Opening the dossier…
Opening the dossier…
Contractor dossier
9 projects on file, including joint ventures this contractor is part of.
Total projects
9
Total budget
₱203.4M
Average progress
99.3%
Completion rate
77.8%
Average risk score
49.3
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region X | 9 | ₱203.4M | 49.3 | 0 | 99.3% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 3 | ₱43.7M | 43.9 | 0 | 98.8% |
| Buildings and Facilities | 3 | ₱14.9M | 38.9 | 0 | 100.0% |
| Flood Control and Drainage | 2 | ₱116.1M | 51.7 | 0 | 100.0% |
| GAA 2025 OO-1 | 1 | ₱28.7M | 91.6 | 0 | 96.9% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25KM0006REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS ALONG MISAMIS ORIENTAL-MA. CRISTINA BDRY. RD K1512 + (-840) - K1512 + (-600), K1512 + (-245) - K1512 + 330 | Region X | Iligan City DEO | On-Going | ₱28.7M | 97% | High risk92 | —-0.016 |
| 2 | 24KM0062CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG ILIGAN RIVER (MERILA), ILIGAN CITY | Region X | Iligan City DEO | Completed | ₱106.5M | 100% | Medium risk59 | —-0.067 |
| 3 | 24KM0043CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ILIGAN RIVER, MERILA, BARANGAY UBALDO LAYA, ILIGAN CITY, LANAO DEL NORTE | Region X | Iligan City DEO | Completed | ₱9.7M | 100% | Medium risk44 | —-0.081 |
| 4 | 24KM0026REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE ALONG ILIGAN CITY DIVERSION RD - K1524+930 - K1524+990, K1530+876 - K1530+896 | Region X | Iligan City DEO | Completed | ₱24.5M | 100% | Medium risk44 | —-0.094 |
| 5 | 25KM0002REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS ALONG MISAMIS ORIENTAL-MA. CRISTINA BDRY. RD K1516+801-K1517+000, K1520+112 - K1520+141, K1520+182 - K1520+308 | Region X | Iligan City DEO | On-Going | ₱14.3M | 96% | Medium risk44 | —-0.061 |
| 6 | 24KM0052CONSTRUCTION OF DRAINAGE, BRGY. LUINAB, CITY OF ILIGAN | Region X | Iligan City DEO | Completed | ₱5M | 100% | Medium risk44 | —-0.095 |
| 7 | 24KM0078CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN LARANJO ELEMENTARY SCHOOL, BARANGAY ROGONGON, ILIGAN CITY, LANAO DEL NORTE | Region X | Iligan City DEO | Completed | ₱5M | 100% | Medium risk39 | —-0.051 |
| 8 | 24KM0081CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN SARDAB ELEMENTARY SCHOOL, BARANGAY DIGKILA-AN, ILIGAN CITY, LANAO DEL NORTE | Region X | Iligan City DEO | Completed | ₱5M | 100% | Medium risk39 | —-0.051 |
| 9 | 24KM0082CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN SULTAN MAMARINTA PANANDIGAN INTEGRATED SCHOOL, BARANGAY BONBONON, ILIGAN CITY, LANAO DEL NORTE | Region X | Iligan City DEO | Completed | ₱5M | 100% | Medium risk39 | —-0.051 |