Opening the dossier…
Opening the dossier…
Contractor dossier
27 projects on file, including joint ventures this contractor is part of.
Total projects
27
Total budget
₱1.2B
Average progress
81.9%
Completion rate
48.1%
Below 70%
Average risk score
63.6
High risk on average, out of 100
Flagged as unusual
4
14.8% of their projects
Risk mix
Exhibit A
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 18 | ₱862.7M | 62.3 | 2 | 81.2% |
| Flood Control and Drainage | 6 | ₱151.4M | 58.1 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱93.7M | 95.9 | 1 | 11.5% |
| OTHER | 1 | ₱48.2M | 89.8 | 1 | 48.2% |
| Buildings and Facilities | 1 | ₱57.5M | 62.2 | 0 | 89.9% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25L00132INSTALLATION OF STREETLIGHTS WITH ROAD SAFETY FACILITIES ALONG PADADA - KIBLAWAN - MATANAO RD, DAVAO DEL SUR | Region XI | Region XI | On-Going | ₱93.7M | 12% | High risk96 | Flagged0.045 |
| 24JA0175CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BOALAN RIVER, BARANGAY BOALAN, PACKAGE 2, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱48.2M | 48% | High risk90 | Flagged0.067 |
| 20J00002ASPHALT PRESERVATION - PREVENTIVE MAINTENANCE - SECONDARY ROADS, ZAMBOANGA CITY - LABUAN - LIMPAPA ROAD, ZAMBOANGA CITY | Region IX | Region IX | Completed | ₱115.6M | 100% | High risk73 | —-0.068 |
| 24JA0002ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE- SECONDARY ROADS- ZAMBOANGA CITY- LABUAN- LIMPAPA RD- K1941 + 631 - K1944 + 620 | Region IX | Zamboanga City 2nd DEO | On-Going | ₱91.9M | 93% | High risk72 | —-0.034 |
| 17J00012IMPROVEMENT/WIDENING OF NATIONAL ROADS ZAMBOANGA CITY - LABUAN - LIMPAPA ROAD, ZAMBOANGA CITY (1ST LD), K1966+780.00 - K1967+588.00, K1967+633.00 - K1969+027.00, K1969+170.00 - K1970+180.00, (NET LENGTH: 3,212.00 LN.M.) | Region IX | Region IX | Completed | ₱65.6M | 100% | High risk70 | —-0.013 |
| 17JA0003REHABILITATION/RECONSTRUCTION OF DAMAGED PAVED NATIONAL ROADS, ZAMBOANGA CITY-LABUAN-LIMPAPA ROAD (SO1185MN), ZC IST LDA. K1952+000 TO K1953+000B. K1953+000 TO K1953+963.80C. K1954+235.90 TO K1954+930.10D. K1955+013.60 TO K1955+105E. K1958+301.8 | Region IX | Zamboanga City 2nd DEO | Completed | ₱46.4M | 100% | High risk69 | —-0.046 |
| 17J00013IMPROVEMENT/WIDENING OF NATIONAL ROADS OF ZAMBOANGA CITY - LABUAN - LIMPAPA ROAD, ZAMBOANGA CITY (1ST LD) K1957+427.00 - K1957+674.80, K1957+750.00 - K1957+980.00, K1964+400.00 - K1966+780.00, (NET LENGTH: 2,857.80 LN.M.) | Region IX | Region IX | Terminated | ₱12.2M | 100% | High risk68 | Flagged0.007 |
| 21J00039CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - NRJ ZAMBOANGA CITY - LABUAN - LIMPAPA ROAD (SINUNUC - MALAGUTAY - SAN ROQUE SECTION), ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱87.7M | 96% | High risk67 | —-0.008 |
| 23J00047CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - NRJ SINUNUC-MALAGUTAY-SAN ROQUE SECTION, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱84M | 37% | High risk66 | —-0.016 |
| 23J00046CONSTRUCTION OF BY-PASS AND DIVERSION ROADS NRJ SINUNUC MALAGUTAY SAN ROQUE SECTION, PHASE II, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱60.8M | 36% | High risk66 | —-0.016 |
| 22J00070CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - NRJ SINUNUC-MALAGUTAY-SAN ROQUE SECTION, PHASE II | Region IX | Region IX | On-Going | ₱63.5M | 10% | High risk66 | Flagged0.012 |
| 24JA0003ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE- SECONDARY ROADS- ZAMBOANGA CITY- LABUAN- LIMPAPA RD- K1952+000- K1952+424, K1952+649- K1952+975, K1952+1165- K1952+1215, K1952+1499- K1952+1532, K1952+1677- K1952+1771, K1954+567- K1954+851 | Region IX | Zamboanga City 2nd DEO | On-Going | ₱58.6M | 93% | High risk65 | —-0.036 |
| 17JA0017CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AYALA RIVER, AYALA SECTION (BOTH SIDE), (INCLUDING RIGHT OF WAY ACQUISITION), ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱32.3M | 100% | High risk65 | —-0.028 |
| 21J00002CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL ALONG AYALA RIVER, TULUNGATUNG SECTION, ZAMBOANGA CITY | Region IX | Region IX | Completed | ₱57.9M | 100% | High risk62 | —-0.057 |
| 22JA0026CONSTRUCTION OF HARDENED TYPHOON SHELTER HANGAR FOR FIXED WING AIRCRAFT, AIR COMBAT COMMAND (ACC), EAAB, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱57.5M | 90% | High risk62 | —-0.015 |
| 23JA0004ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS: PAGADIAN CITY - ZAMBOANGA CITY ROAD - K1934 + 800 - K1934 + 175, K1935 + 205 - K1935 + 760 | Region IX | Zamboanga City 2nd DEO | On-Going | ₱44.1M | 88% | High risk60 | —-0.032 |
| 23JA0055ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE-SECONDARY ROADS: GOVERNOR CAMINS ROAD CHAINAGE 465 - CHAINAGE 1866 | Region IX | Zamboanga City 2nd DEO | On-Going | ₱41.7M | 100% | High risk60 | —-0.036 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24JA0175CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BOALAN RIVER, BARANGAY BOALAN, PACKAGE 2, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱48.2M | 48% | High risk90 | Flagged0.067 |
| 25L00132INSTALLATION OF STREETLIGHTS WITH ROAD SAFETY FACILITIES ALONG PADADA - KIBLAWAN - MATANAO RD, DAVAO DEL SUR | Region XI | Region XI | On-Going | ₱93.7M | 12% | High risk96 | Flagged0.045 |
| 22J00070CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - NRJ SINUNUC-MALAGUTAY-SAN ROQUE SECTION, PHASE II | Region IX | Region IX | On-Going | ₱63.5M | 10% | High risk66 | Flagged0.012 |
| 17J00013IMPROVEMENT/WIDENING OF NATIONAL ROADS OF ZAMBOANGA CITY - LABUAN - LIMPAPA ROAD, ZAMBOANGA CITY (1ST LD) K1957+427.00 - K1957+674.80, K1957+750.00 - K1957+980.00, K1964+400.00 - K1966+780.00, (NET LENGTH: 2,857.80 LN.M.) | Region IX | Region IX | Terminated | ₱12.2M | 100% | High risk68 | Flagged0.007 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25L00132INSTALLATION OF STREETLIGHTS WITH ROAD SAFETY FACILITIES ALONG PADADA - KIBLAWAN - MATANAO RD, DAVAO DEL SUR | Region XI | Region XI | On-Going | ₱93.7M | 12% | High risk96 | Flagged0.045 |
| 2 | 24JA0175CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BOALAN RIVER, BARANGAY BOALAN, PACKAGE 2, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱48.2M | 48% | High risk90 | Flagged0.067 |
| 3 | 20J00002ASPHALT PRESERVATION - PREVENTIVE MAINTENANCE - SECONDARY ROADS, ZAMBOANGA CITY - LABUAN - LIMPAPA ROAD, ZAMBOANGA CITY | Region IX | Region IX | Completed | ₱115.6M | 100% | High risk73 | —-0.068 |
| 4 | 24JA0002ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE- SECONDARY ROADS- ZAMBOANGA CITY- LABUAN- LIMPAPA RD- K1941 + 631 - K1944 + 620 | Region IX | Zamboanga City 2nd DEO | On-Going | ₱91.9M | 93% | High risk72 | —-0.034 |
| 5 | 17J00012IMPROVEMENT/WIDENING OF NATIONAL ROADS ZAMBOANGA CITY - LABUAN - LIMPAPA ROAD, ZAMBOANGA CITY (1ST LD), K1966+780.00 - K1967+588.00, K1967+633.00 - K1969+027.00, K1969+170.00 - K1970+180.00, (NET LENGTH: 3,212.00 LN.M.) | Region IX | Region IX | Completed | ₱65.6M | 100% | High risk70 | —-0.013 |
| 6 | 17JA0003REHABILITATION/RECONSTRUCTION OF DAMAGED PAVED NATIONAL ROADS, ZAMBOANGA CITY-LABUAN-LIMPAPA ROAD (SO1185MN), ZC IST LDA. K1952+000 TO K1953+000B. K1953+000 TO K1953+963.80C. K1954+235.90 TO K1954+930.10D. K1955+013.60 TO K1955+105E. K1958+301.8 | Region IX | Zamboanga City 2nd DEO | Completed | ₱46.4M | 100% | High risk69 | —-0.046 |
| 7 | 17J00013IMPROVEMENT/WIDENING OF NATIONAL ROADS OF ZAMBOANGA CITY - LABUAN - LIMPAPA ROAD, ZAMBOANGA CITY (1ST LD) K1957+427.00 - K1957+674.80, K1957+750.00 - K1957+980.00, K1964+400.00 - K1966+780.00, (NET LENGTH: 2,857.80 LN.M.) | Region IX | Region IX | Terminated | ₱12.2M | 100% | High risk68 | Flagged0.007 |
| 8 | 21J00039CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - NRJ ZAMBOANGA CITY - LABUAN - LIMPAPA ROAD (SINUNUC - MALAGUTAY - SAN ROQUE SECTION), ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱87.7M | 96% | High risk67 | —-0.008 |
| 9 | 23J00047CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - NRJ SINUNUC-MALAGUTAY-SAN ROQUE SECTION, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱84M | 37% | High risk66 | —-0.016 |
| 10 | 23J00046CONSTRUCTION OF BY-PASS AND DIVERSION ROADS NRJ SINUNUC MALAGUTAY SAN ROQUE SECTION, PHASE II, ZAMBOANGA CITY | Region IX | Region IX | On-Going | ₱60.8M | 36% | High risk66 | —-0.016 |
| 11 | 22J00070CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - NRJ SINUNUC-MALAGUTAY-SAN ROQUE SECTION, PHASE II | Region IX | Region IX | On-Going | ₱63.5M | 10% | High risk66 | Flagged0.012 |
| 12 | 24JA0003ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE- SECONDARY ROADS- ZAMBOANGA CITY- LABUAN- LIMPAPA RD- K1952+000- K1952+424, K1952+649- K1952+975, K1952+1165- K1952+1215, K1952+1499- K1952+1532, K1952+1677- K1952+1771, K1954+567- K1954+851 | Region IX | Zamboanga City 2nd DEO | On-Going | ₱58.6M | 93% | High risk65 | —-0.036 |
| 13 | 17JA0017CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AYALA RIVER, AYALA SECTION (BOTH SIDE), (INCLUDING RIGHT OF WAY ACQUISITION), ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱32.3M | 100% | High risk65 | —-0.028 |
| 14 | 21J00002CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL ALONG AYALA RIVER, TULUNGATUNG SECTION, ZAMBOANGA CITY | Region IX | Region IX | Completed | ₱57.9M | 100% | High risk62 | —-0.057 |
| 15 | 22JA0026CONSTRUCTION OF HARDENED TYPHOON SHELTER HANGAR FOR FIXED WING AIRCRAFT, AIR COMBAT COMMAND (ACC), EAAB, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱57.5M | 90% | High risk62 | —-0.015 |
| 16 | 23JA0004ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS: PAGADIAN CITY - ZAMBOANGA CITY ROAD - K1934 + 800 - K1934 + 175, K1935 + 205 - K1935 + 760 | Region IX | Zamboanga City 2nd DEO | On-Going | ₱44.1M | 88% | High risk60 | —-0.032 |
| 17 | 23JA0055ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE-SECONDARY ROADS: GOVERNOR CAMINS ROAD CHAINAGE 465 - CHAINAGE 1866 | Region IX | Zamboanga City 2nd DEO | On-Going | ₱41.7M | 100% | High risk60 | —-0.036 |
| 18 | 24JA0142ASSET PRESERVATION PROGRAM: PREVENTIVE MAINTENANCE - SECONDARY ROADS - PATALON BR. ALONG ZAMBOANGA CITY LABUAN - LIMPAPA ROAD | Region IX | Zamboanga City 2nd DEO | On-Going | ₱27.2M | 15% | Medium risk58 | —-0.019 |
| 19 | 21JA0005PREVENTIVE MAINTENANCE - TERTIARY ROADS - OLD RODS (AYALA-TALISAYAN) - K1956 + 386 - K1958 + 136 | Region IX | Zamboanga City 2nd DEO | Completed | ₱22.5M | 100% | Medium risk58 | —-0.079 |
| 20 | 23JA0054ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENACE- TERTIARY ROADS: ASPHALT OVERLAY- SOUTHERN SUPPORT COMMAND ROAD K1945+(-075)-K1945+893 | Region IX | Zamboanga City 2nd DEO | On-Going | ₱17.9M | 95% | Medium risk58 | —-0.033 |
| 21 | 22JA0001PREVENTIVE MAINTENANCE-PRIMARY ROADS-PAGADIAN CITY-ZAMBOANGA CITY RD - K1899 + 805 - K1899 + 947, K1900 + 000 - K1901 + 000, K1901 + 829 - K1902 + 318 | Region IX | Zamboanga City 2nd DEO | Completed | ₱9.7M | 100% | Medium risk56 | —-0.080 |
| 22 | 18JA0016CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE: CONSTRUCTION OF FLOOD CONTROL ALONG AYALA RIVER, TULUNGATUNG SECTION, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱18.8M | 100% | Medium risk56 | —-0.068 |
| 23 | 22JA0020PREVENTIVE MAINTENANCE-OLD ROAD (AYALA-TALISAYAN) K1956+(-597) - K1956+386 | Region IX | Zamboanga City 2nd DEO | Completed | ₱8.8M | 100% | Medium risk56 | —-0.075 |
| 24 | 22JA0021CONSTRUCTION OF SLOPE PROTECTION STRUCTURE, SINUNUC, ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱19.6M | 100% | Medium risk55 | —-0.067 |
| 25 | 18JA0014CONSTRUCTION OF FLOOD CONTROL AT SINUNUC RIVER, (INCLUDING RIGHT OF WAY ACQUISITION), ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | Completed | ₱13.4M | 100% | Medium risk55 | —-0.068 |