Contractor dossier
5 projects on file, including joint ventures this contractor is part of.
Total projects
5
Total budget
₱70.6M
Average progress
80.5%
Completion rate
0.0%
Below 70%
Average risk score
65.9
High risk on average, out of 100
Flagged as unusual
2
40.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Cordillera Administrative Region | 4 | ₱42.6M | 63.8 | 1 | 77.8% |
| Region I | 1 | ₱27.9M | 74.4 | 1 | 91.5% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 3 | ₱41.5M | 54.4 | 1 | 78.3% |
| GAA 2025 SSP | 1 | ₱9.7M | 93.2 | 1 | 70.2% |
| OTHER | 1 | ₱19.3M | 73.2 | 0 | 97.5% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25P00004CONSTRUCTION OF ROAD WITH DRAINAGE STRUCTURE, SITIO BAYACSAN, BARANGAY TALOY SUR TO BARANGAY TALOY NORTE, TUBA, BENGUET | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱9.7M | 70% | High risk93 | Flagged0.015 |
| 23AA0503IMPROVEMENT OF ROAD ALONG SAUD-CAPARISPISAN ROAD, BRGY. SAUD, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱27.9M | 92% | High risk74 | Flagged0.023 |
| 24P00082REPAIR/RESTORATION OF INFRASTRUCTURES WHICH WERE DAMAGED BY SEVERE TROPICAL STORM CARINA AND ENHANCED SOUTHWEST MONSOON, KENNON ROAD, K0227+050 - K0227+075, TUBA, BENGUET | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱19.3M | 98% | High risk73 | —-0.001 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23AA0503IMPROVEMENT OF ROAD ALONG SAUD-CAPARISPISAN ROAD, BRGY. SAUD, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱27.9M | 92% | High risk74 | Flagged0.023 |
| 25P00004CONSTRUCTION OF ROAD WITH DRAINAGE STRUCTURE, SITIO BAYACSAN, BARANGAY TALOY SUR TO BARANGAY TALOY NORTE, TUBA, BENGUET | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱9.7M | 70% | High risk93 | Flagged0.015 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25P00004CONSTRUCTION OF ROAD WITH DRAINAGE STRUCTURE, SITIO BAYACSAN, BARANGAY TALOY SUR TO BARANGAY TALOY NORTE, TUBA, BENGUET | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱9.7M | 70% | High risk93 | Flagged0.015 |
| 2 | 23AA0503IMPROVEMENT OF ROAD ALONG SAUD-CAPARISPISAN ROAD, BRGY. SAUD, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱27.9M | 92% | High risk74 | Flagged0.023 |
| 3 | 24P00082REPAIR/RESTORATION OF INFRASTRUCTURES WHICH WERE DAMAGED BY SEVERE TROPICAL STORM CARINA AND ENHANCED SOUTHWEST MONSOON, KENNON ROAD, K0227+050 - K0227+075, TUBA, BENGUET | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱19.3M | 98% | High risk73 | —-0.001 |
| 4 | 25PI0004CSSP, BATO-CUBA-BALICANAO-PUA-MANKINGAO ROAD CONNECTING BATO AND MANKINGAO, BRGY. SADSADAN AND BRGY. MONAMON SUR, BAUKO, MOUNTAIN PROVINCE | Cordillera Administrative Region | Mountain Province 1st DEO | On-Going | ₱4.9M | 82% | Medium risk45 | —-0.048 |
| 5 | 25PI0032OFF-CARRIAGEWAY IMPROVEMENT: BAGUIO-BONTOC RD - K0351 + 108 - K0351 + 212, K0351 + 538 - K0351 + 590, K0351 + 624 - K0351 + 660, K0352 + 895 - K0353 + 165 | Cordillera Administrative Region | Mountain Province 1st DEO | On-Going | ₱8.7M | 61% | Medium risk44 | —-0.045 |