Contractor dossier
833 projects on file, including joint ventures this contractor is part of.
Total projects
833
Total budget
₱90.9B
Average progress
90.9%
Completion rate
64.5%
Below 70%
Average risk score
62.3
High risk on average, out of 100
Flagged as unusual
101
12.1% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region V | 416 | ₱43.1B | 67.6 | 45 | 88.9% |
| Region IV-B | 310 | ₱34.8B | 56.4 | 43 | 95.1% |
| Region VI | 66 | ₱4.2B | 53.9 | 1 | 98.4% |
| Region VIII | 33 | ₱8B | 69.4 | 12 | 68.5% |
| Region IV-A | 3 | ₱376.4M | 66.9 | 0 | 3.0% |
| Region XI | 3 | ₱242M | 56.7 | 0 | 100.0% |
| Region IX | 1 | ₱198.4M | 74.0 | 0 | 100.0% |
| Region XII | 1 | ₱86.8M | 34.0 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 481 | ₱44.7B | 59.6 | 9 | 94.5% |
| Flood Control and Drainage | 248 | ₱31.9B | 62.9 | 44 | 88.3% |
| OTHER | 31 | ₱7B | 80.6 | 21 | 85.2% |
| Water Provision and Storage | 24 | ₱651.9M | 50.9 | 1 | 92.9% |
| GAA 2025 SSP | 19 | ₱2.2B | 95.5 | 19 | 64.6% |
| Bridges | 16 | ₱1.7B | 65.6 | 4 | 77.6% |
| Buildings and Facilities | 9 | ₱2.1B | 72.6 | 2 | 81.4% |
| GAA 2025 OO-2 | 3 | ₱455.3M | 93.5 | 1 | 61.9% |
| Bridges, Roads | 2 | ₱192.1M | 67.5 | 0 | 54.3% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25FB0004SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES -CONSTRUCTION OF RIDGE ROAD, CAWAYAN TO MALOBAGO, MANITO, ALBAY | Region V | Albay 2nd DEO | On-Going | ₱93.4M | 68% | High risk96 | Flagged0.014 |
| 25F00377CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES-CONSTRUCTION OF COASTAL ROAD, BARANGAY MALOBAGO, RAPU-RAPU, ALBAY, RAPU-RAPU, ALBAY (2ND LEGISLATIVE DISTRICT) | Region V | Region V | On-Going | ₱154.4M | 66% | High risk96 | Flagged0.024 |
| 25F00272CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-IMPROVEMENT OF ROAD, BARANGAY LIGUAN TO BARANGAY MANCAO, RAPU-RAPU, A | Region V | Region V | On-Going | ₱96M | 48% | High risk96 | Flagged0.021 |
| 25F00273CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-IMPROVEMENT OF ROAD, BARANGAY LIGUAN TO BARANGAY TINOCAWAN, RAPU-RAPU | Region V | Region V | On-Going | ₱96M | 50% | High risk96 | Flagged0.021 |
| 25EH0163CONSTRUCTION OF ROAD, SITIO EAST MAAMBONG, BARANGAY MAGSAYSAY TO SITIO CAPDANG BARANGAY AGMANIC, STA. FE, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱140.2M | 69% | High risk96 | Flagged0.031 |
| 25EH0161CONSTRUCTION OF ROAD, SITIO MAGSUPOT TO SITIO ILAYA, BARANGAY CALAGONSAO, ALCANTARA, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱140.2M | 73% | High risk96 | Flagged0.029 |
| 25EH0080CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY CANTINGAS, SAN FERNANDO, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱145.5M | 93% | High risk96 | Flagged0.024 |
| 25EH0087CONSTRUCTION OF ROAD, ODIONGAN ROAD LEADING TO TUGDAN AIRPORT, ODIONGAN, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱142.6M | 63% | High risk96 | Flagged0.035 |
| 25EH0088CONSTRUCTION OF ROAD, ALCANTARA TO ODIONGAN, ALCANTARA, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱142.7M | 63% | High risk96 | Flagged0.034 |
| 25EH0079CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SITIO CABANGAHAN BARANGAY CARMEN, SAN AGUSTIN, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱145.5M | 100% | High risk96 | Flagged0.023 |
| 25EH0111CONSTRUCTION OF REVETMENT STRUCTURE ALONG PATO-O RIVER (PHASE 2), ODIONGAN, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱139.8M | 22% | High risk96 | Flagged0.043 |
| 25EH0110CONSTRUCTION OF REVETMENT STRUCTURE ALONG PATO-O RIVER, ODIONGAN, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱139.7M | 27% | High risk96 | Flagged0.042 |
| 25EH0042CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, SITIO RIVERSIDE, BARANGAY TABOBO-AN, ODIONGAN, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱137.9M | 69% | High risk95 | Flagged0.031 |
| 25EH0153CONSTRUCTION OF ROAD, SITIO PALATE TO BARANGAY PANIQUE, ODIONGAN, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱93.5M | 65% | High risk95 | Flagged0.026 |
| 25EH0154CONSTRUCTION OF ROAD, BARANGAY LAWAN TO BARANGAY SAN ISIDRO (PHASE 2), ALCANTARA, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱93.5M | 81% | High risk95 | Flagged0.021 |
| 25GB0057CONSTRUCTION OF ROAD, BARANGAY MAYBUNGA-SITIO SADSADAN, LAUA-AN, ANTIQUE | Region VI | Antique DEO | On-Going | ₱45.2M | 57% | High risk95 | Flagged0.025 |
| 25EH0158CONSTRUCTION OF BRGY. PILI TO BRGY. LIMON SUR ROAD (PHASE 2), LOOC, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱119.9M | 68% | High risk95 | Flagged0.030 |
| 25EH0090CONSTRUCTION OF MARI-SUR FLOOD CONTROL STRUCTURE (RIGHT SIDE), SAN ANDRES, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱48.3M | 94% | High risk95 | Flagged0.009 |
| 25EH0152CONSTRUCTION OF ROAD, CLARO M. RECTO TO SITIO SAN ISIDRO, BARANGAY MALILICO, ODIONGAN, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱74.8M | 53% | High risk94 | Flagged0.027 |
| 25EH0054CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG GABAWAN BRIDGE, ODIONGAN, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱132.4M | 89% | High risk94 | —-0.002 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24F00370CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF SEAWALL WITH ROAD DIKE, BARANGAY CARACARAN, RAPU-RAPU, | Region V | Region V | On-Going | ₱284.3M | 85% | High risk91 | Flagged0.070 |
| 24EH0170CONSTRUCTION OF STORM SURGE PROTECTION/CAUSEWAY ALONG POBLACION SEAPORT, ALCANTARA, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱144.8M | 87% | High risk90 | Flagged0.062 |
| 24EH0171CONSTRUCTION OF SHORE PROTECTION/CAUSEWAY POBLACION, ALCANTARA, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱141.9M | 86% | High risk90 | Flagged0.061 |
| 24I00009CLUSTER 1: BASIC INFRASTRUCTURE PROGRAM (BIP) - COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION - CONSTRUCTION OF CAUSEWAY, SUBSECTION 3.2A, TACLOBAN CITY, LEYTE ; AND OTHER FIVE (5) PROJECTS | Region VIII | Region VIII | On-Going | ₱1.3B | 27% | High risk84 | Flagged0.057 |
| 24EH0179CONSTRUCTION OF LUMBANG WESTE FLOOD CONTROL STRUCTURE ALONG LUMBANG RIVER PHASE 2, CAJIDIOCAN, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱130.4M | 100% | High risk90 | Flagged0.057 |
| 24F00511CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MIISI GULLY, PAC | Region V | Region V | On-Going | ₱189.1M | 6% | High risk82 | Flagged0.054 |
| 24F00491CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MIISI GULLY, PAC | Region V | Region V | On-Going | ₱189M | 0% | High risk82 | Flagged0.054 |
| 23I00039CONSTRUCTION OF STORM SURGE PROTECTION/TIDE EMBANKMENT, LEYTE | Region VIII | Region VIII | On-Going | ₱1.1B | 61% | High risk84 | Flagged0.054 |
| 24I00400CONSTRUCTION OF STORM SURGE PROTECTION (WAVE WALL), PACKAGE 2, TACLOBAN CITY | Region VIII | Region VIII | On-Going | ₱144.4M | 0% | High risk74 | Flagged0.052 |
| 24I00397CONSTRUCTION OF STORM SURGE PROTECTION (WAVE WALL), PACKAGE 1, TACLOBAN CITY | Region VIII | Region VIII | On-Going | ₱144.4M | 0% | High risk74 | Flagged0.052 |
| 24I00010CLUSTER 2: 1. SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION - CONSTRUCTION OF CAUSEWAY, SUBSECTION 3.14 AND 3.15, TACLOBAN CITY, LEYTE AND OTHERN ONE (1) PROJECT | Region VIII | Region VIII | On-Going | ₱564M | 45% | High risk85 | Flagged0.051 |
| 24F00510CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MIISI GULLY, PAC | Region V | Region V | On-Going | ₱189.1M | 16% | High risk82 | Flagged0.051 |
| 23E00303SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF ROAD DIKE/ESPLANADE ALONG BUSUANGA RIVER, BRGY. SAN PEDRO,SAN JOSE, OCC. | Region IV-B | Region IV-B | On-Going | ₱186.3M | 83% | High risk73 | Flagged0.051 |
| 23E00349SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE/ESPLANADE ALONG BUSUANGA RIVER, BRGY. PITOGO, RIZAL, OCC. MINDOR | Region IV-B | Region IV-B | On-Going | ₱232.8M | 82% | High risk74 | Flagged0.051 |
| 23E00348SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF ROAD DIKE/ESPLANADE ALONG BUSUANGA RIVER, BRGY. AGUAS, RIZAL, OCC. MINDO | Region IV-B | Region IV-B | On-Going | ₱232.8M | 88% | High risk74 | Flagged0.050 |
| 22I00102CLUSTER 2: PROJECT 1. CONST. OF CAUSEWAY, SECT. 3.1, STA. 0+140-STA. 0+233, TAC. CITY, LEYTE; PROJECT 2. CONST. OF CAUSEWAY, SECT. 3.2, STA. 0+233-STA.0+305, TAC. CITY, LEYTE; PROJECT 3. CONST. OF CAUSEWAY, SECT. 3.3, STA. 0+400-STA. 0+448, TAC. CITY, LEY | Region VIII | Region VIII | On-Going | ₱511.9M | 83% | High risk84 | Flagged0.047 |
| 22I00100CLUSTER 3: PROJECT 1. CONST. OF CAUSEWAY, SECTION 3.18, STA. 1+970 - STA. 2+040, TACLOBAN CITY, LEYTE; PROJECT 2. CONST. OF CAUSEWAY, SECTION 3.19, STA. 2+040 - STA. 2+133, TACLOBAN CITY, LEYTE; PROJECT 3. CONST. OF CAUSEWAY, SECTION 3.20, STA. 2+133 - ST | Region VIII | Region VIII | On-Going | ₱311.9M | 88% | High risk85 | Flagged0.045 |
| 24F00509CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF COASTAL ROAD AND SHORE P | Region V | Region V | On-Going | ₱279.4M | 8% | High risk78 | Flagged0.045 |
| 23F00449CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD, NAGAS-SAN ANTONIO, OAS, | Region V | Region V | On-Going | ₱187.3M | 0% | High risk76 | Flagged0.043 |
| 25EH0111CONSTRUCTION OF REVETMENT STRUCTURE ALONG PATO-O RIVER (PHASE 2), ODIONGAN, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱139.8M | 22% | High risk96 | Flagged0.043 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 176 | 21FB0059LOCAL INFRASTRUCTURE PROGRAM - LOCAL ROADS AND BRIDGES - LOCAL ROADS: CONSTRUCTION OF BUYUAN-MATANAG ALTERNATE ROAD, LEGAZPI CITY, ALBAY | Region V | Albay 2nd DEO | On-Going | ₱92.8M | 90% | High risk70 | —-0.030 |
| 177 | 22FB0241BIP: CONSTRUCTION OF ALTERNATE ROAD FROM ALBAY 2ND DISTRICT TO 3RD DISTRICT (MABINIT-BONGA SECTION), LEGAZPI CITY, ALBAY | Region V | Albay 2nd DEO | Completed | ₱99M | 100% | High risk70 | —-0.088 |
| 178 | 18FA0035CONSTRUCTION OF MAYON ECO PARK ROAD, STO. DOMINGO SECTION, STO. DOMINGO, ALBAY | Region V | Albay 1st DEO | Completed | ₱96.5M | 100% | High risk70 | —-0.090 |
| 179 | 18FA0036CONSTRUCTION OF MAYON ECO PARK ROAD, MALILIPOT SECTION, MALILIPOT, ALBAY | Region V | Albay 1st DEO | Completed | ₱96.5M | 100% | High risk70 | —-0.090 |
| 180 | 19FB0089CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - ASPHALT OVERLAY OF PURO-TAYSAN ROAD, LEGAZPI CITY | Region V | Albay 2nd DEO | On-Going | ₱93.1M | 89% | High risk70 | —-0.023 |
| 181 | 18FB0117ASPHALT OVERLAY OF BANQUEROHAN-BARIIS-SUGOY ROAD, LEGAZPI CITY | Region V | Albay 2nd DEO | Completed | ₱92.9M | 100% | High risk70 | —-0.092 |
| 182 | 22F00012OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-LEGAZPI CITY COASTAL ROAD, ALBAY, LEGAZPI CITY, ALBAY 2ND LEGISLATIVE DISTRICT | Region V | Region V | Completed | ₱96.5M | 100% | High risk70 | —-0.085 |
| 183 | 19FO0147CONSTRUCTION/REHABILITATION/IMPROVEMENT OF MOROPONROS-TALISAY-TABLON ROAD, OAS, ALBAY | Region V | Albay 3rd DEO | On-Going | ₱93.1M | 100% | High risk70 | —-0.026 |
| 184 | 23F00011CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BINAGASBASAN. BARANGAY PARAISO, SAN MI | Region V | Region V | Completed | ₱192.8M | 100% | High risk69 | —-0.052 |
| 185 | 19FO0164CONSTRUCTION/REHABILITATION/IMPROVEMENT OF TIONGSON-BALANAC ROAD, LIGAO, ALBAY | Region V | Albay 3rd DEO | Completed | ₱96M | 100% | High risk69 | —-0.087 |
| 186 | 23FB0041SIPAG: CONSTRUCTION OF NAMANTAO DARAGA TO MARIAWA ROAD (PHASE 2), DARAGA, ALBAY | Region V | Albay 2nd DEO | On-Going | ₱92.3M | 82% | High risk69 | —-0.049 |
| 187 | 23F00080ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-SECONDARY ROADS-DAANG MAHARLIKA JCT.-LEGAZPI-STO. DOMINGO-TABACO-CAMARINES | Region V | Region V | On-Going | ₱236.4M | 79% | High risk69 | —-0.030 |
| 188 | 18FB0132IMPROVEMENT/ASPHALT OVERLAY ALONG TAHAO ROAD (IMELDA ROCES AVENUE), LEGAZPI CITY | Region V | Albay 2nd DEO | Completed | ₱92.4M | 100% | High risk69 | —-0.092 |
| 189 | 19FB0043REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - DAANG MAHARLIKA (LZ) - K0519 + 360 - K0520 + 110, K0525 + 225 - K0527 + 000, K0534 + 300 - K0535 + 000 | Region V | Albay 2nd DEO | On-Going | ₱92M | 89% | High risk69 | —-0.024 |
| 190 | 23F00276CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES-CONSTRUCTION OF BAAO LAKESHORE DIKE ROAD(CIRCUMFERENTIAL ROAD) IN SUPPORT OF AGRIC | Region V | Region V | On-Going | ₱235.7M | 87% | High risk69 | —-0.007 |
| 191 | 23F00171CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES-CONSTRUCTION OF BAAO LAKESHORE DIKE ROAD(CIRCUMFERENTIAL ROAD) IN SUPPORT OF AGRIC | Region V | Region V | On-Going | ₱241.2M | 90% | High risk69 | —-0.007 |
| 192 | 23F00018CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES-CONSTRUCTION OF BAAO LAKESHORE DIKE ROAD(CIRCUMFERENTIAL ROAD) IN SUPPORT OF AGRIC | Region V | Region V | Completed | ₱241.2M | 100% | High risk69 | —-0.047 |
| 193 | 22F00135CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF FLORES-ABELLA ROAD, LIGAO CITY | Region V | Region V | On-Going | ₱102.7M | 33% | High risk69 | —-0.027 |
| 194 | 18FA0037CONSTRUCTION OF DAMACAN WATER IMPOUNDING SYSTEM, BACACAY, ALBAY 1ST LD | Region V | Albay 1st DEO | Completed | ₱96.5M | 100% | High risk69 | —-0.051 |
| 195 | 21FB0044CONSTRUCTION OF BATAN-BAGAOBAWAN-MASAGA TOURISM RIDGE VIEW/CROSS COUNTRY ROAD, RAPU-RAPU, ALBAY | Region V | Albay 2nd DEO | On-Going | ₱93.3M | 98% | High risk69 | —-0.030 |
| 196 | 19FA0062CONSTRUCTION OF DAMACAN-LIPATA COASTAL ROAD, BACACAY, ALBAY | Region V | Albay 1st DEO | Completed | ₱94.1M | 100% | High risk69 | —-0.089 |
| 197 | 19FO0166CONSTRUCTION/REHABILITATION/IMPROVEMENT OF MARCIAL O. RAÑOLA-ONGO-PALANAS ROAD, GUINOBATAN, ALBAY | Region V | Albay 3rd DEO | On-Going | ₱92.1M | 100% | High risk69 | —-0.027 |
| 198 | 24FB0171SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF CARACARAN RIDGE ROAD, (PHASE 2), RAPU-RAPU, ALBAY | Region V | Albay 2nd DEO | On-Going | ₱93.5M | 77% | High risk69 | —-0.054 |
| 199 | 21FB0061LOCAL ROADS AND BRIDGES - LOCAL ROADS - CONSTRUCTION OF BUHATAN-GABA TOURISM RIDGE VIEW/CROSS COUNTRY ROAD, RAPU-RAPU, ALBAY | Region V | Albay 2nd DEO | On-Going | ₱93.4M | 100% | High risk69 | —-0.031 |
| 200 | 22FB0142CONSTRUCTION OF RIDGE ROAD, LAGUNDI - BOGTONG, RAPU-RAPU, ALBAY | Region V | Albay 2nd DEO | Completed | ₱95.5M | 100% | High risk69 | —-0.087 |