Contractor dossier
454 projects on file, including joint ventures this contractor is part of.
Total projects
454
Total budget
₱29.7B
Average progress
98.0%
Completion rate
90.1%
Average risk score
50.8
Medium risk on average, out of 100
Flagged as unusual
23
5.1% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XI | 157 | ₱11.7B | 52.0 | 17 | 97.5% |
| Region IV-A | 126 | ₱6B | 53.6 | 2 | 96.8% |
| Region III | 55 | ₱3.9B | 47.4 | 1 | 98.2% |
| Region XII | 38 | ₱3.2B | 42.0 | 0 | 99.9% |
| Region IV-B | 29 | ₱2.1B | 47.3 | 3 | 100.0% |
| National Capital Region | 24 | ₱1B | 50.0 | 0 | 100.0% |
| Region X | 10 | ₱783.8M | 50.6 | 0 | 100.0% |
| Region IX | 7 | ₱318M | 60.1 | 0 | 100.0% |
| Region VI | 2 | ₱48.9M | 60.1 | 0 | 100.0% |
| Region VII | 2 | ₱159.6M | 52.8 | 0 | 100.0% |
| Region XIII | 2 | ₱292.5M | 48.2 | 0 | 100.0% |
| Region VIII | 1 | ₱57.4M | 52.5 | 0 | 100.0% |
| Region I | 1 | ₱71.2M | 51.4 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 170 | ₱14.8B | 52.0 | 12 | 97.4% |
| Flood Control and Drainage | 107 | ₱6.4B | 50.6 | 1 | 99.1% |
| Buildings and Facilities | 79 | ₱3B | 46.7 | 0 | 96.2% |
| Bridges | 58 | ₱2B | 39.8 | 0 | 100.0% |
| OTHER | 29 | ₱2.2B | 71.8 | 5 | 99.3% |
| Bridges, Roads | 9 | ₱1.2B | 65.3 | 4 | 97.0% |
| GAA 2025 SSP | 1 | ₱96.5M | 95.1 | 1 | 86.9% |
| Water Provision and Storage | 1 | ₱3.2M | 24.6 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CM0017CSSP, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD AT CASTILLEJOS, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱96.5M | 87% | High risk95 | Flagged0.013 |
| 19LH0027ROAD WIDENING ALONG DAVAO-BUKIDNON ROAD, K1632+000 TO K1633+252; K1634+420 TO K1634+960, 3RD CONGRESSIONAL DISTRICT, DAVAO CITY | Region XI | Davao City 2nd DEO | Completed | ₱96.5M | 100% | High risk80 | —-0.016 |
| 17L00067WIDENING/RECONST./IMPVT. OF BYPASS RD @ JCT. DAANG MAHARLIKA-LICANAN-BUNAWAN-MAHAYAG-INDANGAN-CABANT | Region XI | Region XI | Completed | ₱142.5M | 100% | High risk80 | Flagged0.018 |
| 25CM0048CSSP, BIP, MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, REHABILITATION OF MULTI-PURPOSE BUILDING (MUNICIPAL HALL) PHASE 2 BARANGAY SAN JUAN, CASTILLEJOS, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱97.9M | 51% | High risk80 | —-0.006 |
| 17L00004REHAB./RECONST./WIDENING OF DAANG MAHARLIKA (MN) INCL. SLOPE PROTECTION (BRGY. CANOCOTAN-BRGY. BINCU | Region XI | Region XI | Completed | ₱207.6M | 100% | High risk79 | Flagged0.022 |
| 17L00023REHAB./RECONST./WIDENING OF DAANG MAHARLIKA (MN) INCL. SLOPE PROTECTION (BRGY. BINCUNGAN SECT.) DAVA | Region XI | Region XI | Completed | ₱165.4M | 100% | High risk79 | Flagged0.017 |
| 17L00055CONC./WIDENING/IMPVT. OF BYPASS ROAD @ JCT. DAANG MAHARLIKA RD-MUDIANG-MALAGAMOT-INDANGAN-CABANTIAN- | Region XI | Region XI | Completed | ₱151.1M | 100% | High risk79 | Flagged0.016 |
| 18M00022CONSTRUCTION OF CONCRETE ROAD AND GRAVEL ROAD TUPI-SARANGANI ROAD (NHW JCT. TUPI-JCT LINAN MIASONG ROAD), PACKAGE A, TUPI, SOUTH COTABATO | Region XII | Region XII | Completed | ₱192.9M | 100% | High risk78 | —-0.003 |
| 19D00063PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMS, CONSTRUCTION OF SLOPE PROTECTION ALONG CARMONA RIVER, PHASE VII, WEST SIDE, CARMONA, CAVITE | Region IV-A | Region IV-A | Completed | ₱144.7M | 100% | High risk77 | Flagged0.015 |
| 17LA0015WIDENING OF HAGUIMITAN BRIDGE (B00063MN) INCLUDING APPROACHES AND RRW, MONKAYO ALONG DAANG MAHARLIKA (MN), COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱73.1M | 100% | High risk77 | —-0.014 |
| 24DO0091ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - MORONG BYPASS ROAD, RIZAL | Region IV-A | Rizal 2nd DEO | On-Going | ₱96.5M | 80% | High risk76 | Flagged0.008 |
| 17K00058CONST. OF TANGUB-BONIFACIO BYPASS RD INCL.ROW & BR,MIS.OCC. 2ND LD | Region X | Region X | Completed | ₱87.8M | 100% | High risk76 | —-0.008 |
| 18DD0001ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT, OFF-CARRIAGEWAY IMPROVEMENT, TERTIARY ROADS, SAN JUAN-LAIYA RD - K0150+262 - K0150+723, K0150+739 - K0151+808, K0151+815 - K0152+940, SAN JUAN, BATANGAS | Region IV-A | Batangas 4th DEO | Completed | ₱96.5M | 100% | High risk74 | —-0.031 |
| 23EB0014REPLACEMENT OF PERMANENT WEAK BRIDGE-ARAANG BUHAY BR. (B00194MR) ALON G MINDORO WEST COASTAL RD | Region IV-B | Mindoro Occidental DEO | Completed | ₱91.7M | 100% | High risk74 | —-0.006 |
| 25CM0018CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD AT SUBIC, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱76.7M | 92% | High risk74 | —-0.032 |
| 17J00048CONSTRUCTION OF FLOOD CONTROL STRUCTURE (POBLACION SIDE) ALONG LAYAWAN RIVER, POLANCO, ZAMBOANGA DEL NORTE, BEG. OF PROJECT: 1 + 047.00, END OF PROJECT: 1 + 571.30, NET LENGTH: 524.30 LN.M. | Region IX | Region IX | Completed | ₱96.5M | 100% | High risk74 | —-0.028 |
| 17LC0003IMPROVEMENT/WIDENING ALONG TAGUM CITY DIVERSION ROAD INCLUDING RROW. K1461+177.411-K1461+640, K1461+640-K1462+690, K1462+690-K1462+705, DAVAO DEL NORTE | Region XI | Davao del Norte DEO | Completed | ₱46.3M | 100% | High risk73 | —-0.025 |
| 17LA0037WIDENING OF LINDA BRIDGE (B00077MN) INCLUDING APPROACHES, NABUNTURAN ALONG DAANG MAHARLIKA (MN), COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱42.6M | 100% | High risk73 | —-0.023 |
| 18LC0015WIDENING OF CAMBAOGO BRIDGE (B015870MN) ALONG ASUNCION-SAN ISIDRO-LAAK-VERUELA ROAD INCLUDING ROW, DAVAO DEL NORTE | Region XI | Davao del Norte DEO | Completed | ₱16M | 100% | High risk73 | —-0.025 |
| 17LA0044WIDENING OF TAGMANOK BRIDGE (B00079MN) INCLUDING APPROACHES, MAWAB ALONG DAANG MAHARLIKA (MN), COMPOSTELA VALLEY PROVINCE | Region XI | Davao de Oro 1st DEO | Completed | ₱36.1M | 100% | High risk73 | —-0.024 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 20L00110ROAD UPGRADING OF NHJ BUSO - SO. PAYPAY - TAGBINONGA - SO. CALATAGAN, CALAPAGAN - SO. MATIGDAO, MARAYAG - SO. CALINAWAN, TAOCANGA ROAD, PACKAGE 2, DAVAO ORIENTAL | Region XI | Region XI | On-Going | ₱172.7M | 96% | High risk69 | Flagged0.026 |
| 17E00090WIDENING OF PUERTO PRINCESA SOUTH ROAD (PPSR) FROM TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE STRUCTURES AND OTHER ANCILLARY WORKS, KO207+040.00 TO KO207+121.00; KO207+167.00 TO KO209+194.00; KO209+648.00 TO KO212+000.00, PALAWAN | Region IV-B | Region IV-B | Completed | ₱189.9M | 100% | Medium risk51 | Flagged0.025 |
| 17E00091WIDENING OF PUERTO PRINCESA SOUTH ROAD FROM 2LANES TO 6 LANES INCLUDING DRAINAGE STRUCTURES AND OTHER ANCILLARY WORKS K0212+000 - K0215+738; K0216+000 - K0216+531, PALAWAN | Region IV-B | Region IV-B | Completed | ₱193.5M | 100% | Medium risk51 | Flagged0.023 |
| 17L00004REHAB./RECONST./WIDENING OF DAANG MAHARLIKA (MN) INCL. SLOPE PROTECTION (BRGY. CANOCOTAN-BRGY. BINCU | Region XI | Region XI | Completed | ₱207.6M | 100% | High risk79 | Flagged0.022 |
| 17L00067WIDENING/RECONST./IMPVT. OF BYPASS RD @ JCT. DAANG MAHARLIKA-LICANAN-BUNAWAN-MAHAYAG-INDANGAN-CABANT | Region XI | Region XI | Completed | ₱142.5M | 100% | High risk80 | Flagged0.018 |
| 17E00088WIDENING OF PUERTO PRINCESA SOUTH ROAD (PPSR) FROM TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE STRUCTURES AND OTHER ANCILLARY WORKS, KO195+290.00 TO KO199+789.00, PALAWAN | Region IV-B | Region IV-B | Completed | ₱169.9M | 100% | Medium risk52 | Flagged0.018 |
| 20L00109ROAD UPGRADING OF NHJ BUSO - SO. PAYPAY - TAGBINONGA - SO. CALATAGAN, CALAPAGAN - SO. MATIGDAO, MARAYAG - SO. CALINAWAN, TAOCANGA ROAD, PACKAGE 1, DAVAO ORIENTAL | Region XI | Region XI | On-Going | ₱140.7M | 87% | High risk69 | Flagged0.018 |
| 17L00023REHAB./RECONST./WIDENING OF DAANG MAHARLIKA (MN) INCL. SLOPE PROTECTION (BRGY. BINCUNGAN SECT.) DAVA | Region XI | Region XI | Completed | ₱165.4M | 100% | High risk79 | Flagged0.017 |
| 20L00032RECONSTRUCTION TO CONCRETE PAVEMENT - JCT. R MAGSAYSAY AVE. - L. MA. GUERRERO ST. - GUZMAN ST. - VINZON ST. - T. PALMA GIL ST. - JCT. DACUDAO - JCT. J.P. CABAGUIO AVE., DAVAO CITY | Region XI | Region XI | On-Going | ₱214.5M | 91% | High risk66 | Flagged0.017 |
| 18L00142IMPVT./CONC. OF JCT. DAVAO-BUKIDNON ROAD (CALINAN SECT.)-WANGAN-SUBASTA-TAGAKPAN-TUNGKALAN-TAGURANO- | Region XI | Region XI | On-Going | ₱164.6M | 95% | High risk69 | Flagged0.016 |
| 17L00055CONC./WIDENING/IMPVT. OF BYPASS ROAD @ JCT. DAANG MAHARLIKA RD-MUDIANG-MALAGAMOT-INDANGAN-CABANTIAN- | Region XI | Region XI | Completed | ₱151.1M | 100% | High risk79 | Flagged0.016 |
| 18L00065WIDENING (2 INTO 4 LANES) OF BYPASS RD AT JCT. DAANG MAHARLIKA-LICANAN-BUNAWAN-MAHAYAG-INDANGAN-CABA | Region XI | Region XI | On-Going | ₱222.1M | 99% | High risk66 | Flagged0.015 |
| 19D00063PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMS, CONSTRUCTION OF SLOPE PROTECTION ALONG CARMONA RIVER, PHASE VII, WEST SIDE, CARMONA, CAVITE | Region IV-A | Region IV-A | Completed | ₱144.7M | 100% | High risk77 | Flagged0.015 |
| 25CM0017CSSP, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD AT CASTILLEJOS, ZAMBALES | Region III | Zambales 2nd DEO | On-Going | ₱96.5M | 87% | High risk95 | Flagged0.013 |
| 20L00091CONSTRUCTION OF CONCRETE BRIDGE - TALAGUTONG - BALUNTAYA - TICULON - LITTLE BAGUIO DIVERSION ROAD, PACKAGE C, DAVAO OCCIDENTAL | Region XI | Region XI | On-Going | ₱143.7M | 95% | High risk66 | Flagged0.012 |
| 24DO0091ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - MORONG BYPASS ROAD, RIZAL | Region IV-A | Rizal 2nd DEO | On-Going | ₱96.5M | 80% | High risk76 | Flagged0.008 |
| 22L00057CONSTRUCTION OF CONCRETE ROAD - MAWAB - NABUNTURAN ROAD (NUEVO ILOCO - STA. MONICA, MAINIT ROAD, NABUNTURAN), PACKAGE 1, DAVAO DE ORO | Region XI | Region XI | On-Going | ₱207M | 100% | High risk64 | Flagged0.006 |
| 18L00032ROAD UPGRADING (GRAVEL TO PAVED) OF DEMOLOC-LITTLE BAGUIO-ALABEL RD INCL. ROW (DATU DANWATA SECT.),K | Region XI | Region XI | On-Going | ₱165.6M | 100% | High risk66 | Flagged0.005 |
| 22L00134ROAD WIDENING AT SPECIFIC LOCATIONS ALONG SURIGAO - DAVAO COASTAL RD. (S01376MN), K1795+185 - K1804+334, DAVAO DE ORO | Region XI | Region XI | On-Going | ₱170.8M | 78% | High risk65 | Flagged0.003 |
| 22L00018CONSTRUCTION OF GRAVEL ROAD - BYPASS ROAD AT JCT. DAVAO CITY DIVERSION ROAD - TIGATTO ROAD - JCT. DAVAO CITY DIVERSION ROAD, DAVAO CITY | Region XI | Region XI | On-Going | ₱63.6M | 12% | Medium risk55 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 23DC0077ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD MITIGATION STRUCTURES ALONG BUGAAN RIVER - PHASE 3, | Region IV-A | Batangas 3rd DEO | On-Going | ₱94.1M | 98% | High risk65 | —-0.028 |
| 52 | 17DC0003MFO-1 NATIONAL ROAD NETWORK SERVICES, ASSET PRESERVATION OF NATIONAL ROADS, REHABILITATION/RECONSTRU | Region IV-A | Batangas 3rd DEO | Completed | ₱34.5M | 100% | High risk65 | —-0.074 |
| 53 | 18D00019FY 2018 INFRASTRUCTURE PROGRAMORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMNETWORK DEVELOPMENT PROGRAMROAD WIDENING/ TERTIARY ROADSBAUAN-MABINI RD | Region IV-A | Region IV-A | Completed | ₱164M | 100% | High risk65 | —-0.075 |
| 54 | 18L00061CONCRETING OF BOLILA-KIBALATONG-BITO-MANA DIVERSION ROAD, PACKAGE 1 INCLUDING ROW, DAVAO OCCIDENTAL | Region XI | Region XI | Completed | ₱197.6M | 100% | High risk65 | —-0.052 |
| 55 | 18L00041CONC. OF JCT. PADADA(ALONG DIGOS-MAKAR RD)-KIBLAWAN-JCT. MALUNGON(ALONG DIGOS-MAKAR RD) BYPASS RD,PA | Region XI | Region XI | Completed | ₱182.1M | 100% | High risk65 | —-0.060 |
| 56 | 18D00018FY 2018 DPWH INFRASTRUCTURE PROGRAMCONVERGENCE AND SPECIAL SUPPORT PROGRAMCONSTRUCTION / IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONSLOBO-MALABRIGO-LAIYA-SAN JUAN ROAD, LOBO, BATANGAS | Region IV-A | Region IV-A | Completed | ₱142.6M | 100% | High risk65 | —-0.079 |
| 57 | 23DC0076ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG SULPOC - ALT | Region IV-A | Batangas 3rd DEO | On-Going | ₱94M | 80% | High risk65 | —-0.022 |
| 58 | 22L00134ROAD WIDENING AT SPECIFIC LOCATIONS ALONG SURIGAO - DAVAO COASTAL RD. (S01376MN), K1795+185 - K1804+334, DAVAO DE ORO | Region XI | Region XI | On-Going | ₱170.8M | 78% | High risk65 | Flagged0.003 |
| 59 | 25DD0014ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF REVETMENT ALONG LAWAYE RIVE | Region IV-A | Batangas 4th DEO | On-Going | ₱93.7M | 32% | High risk65 | —-0.026 |
| 60 | 22D00050CONSTRUCTION OF TALISOY - APAD ROAD, JOMALIG, QUEZON | Region IV-A | Region IV-A | Completed | ₱168.9M | 100% | High risk65 | —-0.071 |
| 61 | 18L00038CONST./OPENING OF TALAGUTONG-BALUNTAYA-TICULON-LITTLE BAGUIO DIVERSION RD, INCL. ROW, DAVAO OCCIDENT | Region XI | Region XI | On-Going | ₱136.9M | 100% | High risk64 | Flagged0.000 |
| 62 | 22L00057CONSTRUCTION OF CONCRETE ROAD - MAWAB - NABUNTURAN ROAD (NUEVO ILOCO - STA. MONICA, MAINIT ROAD, NABUNTURAN), PACKAGE 1, DAVAO DE ORO | Region XI | Region XI | On-Going | ₱207M | 100% | High risk64 | Flagged0.006 |
| 63 | 21L00124INSTALLATION OF ROAD SAFETY FACILITIES, DAVAO - BUKIDNON ROAD, DAVAO CITY | Region XI | Region XI | Completed | ₱144.7M | 100% | High risk64 | —-0.062 |
| 64 | 18L00035CONCRETING OF NABUNTURAN-MAWAB ROAD, INCLUDING ROW, COMPOSTELA VALLEY | Region XI | Region XI | Completed | ₱224.3M | 100% | High risk64 | —-0.047 |
| 65 | 23DC0074ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG TRAPICHE-PAGASPAS, TANAUA | Region IV-A | Batangas 3rd DEO | Completed | ₱96.5M | 100% | High risk64 | —-0.071 |
| 66 | 23DD0065ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF REVETMENT ALONG LAWAYE RIVE | Region IV-A | Batangas 4th DEO | Completed | ₱96.5M | 100% | High risk64 | —-0.078 |
| 67 | 23DC0075ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM -CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF RIVERBANK PROTECTION ALONG PANSIPIT RIVER - PHASE 7, AGON | Region IV-A | Batangas 3rd DEO | Completed | ₱96.5M | 100% | High risk64 | —-0.073 |
| 68 | 18L00091CONCRETING OF NABUNTURAN-NEW CORELLA-TAGUM ROAD INCLUDING ROW, COMPOSTELA VALLEY | Region XI | Region XI | Completed | ₱224.6M | 100% | High risk64 | —-0.045 |
| 69 | 18L00193CONSTRUCTION OF CONCRETE REVETMENT ON STEEL SHEET PILES ALONG TAGUM - LIBUGANON RIVER, DOWNSTREAM/UPSTREAM MIRANDA BRIDGE II INCLUDING ROW, TAGUM CITY, DAVAO DEL NORTE | Region XI | Region XI | Completed | ₱136.7M | 100% | High risk63 | —-0.045 |
| 70 | 18LF0083UPGRADING OF LAMBOG-CAPASNAN-RIZAL LEADING TO TAOCANGA FMR WITH BRIDGE | Region XI | Davao Oriental 1st DEO | Completed | ₱98M | 100% | High risk63 | —-0.001 |
| 71 | 22DD0303CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING INCLUDING FACILITIES, DEPARTMENT OF AGRICULTURE REGIONAL DROP OFF CENTER - | Region IV-A | Batangas 4th DEO | Completed | ₱96M | 100% | High risk63 | —-0.087 |
| 72 | 18L00067CONC. OF ASUNCION-NEW ALEGRIA-CUAMBOGAN RD CONNECTING ASUNCION OVERLAND TRANSPORT TERMINAL IN SUPPOR | Region XI | Region XI | Completed | ₱131.5M | 100% | High risk63 | —-0.068 |
| 73 | 18L00056CONC. OF NRJ SURIGAO-DAVAO COASTAL RD TO HIJO CADASTRAL CONNECTING TAGUM CITY OVERLAND TRANSPORT TER | Region XI | Region XI | Completed | ₱131.4M | 100% | High risk63 | —-0.041 |
| 74 | 21L00088CONSTRUCTION OF CONCRETE ROAD - TALIKUD CIRCUMFERENTIAL ROAD, IGACOS, DAVAO DEL NORTE | Region XI | Region XI | On-Going | ₱95.5M | 50% | High risk63 | Flagged0.002 |
| 75 | 19L00027RECONSTRUCTION TO CONCRETE PAVEMENT-ON SPECIFIC LOCATIONS ALONG DAVAO-BUKIDNON RD (S01406MN), DAVAO | Region XI | Region XI | Completed | ₱118M | 100% | High risk62 | —-0.070 |