Contractor dossier
402 projects on file, including joint ventures this contractor is part of.
Total projects
402
Total budget
₱20.4B
Average progress
96.7%
Completion rate
90.8%
Average risk score
40.8
Medium risk on average, out of 100
Flagged as unusual
7
1.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 313 | ₱17.1B | 38.8 | 6 | 96.3% |
| National Capital Region | 58 | ₱2.2B | 49.4 | 0 | 98.6% |
| Region IV-B | 14 | ₱307.1M | 37.0 | 0 | 100.0% |
| Region I | 7 | ₱263.6M | 44.8 | 0 | 100.0% |
| Region IV-A | 6 | ₱139.9M | 49.9 | 0 | 100.0% |
| Region V | 2 | ₱77.3M | 74.0 | 1 | 50.0% |
| Central Office | 1 | ₱260.3M | 77.0 | 0 | 100.0% |
| Region II | 1 | ₱96.5M | 54.7 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 188 | ₱10.9B | 39.9 | 0 | 98.4% |
| Roads | 111 | ₱5.6B | 40.8 | 2 | 97.2% |
| Buildings and Facilities | 90 | ₱3.4B | 41.7 | 3 | 94.2% |
| Bridges | 7 | ₱305.8M | 39.9 | 1 | 85.7% |
| OTHER | 5 | ₱167.6M | 49.0 | 0 | 100.0% |
| GAA 2025 OO-1 | 1 | ₱28.1M | 93.3 | 1 | 0.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25F00066ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - MAKABUBOS BR. (B02741LZ) ALONG MAHARLIKA HIGHWAY, BASUD, CAMARINES NORTE (2ND LEGISLATIVE DISTRICT) | Region V | Region V | On-Going | ₱28.1M | 0% | High risk93 | Flagged0.019 |
| 24CM0068NATIONAL BUILDING PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES, CONSTRUCTION OF SUBIC GENERAL HOSPITAL, SUBIC, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱289.5M | 92% | High risk82 | Flagged0.003 |
| 25CM0044CSSP, BIP, MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES STRUCTURAL AND RESILIENCE PROGRAM, CONSTRUCTION OF SUBIC MUNICIPAL HALL, SUBIC, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱97.5M | 1% | High risk81 | Flagged0.007 |
| 25CC0189CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BARANGAY SAN FRANCISCO, BULAKAN, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.6M | 89% | High risk81 | —-0.023 |
| 25CM0029CSSP, BIP, MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING PHASE 2, BARANGAY SAN AGUSTIN, CASTILLEJOS, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱147.8M | 78% | High risk80 | —-0.007 |
| 25CM0047CSSP, BIP, MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, REHABILITATION OF MULTI-PURPOSE BUILDING, SUBIC, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱58.5M | 20% | High risk79 | —-0.006 |
| 25CM0066CSSP, BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. BARACA-CAMACHILE, SUBIC, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱48.7M | 0% | High risk78 | —-0.003 |
| 25C00520CONVERGENCE & SPL. SUPPORT PROG.-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)-REHAB. OF ROAD, CANDABA-BALIWAG ROAD (PASIG-POBLACION SECT.) CANDABA, P | Region III | Region III | On-Going | ₱236.4M | 0% | High risk77 | Flagged0.013 |
| 21Z00015REHABILITATION/RESTORATION OF DETERIORATED DIKES/ERODED RIVERBANKS ALONG PAMPANGA RIVER INCLUDING CANDABA CUT-OFF CHANNEL, CANDABA, PAMPANGA | Central Office | Flood Control Management Cluster | Completed | ₱260.3M | 100% | High risk77 | —-0.028 |
| 24C00410CONVERGENCE & SPL. SUPP. PROG.-SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG)-ACCESS RDS. &/OR BRS. FR. THE NAT;L. RD/S LEAD. TO MAJOR/STRATEGIC PUBLIC BLDGS/FACILITIES-CONST. OF STO. TOMAS-ARAYAT BYPASS ROAD (CANDABA-SAN LUIS SECTION), PROV. OF PAMP. | Region III | Region III | On-Going | ₱189.1M | 0% | High risk76 | Flagged0.016 |
| 25CG0031NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF BYPASS AND DIVERSION ROADS - STA. ANA - ARAYAT BY-PASS ROAD, (STA. ANA SECTION) PHASE II, PAMPANGA | Region III | Pampanga 1st DEO | On-Going | ₱91.1M | 98% | High risk74 | —-0.034 |
| 20CK0044CONSTRUCTION OF TRADOC ATF FACILITY, TRADOC, CAMP O'DONNELL, BRGY. STA. LUCIA, CAPAS, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱23.8M | 100% | High risk71 | —-0.067 |
| 25CM0036CSSP SPECIAL ROAD FUND MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239, INSTALLATION OF ROAD LIGHTING (PHASE II) AT OLONGAPO CITY, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱19.1M | 82% | High risk70 | —-0.035 |
| 25CM0038CSSP - SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239, INSTALLATION OF ROAD LIGHTING, SAN MARCELINO, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱19.1M | 100% | High risk69 | —-0.039 |
| 17CM0030REHAB. OF DAMAGED PAVED ROAD INCL. DRAINAGE, JOSE ABAD SANTOS AVENUE (JASA), OLONGAPO CITY | Region III | Zambales 2nd DEO | Completed | ₱12M | 100% | High risk69 | —-0.065 |
| 17CH0032REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE BASED ON | Region III | Pampanga 2nd DEO | Completed | ₱27.4M | 100% | High risk69 | —-0.067 |
| 17CM0013REHAB. OF DRAINAGE ALONG SAN MARCELINO-NAGBAYTO RD, K0151+(-1012)-KO151+(-459), SAN MARCELINO, ZAMB. | Region III | Zambales 2nd DEO | Completed | ₱9.4M | 100% | High risk69 | —-0.062 |
| 17CG0024REHABILITATION/IMPROVEMENT OF CABALANTIAN CREEK, BACOLOR, PAMPANGA (RA 9506 BACOLOR REHABILITATION ACT), BACOLOR, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱16.2M | 100% | High risk69 | —-0.059 |
| 17CG0031REHABILITATION/IMPROVEMENT OF BUNGANG GUINTO RIVER, SAN LORENZO, MEXICO, PAMPANGA STA. 0+300 - STA. 0+780, MEXICO, PAMPANGA | Region III | Pampanga 1st DEO | Completed | ₱24.8M | 100% | High risk68 | —-0.064 |
| 16CK0186NETWORK DEV'T.-OFF-CARRIAGEWAY IMPT INCLUDING DRAINAGE ALONG CONCEPCION-LAPAZ ROAD, CONC AND LAPAZ, | Region III | Tarlac 2nd DEO | Completed | ₱26.8M | 100% | High risk68 | —-0.068 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CM0075CONSTRUCTION OF SCHOOL BUILDING, OLONGAPO CITY ELEMENTARY SCHOOL (PHASE 2), BARANGAY WEST BAJAC-BAJAC, OLONGAPO CITY, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱19.7M | 34% | Medium risk54 | Flagged0.027 |
| 24C00022CONVERGENCE & SPL. SUPPORT PROGRAM-SUSTAINABLE INFRA PROJS. ALLEVIATIING GAPS (SIPAG)-ACCESS RDS. &/OR BRS. FR. THE NAT'L. RD./S LEAD. TO MAJOR/STRAT. PUBLIC BLDGS./FACILITIES-CONST. OF STO. TOMAS-ARAYAT BYPASS RD. (SAN LUIS SECT.) SAN LUIS, PAMPANGA. | Region III | Region III | On-Going | ₱89.8M | 0% | High risk68 | Flagged0.025 |
| 25F00066ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - MAKABUBOS BR. (B02741LZ) ALONG MAHARLIKA HIGHWAY, BASUD, CAMARINES NORTE (2ND LEGISLATIVE DISTRICT) | Region V | Region V | On-Going | ₱28.1M | 0% | High risk93 | Flagged0.019 |
| 24C00410CONVERGENCE & SPL. SUPP. PROG.-SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG)-ACCESS RDS. &/OR BRS. FR. THE NAT;L. RD/S LEAD. TO MAJOR/STRATEGIC PUBLIC BLDGS/FACILITIES-CONST. OF STO. TOMAS-ARAYAT BYPASS ROAD (CANDABA-SAN LUIS SECTION), PROV. OF PAMP. | Region III | Region III | On-Going | ₱189.1M | 0% | High risk76 | Flagged0.016 |
| 25C00520CONVERGENCE & SPL. SUPPORT PROG.-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)-REHAB. OF ROAD, CANDABA-BALIWAG ROAD (PASIG-POBLACION SECT.) CANDABA, P | Region III | Region III | On-Going | ₱236.4M | 0% | High risk77 | Flagged0.013 |
| 25CM0044CSSP, BIP, MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES STRUCTURAL AND RESILIENCE PROGRAM, CONSTRUCTION OF SUBIC MUNICIPAL HALL, SUBIC, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱97.5M | 1% | High risk81 | Flagged0.007 |
| 24CM0068NATIONAL BUILDING PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES, CONSTRUCTION OF SUBIC GENERAL HOSPITAL, SUBIC, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱289.5M | 92% | High risk82 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 24CK0078REHABILITATION OF EXISTING DIKE ALONG PARUA RIVER (CASTILLO SECTION, LEFT BANK), PACKAGE H, STA. 5+569.50 TO STA. 5+969.90, CONCEPCION, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱96.5M | 100% | Medium risk57 | —-0.081 |
| 52 | 20OB0329CONSTRUCTION OF MULTI-PURPOSE BUILDING AND SITE DEVELOPMENT (SPED CENTER), BRGY. CALZADA TIPAS, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱57M | 100% | Medium risk57 | —-0.096 |
| 53 | 19CK0054REHABILITATION OF EXISTING DIKE ALONG O'DONNELL RIVER (PATLING SECTION, RIGHT SIDE), CAPAS, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱96.4M | 100% | Medium risk57 | —-0.075 |
| 54 | 23C00160FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF SLOPE PROTECTION WORKS AT MALASIK RIVER (MAGUMBALI SECTION), BARANGAY MAGUMBALI, CANDABA, PAMPANGA, PROVINCE OF PAMPANGA | Region III | Region III | Completed | ₱144.8M | 100% | Medium risk57 | —-0.068 |
| 55 | 23C00159FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF SLOPE PROTECTION WORKS AT MALASIK RIVER (BARANGCA SECTION), BARANGAY BARANGCA, CANDABA, PAMPANGA, PROVINCE OF PAMPANGA | Region III | Region III | Completed | ₱144.8M | 100% | Medium risk57 | —-0.068 |
| 56 | 18CL0008IMPROVEMENT/ REHABILITATION OF SLOPE PROTECTION/ FLOOD CONTROL @ SITIO LAOAG, MALOMA DIKE RIGHT SIDE (DOWNSTREAM), CABANGAN SIDE, CABANGAN, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱93.1M | 100% | Medium risk56 | —-0.073 |
| 57 | 22OF0229CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AND LEARNING CENTER, BARANGAY STA. MONICA, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱47.5M | 100% | Medium risk56 | —-0.094 |
| 58 | 18CL0009IMPROVEMENT/ REHABILITATION OF SLOPE PROTECTION/ FLOOD CONTROL ALONG MALOMA RIVER (DOWNSTREAM), SAN FELIPE SIDE, SAN FELIPE, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱93.1M | 100% | Medium risk56 | —-0.073 |
| 59 | 21CK0041REHABILITATION OF EXISTING DIKE ALONG RIO CHICO RIVER (SAN ROQUE SECTION, RIGHT BANK), D/S OF RIO CHICO BRIDGE, LA PAZ, TARLAC | Region III | Tarlac 2nd DEO | Completed | ₱96.5M | 100% | Medium risk56 | —-0.076 |
| 60 | 25CM0035CSSP - SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239 INSTALLATION OF ROAD LIGHTING ALONG JASA, OLONGAPO CITY, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱94.1M | 82% | Medium risk56 | —-0.060 |
| 61 | 18OB0481STRUCTURAL IMPROVEMENT OF PUBLIC BUILDINGS AND CONSTRUCTION OF EVACUATION CENTERS, NATIONAL CAPITAL REGION TECHNOLOGY BUILDING, TECHNOLOGICAL UNIVERSITY OF THE PHILIPPINES-TAGUIG CAMPUS, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱55M | 100% | Medium risk56 | —-0.096 |
| 62 | 21OB0270CONSTRUCTION OF MULTI-PURPOSE BUILDING, MARIKINA POLYTECHNIC COLLEGE, MARIKINA CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱48M | 100% | Medium risk55 | —-0.098 |
| 63 | 18OB0421REHABILITATION/CONSTRUCTION OF MULTI-PURPOSE BUILDING INCLUDING SITE DEVELOPMENT (PINAGLABANAN SHRINE) BRGY. CORAZON DE JESUS, SAN JUAN CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱48M | 100% | Medium risk55 | —-0.093 |
| 64 | 20OB0233CONSTRUCTION OF THREE (3) STOREY MULTI-PURPOSE BUILDING, SAN JUAN ELEMENTARY SCHOOL, BRGY. RIVERA, SAN JUAN CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱47.5M | 100% | Medium risk55 | —-0.093 |
| 65 | 21F00067OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-BRIDGE PROGRAM-WIDENING OF PERMANENT BRIDGES-PAGSANGAHAN BR. (B02731LZ) ALONG DAANG MAHARLIKA (LZ), BASUD, CAMARINES NORTE 2ND LEGISLATIVE DISTRICT | Region V | Region V | Completed | ₱49.2M | 100% | Medium risk55 | —-0.052 |
| 66 | 22BI0044ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET RESERVATION PROGRAM-REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-TERTIARY ROAD-PAPAYA-MALABING-WANGAL-BINUGAWAN-TADJI-RUNRUNO ROAD, | Region II | Nueva Vizcaya DEO | Completed | ₱96.5M | 100% | Medium risk55 | —-0.071 |
| 67 | 20OE0180CONSTRUCTION OF MULTI - PURPOSE BUILDING AT ZONE 59, BARANGAY 598, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱49.5M | 100% | Medium risk55 | —-0.098 |
| 68 | 22OE0089CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. HEALTH CENTER / BRGY. HALL, BRGY. 308, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱49M | 100% | Medium risk55 | —-0.094 |
| 69 | 21OE0024CONSTRUCTION OF ENLISTED PERSONNEL TRANSIENT (2-STOREY) BUILDING, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱49M | 100% | Medium risk54 | —-0.096 |
| 70 | 24C00409CONVERGENCE & SPL. SUPP. PROG.-SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FR. THE NAT'L. ROAD/S LEAD. TO MAJOR/STRATEGIC PUBLIC BLDGS./FACILITIES-CONST. OF STO. TOMAS-ARAYAT BYPASS ROAD (CANDABA SECTION), PROV. OF PAMP. | Region III | Region III | On-Going | ₱283.7M | 35% | Medium risk54 | —-0.021 |
| 71 | 25CM0075CONSTRUCTION OF SCHOOL BUILDING, OLONGAPO CITY ELEMENTARY SCHOOL (PHASE 2), BARANGAY WEST BAJAC-BAJAC, OLONGAPO CITY, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱19.7M | 34% | Medium risk54 | Flagged0.027 |
| 72 | 19OE0200CONSTRUCTION OF FOUR (4) STOREY SIXTEEN (16) CLASSROOM SCHOOL BUILDING AT ISABELO DELOSREYES ELEMENTARY SCHOOL (BASED ON 2017 PLAN, REVISED 3-24-2017) | National Capital Region | North Manila DEO | Completed | ₱56.4M | 100% | Medium risk53 | —-0.038 |
| 73 | 21OF0111CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BRGY. NOVALICHES PROPER, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱43.2M | 100% | Medium risk53 | —-0.067 |
| 74 | 19OE0012ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - BANK IMPROVEMENT ALONG ESTERO DELA REINA, STA. 0+492.40 TO STA. 0+571.60, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱57.4M | 100% | Medium risk53 | —-0.087 |
| 75 | 24CJ0269CONSTRUCTION OF MANILA NORTH ROAD TO SCTEX LUISITA (SCTEX LUISITA ACCESS ROAD - SEGMENT U), TARLAC CITY, TARLAC | Region III | Tarlac DEO | On-Going | ₱144.8M | 95% | Medium risk53 | —-0.043 |