Contractor dossier
45 projects on file, including joint ventures this contractor is part of.
Total projects
45
Total budget
₱2.5B
Average progress
87.3%
Completion rate
66.7%
Below 70%
Average risk score
51.2
Medium risk on average, out of 100
Flagged as unusual
6
13.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-B | 40 | ₱2.4B | 51.8 | 5 | 87.0% |
| Region IV-A | 3 | ₱56.9M | 46.1 | 0 | 100.0% |
| National Capital Region | 2 | ₱35.6M | 47.4 | 1 | 73.4% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 24 | ₱1.2B | 45.4 | 0 | 88.1% |
| Buildings and Facilities | 14 | ₱851.3M | 46.2 | 1 | 82.0% |
| OTHER | 4 | ₱251.8M | 78.4 | 4 | 97.1% |
| GAA 2025 OO-1 | 3 | ₱176.5M | 84.6 | 1 | 91.4% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25EA0077ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, MOGPOG-BALANACAN PORT RD - K0008 + (-147) - K0009 + 000, K0009 + 585 - K0010 + 228 | Region IV-B | Marinduque DEO | On-Going | ₱101M | 74% | High risk93 | Flagged0.008 |
| 25EE0062PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) SECONDARY ROADS ALONG PUERTO PRINCESA NORTH ROAD, K0115+063 - K0115+905, ROXAS, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱34.4M | 100% | High risk81 | —-0.012 |
| 25EE0063PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) SECONDARY ROADS ALONG ROXAS DIVERSION ROAD, K0134+(-711) - K0134+264, ROXAS, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱41.1M | 100% | High risk80 | —-0.013 |
| 24EA0040ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, MOGPOG - BALANACAN PORT RD - K0013+000 - K0013+168, K0013+642 - K0014+203, K0014+317 - K0015+335 | Region IV-B | Marinduque DEO | On-Going | ₱56.9M | 100% | High risk80 | Flagged0.010 |
| 24EA0039ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, MARINDUQUE CIRCUMFERENTIAL RD - K0037+687 - K0039+000 | Region IV-B | Marinduque DEO | On-Going | ₱75M | 100% | High risk79 | Flagged0.004 |
| 24EA0038ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, MARINDUQUE CIRCUMFERENTIAL RD - K0000+000 - K0001+000, K0003+264 - K0004+000, K0027+786-K0028+930 | Region IV-B | Marinduque DEO | On-Going | ₱80.7M | 96% | High risk79 | Flagged0.011 |
| 24EE0128PACKAGE III-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS:1. CONSTRUCTION OF ROAD, ZONE IV. BRGY. ITANGIL, DUMARAN2. CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD FROM NATIONAL HIGHWAY LEADING TO DULI BEACH, EL NIDO3. CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LE | Region IV-B | Palawan 1st DEO | On-Going | ₱39.2M | 92% | High risk76 | Flagged0.015 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 21O00138CONSTRUCTION OF MANDAMUS OFFICE | National Capital Region | National Capital Region | On-Going | ₱30.7M | 47% | Medium risk47 | Flagged0.021 |
| 24EE0128PACKAGE III-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS:1. CONSTRUCTION OF ROAD, ZONE IV. BRGY. ITANGIL, DUMARAN2. CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD FROM NATIONAL HIGHWAY LEADING TO DULI BEACH, EL NIDO3. CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LE | Region IV-B | Palawan 1st DEO | On-Going | ₱39.2M | 92% | High risk76 | Flagged0.015 |
| 24EA0038ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, MARINDUQUE CIRCUMFERENTIAL RD - K0000+000 - K0001+000, K0003+264 - K0004+000, K0027+786-K0028+930 | Region IV-B | Marinduque DEO | On-Going | ₱80.7M | 96% | High risk79 | Flagged0.011 |
| 24EA0040ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, MOGPOG - BALANACAN PORT RD - K0013+000 - K0013+168, K0013+642 - K0014+203, K0014+317 - K0015+335 | Region IV-B | Marinduque DEO | On-Going | ₱56.9M | 100% | High risk80 | Flagged0.010 |
| 25EA0077ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, MOGPOG-BALANACAN PORT RD - K0008 + (-147) - K0009 + 000, K0009 + 585 - K0010 + 228 | Region IV-B | Marinduque DEO | On-Going | ₱101M | 74% | High risk93 | Flagged0.008 |
| 24EA0039ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, MARINDUQUE CIRCUMFERENTIAL RD - K0037+687 - K0039+000 | Region IV-B | Marinduque DEO | On-Going | ₱75M | 100% | High risk79 | Flagged0.004 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25EA0077ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, MOGPOG-BALANACAN PORT RD - K0008 + (-147) - K0009 + 000, K0009 + 585 - K0010 + 228 | Region IV-B | Marinduque DEO | On-Going | ₱101M | 74% | High risk93 | Flagged0.008 |
| 2 | 25EE0062PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) SECONDARY ROADS ALONG PUERTO PRINCESA NORTH ROAD, K0115+063 - K0115+905, ROXAS, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱34.4M | 100% | High risk81 | —-0.012 |
| 3 | 25EE0063PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) SECONDARY ROADS ALONG ROXAS DIVERSION ROAD, K0134+(-711) - K0134+264, ROXAS, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱41.1M | 100% | High risk80 | —-0.013 |
| 4 | 24EA0040ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, MOGPOG - BALANACAN PORT RD - K0013+000 - K0013+168, K0013+642 - K0014+203, K0014+317 - K0015+335 | Region IV-B | Marinduque DEO | On-Going | ₱56.9M | 100% | High risk80 | Flagged0.010 |
| 5 | 24EA0039ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, MARINDUQUE CIRCUMFERENTIAL RD - K0037+687 - K0039+000 | Region IV-B | Marinduque DEO | On-Going | ₱75M | 100% | High risk79 | Flagged0.004 |
| 6 | 24EA0038ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, MARINDUQUE CIRCUMFERENTIAL RD - K0000+000 - K0001+000, K0003+264 - K0004+000, K0027+786-K0028+930 | Region IV-B | Marinduque DEO | On-Going | ₱80.7M | 96% | High risk79 | Flagged0.011 |
| 7 | 24EE0128PACKAGE III-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS:1. CONSTRUCTION OF ROAD, ZONE IV. BRGY. ITANGIL, DUMARAN2. CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD FROM NATIONAL HIGHWAY LEADING TO DULI BEACH, EL NIDO3. CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LE | Region IV-B | Palawan 1st DEO | On-Going | ₱39.2M | 92% | High risk76 | Flagged0.015 |
| 8 | 25EA0020BASIC INFRASTRUCTURE PROGRAM ( BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, REHABILITATION OF MARINDUQUE CONVENTION CENTER, CAPITOL COMPOUND, BRGY. BANGBANGALON, BOAC, MARINDUQUE (PHASE 2) | Region IV-B | Marinduque DEO | On-Going | ₱127.9M | 71% | Medium risk59 | —-0.027 |
| 9 | 25E00128ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE- SECONDARY ROADS, ARAMAYWAN-BERONG-PTO. PRINCESA ROAD, K0098+750-K0098+809; K0098+980-K0101+543, QUEZON, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱125.7M | 14% | Medium risk57 | —-0.006 |
| 10 | 25E00001ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE- SECONDARY ROADS- MARINDUQUE CIRCUMFERENTIAL ROAD, K027+112-K027+786; K028+930-K030+651, MARINDUQUE | Region IV-B | Region IV-B | On-Going | ₱111.7M | 1% | Medium risk56 | —-0.030 |
| 11 | 24EA0077REHABILITATION OF MARINDUQUE CONVENTION CENTER, CAPITOL COMPOUND, BRGY. BANGBANGALON, BOAC, MARINDUQUE | Region IV-B | Marinduque DEO | On-Going | ₱95.3M | 67% | Medium risk55 | —-0.021 |
| 12 | 24EG0015PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - PUERTO PRINCESA SOUTH RD, K0005+000 - K0007+081, PUERTO PRINCESA CITY | Region IV-B | Palawan 3rd DEO | Completed | ₱114.6M | 100% | Medium risk54 | —-0.062 |
| 13 | 21E00098CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF MULTI-PURPOSE BUILDING (PHASE III), BRGY. POBLACION, TORRIJOS, MARINDUQUE | Region IV-B | Region IV-B | Completed | ₱115.8M | 100% | Medium risk54 | —-0.068 |
| 14 | 25E00127ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-SECONDARY ROADS, PUERTO PRINCESA SOUTH ROAD, K0105+832-K0106+665, NARRA, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱109M | 1% | Medium risk54 | —-0.007 |
| 15 | 19EF0156REHABILITATION/IMPROVEMENT (ASPHALT OVERLAY) ALONG QUEZON-PUNTA BAJA & PCR (RIZAL-PANALINGAAN SECTION) K0196+976-K0197+352, K0201+377-K0202+500, K0204+770-K0208+100, PALAWAN | Region IV-B | Palawan 2nd DEO | Completed | ₱96.5M | 100% | Medium risk53 | —-0.046 |
| 16 | 22E00066BASIC INFRASTRUCTURE PROGRAM (BIP)-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONST. OF MULTI-PURPOSE BUILDING (PHASE IV), BRGY. POBLACION, TORRIJOS, MARINDUQUE | Region IV-B | Region IV-B | Completed | ₱99M | 100% | Medium risk51 | —-0.070 |
| 17 | 25EE0065PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) ALONG PUERTO PRINCESA NORTH ROAD, K0263+000 - K0264+975, EL NIDO, PALAWAN | Region IV-B | Palawan 1st DEO | On-Going | ₱82.3M | 100% | Medium risk49 | —-0.045 |
| 18 | 19EE0144REHABILITATION/IMPROVEMENT (ASPHALT OVERLAY) JCT. PAGLAUM-BATO ROAD, K0187+(-691)-K0189+138, K0195+361-K0197+059, K0200+827-K0201+000 TAYTAY, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱57.9M | 100% | Medium risk48 | —-0.057 |
| 19 | 23E00052ROAD WIDENING - SECONDARY ROADS - ROXAS DIVERSION ROAD, KO137+(-709) - KO137+268, ROXAS, PALAWAN | Region IV-B | Region IV-B | Completed | ₱68.5M | 100% | Medium risk48 | —-0.070 |
| 20 | 24EG0005PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - PUERTO PRINCESA SOUTH RD - K0000+000 - K0001+373, PUERTO PRINCESA CITY | Region IV-B | Palawan 3rd DEO | Completed | ₱59M | 100% | Medium risk48 | —-0.070 |
| 21 | 19OB0394CONSTRUCTION OF MULTI-PURPOSE BUILDING, COUNTER INTELLIGENCE GROUP, HQ NAVAL INTELLIGENCE AND SECURITY FORCE, BONIFACIO NAVAL STATION, NAVAL STATION JOSE FRANCISCO, FORT BONIFACIO TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱4.9M | 100% | Medium risk48 | —-0.102 |
| 22 | 21O00138CONSTRUCTION OF MANDAMUS OFFICE | National Capital Region | National Capital Region | On-Going | ₱30.7M | 47% | Medium risk47 | Flagged0.021 |
| 23 | 23E00133SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIP[AG)- CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, PHASE 5, BRGY. POBLACION, TORRIJOS, MARINDUQUE | Region IV-B | Region IV-B | Completed | ₱74.8M | 100% | Medium risk47 | —-0.077 |
| 24 | 24E00088NATIONAL BUILDING PROGRAM- MULYIPURPOSE/FACILITIES- CONST. (COMPLETION) OF BUILDING OF PRESIDENTIAL MANAGEMENT STAFF (PMS)-OFFICE OF THE PRESIDENT (OP) INTEGRATED OPERATIONS & SERVICE CONTINUITY (IOSC) IN BRGY. MONICA, PTO. PRINCESA CITY, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱76M | 35% | Medium risk47 | —-0.002 |
| 25 | 25EE0064PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) - PPNR JCT. - TAYTAY POBLACION ROAD, K0208+116 - K0209+579, TAYTAY, PALAWAN | Region IV-B | Palawan 1st DEO | On-Going | ₱53.8M | 100% | Medium risk46 | —-0.050 |