON, SAN FERNANDO CITY, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱4.7M | 100% | Low risk16 | —-0.106 |
| 11 | 19CG0028CONSTRUCTION OF MULTI-PURPOSE BUILDING AT CABALANTIAN, BACOLOR, PAMPANGA (R.A. 9506-BACOLOR REHABILITATION ACT) | Region III | Pampanga 1st DEO | Completed | ₱4.7M | 100% | Low risk14 | —-0.105 |
| 12 | 19CG0029CONSTRUCTION OF MULTI-PURPOSE BUILDING AT TINAJERO, BACOLOR, PAMPANGA (R.A. 9506-BACOLOR REHABILITATION ACT) | Region III | Pampanga 1st DEO | Completed | ₱4.7M | 100% | Low risk14 | —-0.105 |
| 13 | 22CG0205SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES - REHABILITATION OF SAN ROQUE BARANGAY ROAD, BARANGAY SAN ROQUE, SAN LUIS, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱4.7M | 100% | Low risk13 | —-0.106 |
| 14 | 19CG0025CONSTRUCTION OF MULTI-PURPOSE COVERED COURT, SAN ISIDRO, SAN FERNANDO, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱4.2M | 100% | Low risk13 | —-0.105 |
| 15 | 23CG0155BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION OF MULTI-PURPOSE BUILDING, GANDUS, CAMUNING AND EDEN, MEXICO, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱3.8M | 100% | Low risk12 | —-0.105 |
| 16 | 23CG0113BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION (CONSTRUCTION) OF MULTI-PURPOSE BUILDINGS AT BALITI, LARA AND PULUNG BULU, CITY OF SAN FERNANDO, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱3.8M | 100% | Low risk12 | —-0.104 |
| 17 | 23CG0269BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS/ FACILITIES - COMPLETION (CONSTRUCTION) OF MULTI-PURPOSE BUILDING, SAN JOAQUIN, STA. ANA, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱2.8M | 100% | Low risk11 | —-0.104 |
| 18 | 23CG0163BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION OF MULTI-PURPOSE BUILDINGS, SAN ROQUE BITAS AND STO. NIÑO TABUAN, ARAYAT, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱2.8M | 100% | Low risk11 | —-0.102 |
| 19 | 20CG0221LOCAL INFRASTRUCTURE PROGRAM: BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE / FACILITIES - REHABILITATION OF MULTI-PURPOSE BUILDING, ALASAS, CITY SAN FERNANDO CITY, PAMPANG | Region III | Pampanga 1st DEO | Completed | ₱2.3M | 100% | Low risk10 | —-0.102 |
| 20 | 20CG0220LOCAL INFRASTRUCTURE PROGRAM: BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE / FACILITIES - REPAIR AND REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) BULAON ELEMENTARY SCHOOL, BRGY. BULAON, SAN FERNANDO CITY, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱2.3M | 100% | Low risk10 | —-0.102 |
| 21 | 19CG0046CONSTRUCTION/ REHABILITATION OF MULTI-PURPOSE COVERED COURT, SAN ISIDRO, SAN FERNANDO, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱2.3M | 100% | Low risk10 | —-0.104 |
| 22 | 19CG0050CONSTRUCTION/ REHABILITATION OF MULTI PURPOSE COVERED COURT, JULIANA, SAN FERNANDO, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱2.3M | 100% | Low risk10 | —-0.106 |