Contractor dossier
161 projects on file, including joint ventures this contractor is part of.
Total projects
161
Total budget
₱7B
Average progress
93.3%
Completion rate
78.9%
Average risk score
49.3
Medium risk on average, out of 100
Flagged as unusual
5
3.1% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VII | 91 | ₱3.3B | 47.8 | 2 | 97.0% |
| Region X | 70 | ₱3.7B | 51.2 | 3 | 88.5% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 146 | ₱6.4B | 48.1 | 0 | 95.0% |
| Bridges | 6 | ₱51.5M | 42.9 | 0 | 83.3% |
| GAA 2025 OO-1 | 3 | ₱271.1M | 94.4 | 3 | 43.9% |
| OTHER | 3 | ₱90.4M | 69.6 | 1 | 90.0% |
| GAA 2025 SSP | 1 | ₱95.5M | 95.9 | 1 | 47.9% |
| Flood Control and Drainage | 1 | ₱91.4M | 52.8 | 0 | 100.0% |
| Buildings and Facilities | 1 | ₱2.4M | 17.7 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25K00227CONSTRUCTION OF ROAD TO EARTH SKY RESORT, BARANGAY IMBAYAO, MALAYBALAY CITY, BUKIDNON | Region X | Region X | On-Going | ₱95.5M | 48% | High risk96 | Flagged0.022 |
| 25HN0084OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - MACTAN CIRCUMFERENTIAL RD - K0033+460-K0035+100, LAPU-LAPU CITY, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱70.9M | 13% | High risk95 | Flagged0.028 |
| 25H00046ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, ASTURIAS-DANAO-LILOAN BYPASS ROAD (PHASE 6), CEBU | Region VII | Region VII | On-Going | ₱106M | 47% | High risk95 | Flagged0.021 |
| 25K00106CONST. OF BY-PASS AND DIVERSION ROADS, MASTERSON AVENUE ALTERNATE ROAD, PACKAGE 4, CAGAYAN DE ORO CITY | Region X | Region X | On-Going | ₱94.2M | 72% | High risk94 | Flagged0.004 |
| 23K00337CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, JCT CDO TALAKAG ROAD / MACAPAGAL DRIVE - UPPER CARMEN - PATAG - JCT BCIR/ KAUSWAGAN, PACKAGE 6, CAGAYAN DE ORO CITY | Region X | Region X | Completed | ₱28.8M | 100% | High risk72 | —-0.033 |
| 24K00093CONST. OF BY-PASS AND DIVERSION ROADS, JCT. CDO TALAKAG ROAD/MACAPAGAL DRIVE-UPPER CARMEN-PATAG-JCT. BCIR/KAUSWAGAN, PACKAGE 7, CAGAYAN DE ORO CITY | Region X | Region X | On-Going | ₱38M | 70% | High risk72 | Flagged0.001 |
| 20HF0013ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF TOLEDO-PINAMUNGAJAN-ALOGUINSAN-MANTALONGON RD., K0069+000-K0069+227, K0071+000-K0071+710 | Region VII | Cebu 3rd DEO | Completed | ₱23.6M | 100% | High risk65 | —-0.031 |
| 23H00108REHABILITATION/RECONSTRUCTION OF TOLEDO-PINAMUNGAJAN-ALOGUINSAN-MANTALONGON ROAD, K0077+000-K0077+200 L/S AND K0077+950-K0078+050 L/S WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE, CEBU PROVINCE | Region VII | Region VII | On-Going | ₱164.1M | 100% | High risk65 | —-0.032 |
| 23H00035ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, ASTURIAS - DANAO - LILOAN ROAD, CEBU (PHASE 8), CEBU | Region VII | Region VII | On-Going | ₱289.5M | 71% | High risk63 | —-0.007 |
| 23HN0162CSSP: SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BLDG./FACILITIES - REHABILITATION OF PUNTA ENGANO ROAD INCLUDING DRAINAGE FACILITIES, LAPU-LAPU CITY, CEBU | Region VII | Cebu 6th DEO | Completed | ₱96.3M | 100% | High risk61 | —-0.024 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25HN0084OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - MACTAN CIRCUMFERENTIAL RD - K0033+460-K0035+100, LAPU-LAPU CITY, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱70.9M | 13% | High risk95 | Flagged0.028 |
| 25K00227CONSTRUCTION OF ROAD TO EARTH SKY RESORT, BARANGAY IMBAYAO, MALAYBALAY CITY, BUKIDNON | Region X | Region X | On-Going | ₱95.5M | 48% | High risk96 | Flagged0.022 |
| 25H00046ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, ASTURIAS-DANAO-LILOAN BYPASS ROAD (PHASE 6), CEBU | Region VII | Region VII | On-Going | ₱106M | 47% | High risk95 | Flagged0.021 |
| 25K00106CONST. OF BY-PASS AND DIVERSION ROADS, MASTERSON AVENUE ALTERNATE ROAD, PACKAGE 4, CAGAYAN DE ORO CITY | Region X | Region X | On-Going | ₱94.2M | 72% | High risk94 | Flagged0.004 |
| 24K00093CONST. OF BY-PASS AND DIVERSION ROADS, JCT. CDO TALAKAG ROAD/MACAPAGAL DRIVE-UPPER CARMEN-PATAG-JCT. BCIR/KAUSWAGAN, PACKAGE 7, CAGAYAN DE ORO CITY | Region X | Region X | On-Going | ₱38M | 70% | High risk72 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25K00227CONSTRUCTION OF ROAD TO EARTH SKY RESORT, BARANGAY IMBAYAO, MALAYBALAY CITY, BUKIDNON | Region X | Region X | On-Going | ₱95.5M | 48% | High risk96 | Flagged0.022 |
| 2 | 25HN0084OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - MACTAN CIRCUMFERENTIAL RD - K0033+460-K0035+100, LAPU-LAPU CITY, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱70.9M | 13% | High risk95 | Flagged0.028 |
| 3 | 25H00046ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, ASTURIAS-DANAO-LILOAN BYPASS ROAD (PHASE 6), CEBU | Region VII | Region VII | On-Going | ₱106M | 47% | High risk95 | Flagged0.021 |
| 4 | 25K00106CONST. OF BY-PASS AND DIVERSION ROADS, MASTERSON AVENUE ALTERNATE ROAD, PACKAGE 4, CAGAYAN DE ORO CITY | Region X | Region X | On-Going | ₱94.2M | 72% | High risk94 | Flagged0.004 |
| 5 | 23K00337CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, JCT CDO TALAKAG ROAD / MACAPAGAL DRIVE - UPPER CARMEN - PATAG - JCT BCIR/ KAUSWAGAN, PACKAGE 6, CAGAYAN DE ORO CITY | Region X | Region X | Completed | ₱28.8M | 100% | High risk72 | —-0.033 |
| 6 | 24K00093CONST. OF BY-PASS AND DIVERSION ROADS, JCT. CDO TALAKAG ROAD/MACAPAGAL DRIVE-UPPER CARMEN-PATAG-JCT. BCIR/KAUSWAGAN, PACKAGE 7, CAGAYAN DE ORO CITY | Region X | Region X | On-Going | ₱38M | 70% | High risk72 | Flagged0.001 |
| 7 | 20HF0013ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF TOLEDO-PINAMUNGAJAN-ALOGUINSAN-MANTALONGON RD., K0069+000-K0069+227, K0071+000-K0071+710 | Region VII | Cebu 3rd DEO | Completed | ₱23.6M | 100% | High risk65 | —-0.031 |
| 8 | 23H00108REHABILITATION/RECONSTRUCTION OF TOLEDO-PINAMUNGAJAN-ALOGUINSAN-MANTALONGON ROAD, K0077+000-K0077+200 L/S AND K0077+950-K0078+050 L/S WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE, CEBU PROVINCE | Region VII | Region VII | On-Going | ₱164.1M | 100% | High risk65 | —-0.032 |
| 9 | 23H00035ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, ASTURIAS - DANAO - LILOAN ROAD, CEBU (PHASE 8), CEBU | Region VII | Region VII | On-Going | ₱289.5M | 71% | High risk63 | —-0.007 |
| 10 | 23HN0162CSSP: SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BLDG./FACILITIES - REHABILITATION OF PUNTA ENGANO ROAD INCLUDING DRAINAGE FACILITIES, LAPU-LAPU CITY, CEBU | Region VII | Cebu 6th DEO | Completed | ₱96.3M | 100% | High risk61 | —-0.024 |
| 11 | 24HI0038REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG CEBU NORTH HAGNAYA WHARF RD- K0018+000 - K0018+500, K0023+300 - K0024+000, K0031+454 - K0031+948 | Region VII | Cebu 5th DEO | Completed | ₱121.3M | 100% | Medium risk60 | —-0.079 |
| 12 | 25HI0005CSSP SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239 - PREVENTIVE MAINTENANCE - PRIMARY ROADS ALONG CEBU NORTH HAGNAYA WHARF RD - K0022+496 - K0023+300, K0031+963 - K0032+397 | Region VII | Cebu 5th DEO | On-Going | ₱93.5M | 92% | Medium risk59 | —-0.053 |
| 13 | 25HN0085OO1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - MACTAN CIRCUMFERENTIAL RD - K0017+650-K0019+730, LAPU-LAPU CITY, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱96.3M | 2% | Medium risk59 | —-0.023 |
| 14 | 24HN0099CSSP: SIPAG -ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF PUNTA ENGANO ROAD INCLUDING DRAINAGE FACILITIES, LAPU-LAPU CITY, CEBU (PHASE II) | Region VII | Cebu 6th DEO | Completed | ₱96.3M | 100% | Medium risk59 | —-0.084 |
| 15 | 24HI0039REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG CEBU NORTH HAGNAYA WHARF RD - K0047+849 - K0048+000, K0052+302 - K0052+356, K0052+491 - K0052+603, K0062+280 - K0062+342, | Region VII | Cebu 5th DEO | Completed | ₱93M | 100% | Medium risk59 | —-0.085 |
| 16 | 25K00315CONSTRUCTION OF ROAD LEADING TO LILINGAYON CUT FLOWER FARMS, BARANGAY LILINGAYON, VALENCIA CITY, BUKIDNON | Region X | Region X | On-Going | ₱95.9M | 40% | Medium risk57 | —-0.035 |
| 17 | 25K00314CONSTRUCTION OF ROAD LEADING TO MOUNT KITANGLAD AGRI ECO PARK, BARANGAY IMBAYAO, MALAYBALAY CITY, BUKIDNON | Region X | Region X | On-Going | ₱95.8M | 20% | Medium risk57 | —-0.026 |
| 18 | 25K00313CONSTRUCTION OF ROAD LEADING TO CANAYAN VIEW DECK, BARANGAY CANAYAN, MALAYBALAY CITY, BUKIDNON | Region X | Region X | On-Going | ₱96M | 26% | Medium risk57 | —-0.027 |
| 19 | 25KD0062CONSTRUCTION OF ROAD LEADING TO CDO HERITAGE TREE, BARANGAY CUGMAN, CAGAYAN DE ORO CITY | Region X | Cagayan de Oro City 2nd DEO | On-Going | ₱96.4M | 67% | Medium risk57 | —-0.042 |
| 20 | 25KD0061CONSTRUCTION OF ROAD LEADING TO FS CATANICO FALLS, BARANGAY FS CATANICO, CAGAYAN DE ORO CITY | Region X | Cagayan de Oro City 2nd DEO | On-Going | ₱96.4M | 66% | Medium risk57 | —-0.042 |
| 21 | 25KD0060CONSTRUCTION OF ROAD LEADING TO GUADALUPE SHRINE, BARANGAY BALUBAL, CAGAYAN DE ORO CITY | Region X | Cagayan de Oro City 2nd DEO | On-Going | ₱96.4M | 78% | Medium risk57 | —-0.046 |
| 22 | 21K00081CONST. OF BYPASS & DIVERSION ROADS, CDO DIVERSION ROAD(JCT.BALUBAL SAYRE HIGHWAY-PUEBLO DE ORO, CDO | Region X | Region X | Completed | ₱96M | 100% | Medium risk57 | —-0.065 |
| 23 | 25KA0100CONSTRUCTION OF ROAD LEADING TO COMMUNAL RANCH, BARANGAY CAPITAN BAYONG, IMPASUG-ONG, BUKIDNONBRGY. CAPITAN BAYONG, IMPASUG-ONG, BUKIDNON 2ND LD | Region X | Bukidnon 1st DEO | On-Going | ₱96.3M | 58% | Medium risk57 | —-0.039 |
| 24 | 21K00090CONST. OF MISSING LINKS/NEW ROADS, TAGOLOAN-MISAMIS ORIENTAL BOUNDARY,PACKAGE 4, MIS OR | Region X | Region X | Completed | ₱96M | 100% | Medium risk57 | —-0.081 |
| 25 | 25K00404CONSTRUCTION OF ROAD LEADING TO TUGASNON HOT SPRINGS (PHASE 2), BARANGAY TUGASNON, ALUBIJID, MISAMIS ORIENTAL | Region X | Region X | On-Going | ₱115.5M | 26% | Medium risk56 | —-0.027 |