Contractor dossier
454 projects on file, including joint ventures this contractor is part of.
Total projects
454
Total budget
₱29.7B
Average progress
98.0%
Completion rate
90.1%
Average risk score
50.8
Medium risk on average, out of 100
Flagged as unusual
23
5.1% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XI | 157 | ₱11.7B | 52.0 | 17 | 97.5% |
| Region IV-A | 126 | ₱6B | 53.6 | 2 | 96.8% |
| Region III | 55 | ₱3.9B | 47.4 | 1 | 98.2% |
| Region XII | 38 | ₱3.2B | 42.0 | 0 | 99.9% |
| Region IV-B | 29 | ₱2.1B | 47.3 | 3 | 100.0% |
| National Capital Region | 24 | ₱1B | 50.0 | 0 | 100.0% |
| Region X | 10 | ₱783.8M | 50.6 | 0 | 100.0% |
| Region IX | 7 | ₱318M | 60.1 | 0 | 100.0% |
| Region VI | 2 | ₱48.9M | 60.1 | 0 | 100.0% |
| Region VII | 2 | ₱159.6M | 52.8 | 0 | 100.0% |
| Region XIII | 2 | ₱292.5M | 48.2 | 0 | 100.0% |
| Region VIII | 1 | ₱57.4M | 52.5 | 0 | 100.0% |
| Region I | 1 | ₱71.2M | 51.4 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 170 | ₱14.8B | 52.0 | 12 | 97.4% |
| Flood Control and Drainage | 107 | ₱6.4B | 50.6 | 1 | 99.1% |
| Buildings and Facilities | 79 | ₱3B | 46.7 | 0 | 96.2% |
| Bridges | 58 | ₱2B | 39.8 | 0 | 100.0% |
| OTHER | 29 | ₱2.2B | 71.8 | 5 | 99.3% |
| Bridges, Roads | 9 | ₱1.2B | 65.3 | 4 | 97.0% |
| GAA 2025 SSP | 1 | ₱96.5M | 95.1 | 1 | 86.9% |
| Water Provision and Storage | 1 | ₱3.2M | 24.6 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CM0017CSSP, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD AT CASTILLEJOS, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱96.5M | 87% | High risk95 | Flagged0.013 |
| 19LH0027ROAD WIDENING ALONG DAVAO-BUKIDNON ROAD, K1632+000 TO K1633+252; K1634+420 TO K1634+960, 3RD CONGRESSIONAL DISTRICT, DAVAO CITY | Region XI | Davao City 2nd DEO | Completed | ₱96.5M | 100% | High risk80 | —-0.016 |
| 17L00067WIDENING/RECONST./IMPVT. OF BYPASS RD @ JCT. DAANG MAHARLIKA-LICANAN-BUNAWAN-MAHAYAG-INDANGAN-CABANT | Region XI | Region XI | Completed | ₱142.5M | 100% | High risk80 | Flagged0.018 |
| 25CM0048CSSP, BIP, MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, REHABILITATION OF MULTI-PURPOSE BUILDING (MUNICIPAL HALL) PHASE 2 BARANGAY SAN JUAN, CASTILLEJOS, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱97.9M | 51% | High risk80 | —-0.006 |
| 17L00004REHAB./RECONST./WIDENING OF DAANG MAHARLIKA (MN) INCL. SLOPE PROTECTION (BRGY. CANOCOTAN-BRGY. BINCU | Region XI | Region XI | Completed | ₱207.6M | 100% | High risk79 | Flagged0.022 |
| 17L00023REHAB./RECONST./WIDENING OF DAANG MAHARLIKA (MN) INCL. SLOPE PROTECTION (BRGY. BINCUNGAN SECT.) DAVA | Region XI | Region XI | Completed | ₱165.4M | 100% | High risk79 | Flagged0.017 |
| 17L00055CONC./WIDENING/IMPVT. OF BYPASS ROAD @ JCT. DAANG MAHARLIKA RD-MUDIANG-MALAGAMOT-INDANGAN-CABANTIAN- | Region XI | Region XI | Completed | ₱151.1M | 100% | High risk79 | Flagged0.016 |
| 18M00022CONSTRUCTION OF CONCRETE ROAD AND GRAVEL ROAD TUPI-SARANGANI ROAD (NHW JCT. TUPI-JCT LINAN MIASONG ROAD), PACKAGE A, TUPI, SOUTH COTABATO | Region XII | Region XII | Completed | ₱192.9M | 100% | High risk78 | —-0.003 |
| 19D00063PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMS, CONSTRUCTION OF SLOPE PROTECTION ALONG CARMONA RIVER, PHASE VII, WEST SIDE, CARMONA, CAVITE | Region IV-A | Region IV-A | Completed | ₱144.7M | 100% | High risk77 | Flagged0.015 |
| 17LA0015WIDENING OF HAGUIMITAN BRIDGE (B00063MN) INCLUDING APPROACHES AND RRW, MONKAYO ALONG DAANG MAHARLIKA (MN), COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱73.1M | 100% | High risk77 | —-0.014 |
| 24DO0091ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - MORONG BYPASS ROAD, RIZAL | Region IV-A | Rizal 2nd DEO | On-Going | ₱96.5M | 80% | High risk76 | Flagged0.008 |
| 17K00058CONST. OF TANGUB-BONIFACIO BYPASS RD INCL.ROW & BR,MIS.OCC. 2ND LD | Region X | Region X | Completed | ₱87.8M | 100% | High risk76 | —-0.008 |
| 18DD0001ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT, OFF-CARRIAGEWAY IMPROVEMENT, TERTIARY ROADS, SAN JUAN-LAIYA RD - K0150+262 - K0150+723, K0150+739 - K0151+808, K0151+815 - K0152+940, SAN JUAN, BATANGAS | Region IV-A | Batangas 4th DEO | Completed | ₱96.5M | 100% | High risk74 | —-0.031 |
| 23EB0014REPLACEMENT OF PERMANENT WEAK BRIDGE-ARAANG BUHAY BR. (B00194MR) ALON G MINDORO WEST COASTAL RD | Region IV-B | Mindoro Occidental DEO | Completed | ₱91.7M | 100% | High risk74 | —-0.006 |
| 25CM0018CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD AT SUBIC, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱76.7M | 92% | High risk74 | —-0.032 |
| 17J00048CONSTRUCTION OF FLOOD CONTROL STRUCTURE (POBLACION SIDE) ALONG LAYAWAN RIVER, POLANCO, ZAMBOANGA DEL NORTE, BEG. OF PROJECT: 1 + 047.00, END OF PROJECT: 1 + 571.30, NET LENGTH: 524.30 LN.M. | Region IX | Region IX | Completed | ₱96.5M | 100% | High risk74 | —-0.028 |
| 17LC0003IMPROVEMENT/WIDENING ALONG TAGUM CITY DIVERSION ROAD INCLUDING RROW. K1461+177.411-K1461+640, K1461+640-K1462+690, K1462+690-K1462+705, DAVAO DEL NORTE | Region XI | Davao del Norte DEO | Completed | ₱46.3M | 100% | High risk73 | —-0.025 |
| 17LA0037WIDENING OF LINDA BRIDGE (B00077MN) INCLUDING APPROACHES, NABUNTURAN ALONG DAANG MAHARLIKA (MN), COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱42.6M | 100% | High risk73 | —-0.023 |
| 18LC0015WIDENING OF CAMBAOGO BRIDGE (B015870MN) ALONG ASUNCION-SAN ISIDRO-LAAK-VERUELA ROAD INCLUDING ROW, DAVAO DEL NORTE | Region XI | Davao del Norte DEO | Completed | ₱16M | 100% | High risk73 | —-0.025 |
| 17LA0044WIDENING OF TAGMANOK BRIDGE (B00079MN) INCLUDING APPROACHES, MAWAB ALONG DAANG MAHARLIKA (MN), COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱36.1M | 100% | High risk73 | —-0.024 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 20L00110ROAD UPGRADING OF NHJ BUSO - SO. PAYPAY - TAGBINONGA - SO. CALATAGAN, CALAPAGAN - SO. MATIGDAO, MARAYAG - SO. CALINAWAN, TAOCANGA ROAD, PACKAGE 2, DAVAO ORIENTAL | Region XI | Region XI | On-Going | ₱172.7M | 96% | High risk69 | Flagged0.026 |
| 17E00090WIDENING OF PUERTO PRINCESA SOUTH ROAD (PPSR) FROM TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE STRUCTURES AND OTHER ANCILLARY WORKS, KO207+040.00 TO KO207+121.00; KO207+167.00 TO KO209+194.00; KO209+648.00 TO KO212+000.00, PALAWAN | Region IV-B | Region IV-B | Completed | ₱189.9M | 100% | Medium risk51 | Flagged0.025 |
| 17E00091WIDENING OF PUERTO PRINCESA SOUTH ROAD FROM 2LANES TO 6 LANES INCLUDING DRAINAGE STRUCTURES AND OTHER ANCILLARY WORKS K0212+000 - K0215+738; K0216+000 - K0216+531, PALAWAN | Region IV-B | Region IV-B | Completed | ₱193.5M | 100% | Medium risk51 | Flagged0.023 |
| 17L00004REHAB./RECONST./WIDENING OF DAANG MAHARLIKA (MN) INCL. SLOPE PROTECTION (BRGY. CANOCOTAN-BRGY. BINCU | Region XI | Region XI | Completed | ₱207.6M | 100% | High risk79 | Flagged0.022 |
| 17L00067WIDENING/RECONST./IMPVT. OF BYPASS RD @ JCT. DAANG MAHARLIKA-LICANAN-BUNAWAN-MAHAYAG-INDANGAN-CABANT | Region XI | Region XI | Completed | ₱142.5M | 100% | High risk80 | Flagged0.018 |
| 17E00088WIDENING OF PUERTO PRINCESA SOUTH ROAD (PPSR) FROM TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE STRUCTURES AND OTHER ANCILLARY WORKS, KO195+290.00 TO KO199+789.00, PALAWAN | Region IV-B | Region IV-B | Completed | ₱169.9M | 100% | Medium risk52 | Flagged0.018 |
| 20L00109ROAD UPGRADING OF NHJ BUSO - SO. PAYPAY - TAGBINONGA - SO. CALATAGAN, CALAPAGAN - SO. MATIGDAO, MARAYAG - SO. CALINAWAN, TAOCANGA ROAD, PACKAGE 1, DAVAO ORIENTAL | Region XI | Region XI | On-Going | ₱140.7M | 87% | High risk69 | Flagged0.018 |
| 17L00023REHAB./RECONST./WIDENING OF DAANG MAHARLIKA (MN) INCL. SLOPE PROTECTION (BRGY. BINCUNGAN SECT.) DAVA | Region XI | Region XI | Completed | ₱165.4M | 100% | High risk79 | Flagged0.017 |
| 20L00032RECONSTRUCTION TO CONCRETE PAVEMENT - JCT. R MAGSAYSAY AVE. - L. MA. GUERRERO ST. - GUZMAN ST. - VINZON ST. - T. PALMA GIL ST. - JCT. DACUDAO - JCT. J.P. CABAGUIO AVE., DAVAO CITY | Region XI | Region XI | On-Going | ₱214.5M | 91% | High risk66 | Flagged0.017 |
| 18L00142IMPVT./CONC. OF JCT. DAVAO-BUKIDNON ROAD (CALINAN SECT.)-WANGAN-SUBASTA-TAGAKPAN-TUNGKALAN-TAGURANO- | Region XI | Region XI | On-Going | ₱164.6M | 95% | High risk69 | Flagged0.016 |
| 17L00055CONC./WIDENING/IMPVT. OF BYPASS ROAD @ JCT. DAANG MAHARLIKA RD-MUDIANG-MALAGAMOT-INDANGAN-CABANTIAN- | Region XI | Region XI | Completed | ₱151.1M | 100% | High risk79 | Flagged0.016 |
| 18L00065WIDENING (2 INTO 4 LANES) OF BYPASS RD AT JCT. DAANG MAHARLIKA-LICANAN-BUNAWAN-MAHAYAG-INDANGAN-CABA | Region XI | Region XI | On-Going | ₱222.1M | 99% | High risk66 | Flagged0.015 |
| 19D00063PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMS, CONSTRUCTION OF SLOPE PROTECTION ALONG CARMONA RIVER, PHASE VII, WEST SIDE, CARMONA, CAVITE | Region IV-A | Region IV-A | Completed | ₱144.7M | 100% | High risk77 | Flagged0.015 |
| 25CM0017CSSP, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD AT CASTILLEJOS, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱96.5M | 87% | High risk95 | Flagged0.013 |
| 20L00091CONSTRUCTION OF CONCRETE BRIDGE - TALAGUTONG - BALUNTAYA - TICULON - LITTLE BAGUIO DIVERSION ROAD, PACKAGE C, DAVAO OCCIDENTAL | Region XI | Region XI | On-Going | ₱143.7M | 95% | High risk66 | Flagged0.012 |
| 24DO0091ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - MORONG BYPASS ROAD, RIZAL | Region IV-A | Rizal 2nd DEO | On-Going | ₱96.5M | 80% | High risk76 | Flagged0.008 |
| 22L00057CONSTRUCTION OF CONCRETE ROAD - MAWAB - NABUNTURAN ROAD (NUEVO ILOCO - STA. MONICA, MAINIT ROAD, NABUNTURAN), PACKAGE 1, DAVAO DE ORO | Region XI | Region XI | On-Going | ₱207M | 100% | High risk64 | Flagged0.006 |
| 18L00032ROAD UPGRADING (GRAVEL TO PAVED) OF DEMOLOC-LITTLE BAGUIO-ALABEL RD INCL. ROW (DATU DANWATA SECT.),K | Region XI | Region XI | On-Going | ₱165.6M | 100% | High risk66 | Flagged0.005 |
| 22L00134ROAD WIDENING AT SPECIFIC LOCATIONS ALONG SURIGAO - DAVAO COASTAL RD. (S01376MN), K1795+185 - K1804+334, DAVAO DE ORO | Region XI | Region XI | On-Going | ₱170.8M | 78% | High risk65 | Flagged0.003 |
| 22L00018CONSTRUCTION OF GRAVEL ROAD - BYPASS ROAD AT JCT. DAVAO CITY DIVERSION ROAD - TIGATTO ROAD - JCT. DAVAO CITY DIVERSION ROAD, DAVAO CITY | Region XI | Region XI | On-Going | ₱63.6M | 12% | Medium risk55 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 226 | 24DC0124CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP), BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, COMPLETION OF MULTI-PURPOSE BUILDING (NEW MUNICIPAL BUILDING), BRGY. MAKINA, BALETE, BATANGAS (PHASE 2) | Region IV-A | Batangas 3rd DEO | On-Going | ₱19.8M | 96% | Medium risk51 | —-0.057 |
| 227 | 21DC0192LOCAL PROGRAM, BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES - LOCAL INFRASTRUCTURE PROGRAM, CONSTRUCTION OF MULTI-PURPOSE BUILDING AT NEW TOWN BALETE, BATANGAS | Region IV-A | Batangas 3rd DEO | Completed | ₱23.7M | 100% | Medium risk51 | —-0.103 |
| 228 | 24DC0123CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP), BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, MUNICIPAL BUILDING, BRGY. MAKINA, BALETE, BATANGAS | Region IV-A | Batangas 3rd DEO | Completed | ₱19.7M | 100% | Medium risk51 | —-0.104 |
| 229 | 17LH0002CONSTRUCTION OF REVETMENT ON STEEL SHEET PILES ALONG LIPADAS RIVER, TORIL, DAVAO CITY 3RD LD | Region XI | Davao City 2nd DEO | Completed | ₱29.3M | 100% | Medium risk51 | —-0.050 |
| 230 | 21LD0054REHABILITATION OF CONCRETE REVETMENT ALONG DIGOS RIVER, PUROK CENTENNIAL SECTION, BARANGAY ZONE L, DIGOS CITY, DAVAO DEL SUR | Region XI | Davao del Sur DEO | Completed | ₱57.9M | 100% | Medium risk51 | —-0.073 |
| 231 | 17K00401CONST. OF BY-PASSES/DIVERSION RDS,INCL.ROW,PANGUIL BAY ACCESS RD(TANGUB-COASTAL SECT),PACKAGE 1,MIS. | Region X | Region X | Completed | ₱132.8M | 100% | Medium risk51 | —-0.033 |
| 232 | 23LD0008CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, PILAN RIVER, STA. CRUZ, DAVAO DEL SUR | Region XI | Davao del Sur DEO | Completed | ₱62.7M | 100% | Medium risk51 | —-0.073 |
| 233 | 22L00112CONSTRUCTION OF CONCRETE ROAD - CARMEN - TAGUM CITY COASTAL ROAD, DAVAO DEL NORTE | Region XI | Region XI | On-Going | ₱46.8M | 90% | Medium risk50 | —-0.026 |
| 234 | 20LB0288CONSTRUCTION OF REVETMENT ALONG TALOMO RIVER STA. 3+455 TO STA. 3+542, DAVAO CITY | Region XI | Davao City DEO | Completed | ₱39.2M | 100% | Medium risk50 | —-0.051 |
| 235 | 17L00129WIDENING (4 INTO 6 LANES) OF DAVAO-BUKIDNON RD INCL. RECONST. OF DAMAGED PAVED NAT'L. RD (ASPHALT TO | Region XI | Region XI | Completed | ₱124.6M | 100% | Medium risk50 | —-0.020 |
| 236 | 17LH0001CONSTRUCTION OF REVETMENT ON STEEL SHEET PILES ALONG TALOMO RIVER, BRGY. TUGBOK DISTRICT, DAVAO CITY 3RD LD | Region XI | Davao City 2nd DEO | Completed | ₱19.6M | 100% | Medium risk50 | —-0.051 |
| 237 | 19DD0444LOCAL PROGRAM, CONSTRUCTION/ REPAIR/ REHABILITATION/ IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/ FACILITIES, CONSTRUCTION OF MPB, LTO DISTRICT OFFICE, BRGY. MARAWOY, LIPA CITY, BATANGAS | Region IV-A | Batangas 4th DEO | Completed | ₱28.5M | 100% | Medium risk50 | —-0.101 |
| 238 | 19DD0443LOCAL PROGRAM, CONSTRUCTION/ REPAIR/ REHABILITATION/ IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/ FACILITIES, CONSTRUCTION OF MPB, DENR REGION IV-A CENRO OFFICE, BARANGAY MARAWOY, LIPA CITY, | Region IV-A | Batangas 4th DEO | Completed | ₱28.5M | 100% | Medium risk50 | —-0.101 |
| 239 | 21LB0017REHABILITATION / MAJOR REPAIR OF FLOOD CONTROL STRUCTURE ALONG DAVAO RIVER, SANDAWA SECTION, RIGHT BANK, DAVAO CITY (STA. 2+246 - STA. 2+635) | Region XI | Davao City DEO | Completed | ₱67.6M | 100% | Medium risk50 | —-0.065 |
| 240 | 20M00053ROAD WIDENING -MARBEL - ALLAH VALLEY-COTABATO ROAD, K1775+(-736)-K1779+000, ESPERANZA, SULTAN KUDARAT | Region XII | Region XII | Completed | ₱143.9M | 100% | Medium risk50 | —-0.066 |
| 241 | 18DD0423LOCAL PROGRAM, CONSTRUCTION/REPAIR/REHABILITATION/ IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/ FACILITIES, CONSTRUCTION OF MULTI PURPOSE BUILDING (MUNICIPAL HALL), BRGY. DON LUIS, SAN JOSE, | Region IV-A | Batangas 4th DEO | Completed | ₱19.3M | 100% | Medium risk50 | —-0.104 |
| 242 | 17L00068WIDENING (4 INTO 6 LANES) OF DAVAO-COTABATO RD (DVO. CITY-JCT. DIGOS SECT.) INCL. RROW BRGY. SIRAWAN | Region XI | Region XI | Completed | ₱128.6M | 100% | Medium risk50 | —-0.018 |
| 243 | 17N00005IMPROVEMENT/WIDENING OF NATIONAL ROADS, DAANG MAHARLIKA (SURIGAO - AGUSAN SECTION), K1168+050 - K1168+344, K1168+-094 - K1168+009, K1168+368 - K1168+444, K1169+711 - K1170+200, K1177+340 - K1180+102, KITCHARAO, AGUSAN DEL NORTE | Region XIII | Region XIII | Completed | ₱152.6M | 100% | Medium risk50 | —-0.027 |
| 244 | 24DC0076CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF BALETE MUNICIPAL BUILDING, BALETE, BATANGAS | Region IV-A | Batangas 3rd DEO | Completed | ₱14.8M | 100% | Medium risk50 | —-0.102 |
| 245 | 17L00052WIDENING 2-4 INTO 6 LANES OF DAVAO-COT. RD (DAVAO CITY-JCT. DIGOS SECT.) INCL. RROW (BATO-COGON SECT | Region XI | Region XI | Completed | ₱63.8M | 100% | Medium risk50 | —-0.052 |
| 246 | 20LA0326REPAIR/REHABILITATION/IMPROVEMENT OF ROAD ALONG ASUNCION-SAN ISIDRO-LAAK-VERUELA ROAD, COMPOSTELA VALLEY | Region XI | Davao de Oro 1st DEO | Completed | ₱49.5M | 100% | Medium risk50 | —-0.085 |
| 247 | 17LB0035CONST. OF LATERAL DRAINAGE AT PAMPANGA-COACO MAINDRAIN DAVAO CITY | Region XI | Davao City DEO | Completed | ₱19.6M | 100% | Medium risk50 | —-0.047 |
| 248 | 21DD0234ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF REVETMENT ALONG MALAKING ILOG, SAN JOSE, BATANGAS | Region IV-A | Batangas 4th DEO | Completed | ₱47.5M | 100% | Medium risk50 | —-0.088 |
| 249 | 24DC0131CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP), BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY MAKINA, BALETE, BATANGAS | Region IV-A | Batangas 3rd DEO | On-Going | ₱9.9M | 84% | Medium risk50 | —-0.055 |
| 250 | 24DC0078CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BRGY. MAKINA, BALETE, BATANGAS | Region IV-A | Batangas 3rd DEO | Completed | ₱9.9M | 100% | Medium risk50 | —-0.107 |