Contractor dossier
243 projects on file, including joint ventures this contractor is part of.
Total projects
243
Total budget
₱7B
Average progress
95.0%
Completion rate
84.0%
Average risk score
48.0
Medium risk on average, out of 100
Flagged as unusual
14
5.8% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region II | 229 | ₱7B | 48.1 | 14 | 94.7% |
| Region IV-A | 14 | ₱94.1M | 46.5 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 129 | ₱2.9B | 43.7 | 0 | 96.2% |
| Flood Control and Drainage | 44 | ₱2.6B | 50.1 | 0 | 98.9% |
| Buildings and Facilities | 36 | ₱308.6M | 39.9 | 0 | 100.0% |
| Bridges | 8 | ₱298.3M | 49.5 | 1 | 97.5% |
| GAA 2025 SSP | 6 | ₱116M | 92.8 | 4 | 71.0% |
| OTHER | 6 | ₱282.4M | 77.6 | 3 | 80.6% |
| Water Provision and Storage | 6 | ₱70.3M | 42.0 | 1 | 83.3% |
| GAA 2025 OO-2 | 4 | ₱289.1M | 89.1 | 2 | 91.6% |
| GAA 2025 OO-1 | 4 | ₱177.1M | 88.2 | 3 | 42.8% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25BB0072CSSP - SPECIAL ROAD FUND - MOTOR VEHICLES USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION/APPLICATION OF RD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG JCT. MAGAPIT - CAPISSAYAN RD - K0557+(-234.80) - K0569+621.30, LAL-LO - GATTARAN, CAGAYAN | Region II | Cagayan 1st DEO | On-Going | ₱29.4M | 49% | High risk95 | Flagged0.025 |
| 25BB0071CSSP - SPECIAL ROAD FUND - MOTOR VEHICLES USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION/APPLICATION OF RD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG CVR (MAGAPIT-JCT APARRI SECT) - K0564+096 - K0571+525, LAL-LO - CAMALANIUGAN, CAGAYAN | Region II | Cagayan 1st DEO | On-Going | ₱19.6M | 30% | High risk95 | Flagged0.029 |
| 25B00081OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS MAHARLIKA HIGHWAY (CAGAYAN VALLEY ROAD) - K0541+000 - K0541+533, K0548+000 - K0548+920, K0549+050 - K0549+940, K0550+094 - K0550+605.50 | Region II | Region II | On-Going | ₱138.5M | 14% | High risk94 | Flagged0.036 |
| 25BB0064CSSP- SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, TANGLAGAN - BOLOS POINT ROAD, GATTARAN, CAGAYAN | Region II | Cagayan 1st DEO | On-Going | ₱9.8M | 100% | High risk94 | Flagged0.005 |
| 25BB0084OO2: PROTECT LIVES & PROPERTIES AGAINST MAJ FLDS - FLD MANAG'T PROG - CONST/REHAB OF FLD MITIGATN FACILITIES W/N MAJ RIVER BASINS & PRINCIPAL RIVERS - CONST OF FLD CONTL STRUCTURE ALONG CAGAYAN RIVER PACKAGE 8, BARANGAY AGUIGUICAN, GATTARAN, CAGAYAN | Region II | Cagayan 1st DEO | On-Going | ₱93.5M | 79% | High risk93 | Flagged0.003 |
| 25BB0038CSSP - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS RDS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, PHASE 1, BARANGAY SAN ANTONIO, BAGGAO, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱4.9M | 100% | High risk92 | —-0.021 |
| 25BB0074OO2: PROTECT LIVES PROPERTIES AGAINST MAJ FLDS - FLD MANAGT PROG - CONST/REHAB OF FLD MITIGATN FACILITIES WITHIN MAJ. RIVER BASINS & PRINCIPAL RIVERS - CFMS - CONST. OF FLD CONTRL STRUCTURE ALONG CAG. RIVER, PACKAGE 6, BRGY. AGUIGUICAN, GATTARAN, CAGAYAN | Region II | Cagayan 1st DEO | On-Going | ₱96.5M | 96% | High risk92 | Flagged0.000 |
| 25BB0148CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - EVACUATION CENTERS/QUARANTINE FACILITIES/ PUBLIC HEALTH FACILITIES - CONSTRUCTION OF EVACUATION CENTER, BARANGAY C. VERZOSA, BAGGAO, CAGAYAN | Region II | Cagayan 1st DEO | On-Going | ₱47.5M | 47% | High risk92 | Flagged0.028 |
| 25BB0083OO2: PROTECT LIVES & PROPERTIES AGAINST MAJ FLOODS - FLD MANAG'T PROG - CONST/REHAB OF FLD MITIGATION FACILITIES W/N MAJOR RIVER BASINS & PRINCIPAL RIVERS - CONST OF FLD CONTROL STRUCTURE ALONG CAGAYAN RIVER PACKAGE 7, BRGY AGUIGUICAN, GATTARAN, CAGAYAN | Region II | Cagayan 1st DEO | On-Going | ₱84.5M | 91% | High risk92 | —-0.003 |
| 25B00092OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - JCT LOGAC -MAGAPIT RD K0705+(-113) - K0705+342.50 | Region II | Region II | On-Going | ₱20M | 100% | High risk91 | —-0.009 |
| 25B00019ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGES: NAGANTATAPIAN BR. (B01094LZ) ALONG MAHARLIKA HIGHWAY ( CAGAYAN VALLEY RD) (PHASE II) | Region II | Region II | On-Going | ₱14.4M | 49% | High risk90 | Flagged0.007 |
| 25BB0104CSSP - BIP - ACCESS RDS AND/OR BR. FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BLDGS/FACILITIES - COC ROAD - CONST OF ROAD GOING TO SMALL WATER IMPOUNDING PROJECT FOR ECOTOURISM, AT BARANGAY DAMMANG NORTE, CAMALANIUGAN, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱4.8M | 100% | High risk89 | —-0.021 |
| 24BB0097OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CONSTRUCTION OF CONCRETE ROAD - ALCALA BYPASS ROAD, ALCALA, CAGAYAN | Region II | Cagayan 1st DEO | On-Going | ₱96.5M | 100% | High risk84 | Flagged0.018 |
| 24B00157DOH - FY 2024 HEALTH CARE FACILITIES ENHANCEMENT PROGRAM (HFEP): LGU HOSPITALS: LGU HOSPITALS - APARRI PROVINCIAL HOSPITAL | Region II | Region II | On-Going | ₱48.3M | 27% | High risk83 | Flagged0.070 |
| 24B00091OO1: ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - CAGAYAN VALLEY RD - K0529+809 - K0530+811, K0535+325 - K0535+400 | Region II | Region II | Completed | ₱69.8M | 100% | High risk82 | —-0.020 |
| 25BB0056OO2: PROTECT LIVES & PROPERTIES AGAINST MAJ. FLDS - FLD MANAG'T PROG - CONST/ MAINT. OF FLD MITIGATION STRUCTURES & DRAINAGE SYSTEMS - CONST.OF REVETMENT, BANURBUR CREEK IRRIGATN SYS., STA. 0+000 - STA 0+050, BUGUEY, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱14.7M | 100% | High risk79 | —-0.037 |
| 24BA0030SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG); ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES- CONSTRUCTION OF SUMNANGA DIVERSION ROAD, SABTANG, BATANES | Region II | Batanes DEO | On-Going | ₱49M | 57% | High risk79 | Flagged0.022 |
| 25B00115OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES - LENGUA BR. (B01087LZ) ALONG MAHARLIKA HIGHWAY (CAGAYAN VALLEY RD) | Region II | Region II | On-Going | ₱4.2M | 8% | High risk78 | Flagged0.016 |
| 24BB0162CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION OF MULTI-PURPOSE BUILDING DIORA ZINUNGAN, STA. ANA, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱4.9M | 100% | High risk69 | —-0.025 |
| 21DF0149LOCAL PROGRAMLOCAL INFRASTRUCTURE PROGRAMBUILDINGS AND OTHER STRUCTURESMULTIPURPOSE/FACILITIESCONSTRUCTION/ REHABILITATION OF MULTI-PURPOSE BUILDING AT BAYAN LUMA V, IMUS; CONSTRUCTION/ REHABILITATION OF MULTI-PURPOSE BUILDING AT PASONG BUAYA, IMU | Region IV-A | Cavite 1st DEO | Completed | ₱13.9M | 100% | High risk68 | —-0.042 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24B00157DOH - FY 2024 HEALTH CARE FACILITIES ENHANCEMENT PROGRAM (HFEP): LGU HOSPITALS: LGU HOSPITALS - APARRI PROVINCIAL HOSPITAL | Region II | Region II | On-Going | ₱48.3M | 27% | High risk83 | Flagged0.070 |
| 24BB0223CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM - CONSTRUCTION OF WATER SYSTEM BARANGAYS CENTRO SUR AND CENTRO NORTE, GATTARAN, CAGAYAN | Region II | Cagayan 1st DEO | On-Going | ₱38.6M | 0% | Medium risk51 | Flagged0.047 |
| 25B00081OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS MAHARLIKA HIGHWAY (CAGAYAN VALLEY ROAD) - K0541+000 - K0541+533, K0548+000 - K0548+920, K0549+050 - K0549+940, K0550+094 - K0550+605.50 | Region II | Region II | On-Going | ₱138.5M | 14% | High risk94 | Flagged0.036 |
| 25BB0071CSSP - SPECIAL ROAD FUND - MOTOR VEHICLES USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION/APPLICATION OF RD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG CVR (MAGAPIT-JCT APARRI SECT) - K0564+096 - K0571+525, LAL-LO - CAMALANIUGAN, CAGAYAN | Region II | Cagayan 1st DEO | On-Going | ₱19.6M | 30% | High risk95 | Flagged0.029 |
| 25BB0148CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - EVACUATION CENTERS/QUARANTINE FACILITIES/ PUBLIC HEALTH FACILITIES - CONSTRUCTION OF EVACUATION CENTER, BARANGAY C. VERZOSA, BAGGAO, CAGAYAN | Region II | Cagayan 1st DEO | On-Going | ₱47.5M | 47% | High risk92 | Flagged0.028 |
| 25BB0072CSSP - SPECIAL ROAD FUND - MOTOR VEHICLES USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION/APPLICATION OF RD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG JCT. MAGAPIT - CAPISSAYAN RD - K0557+(-234.80) - K0569+621.30, LAL-LO - GATTARAN, CAGAYAN | Region II | Cagayan 1st DEO | On-Going | ₱29.4M | 49% | High risk95 | Flagged0.025 |
| 24BA0030SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG); ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES- CONSTRUCTION OF SUMNANGA DIVERSION ROAD, SABTANG, BATANES | Region II | Batanes DEO | On-Going | ₱49M | 57% | High risk79 | Flagged0.022 |
| 24BB0097OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CONSTRUCTION OF CONCRETE ROAD - ALCALA BYPASS ROAD, ALCALA, CAGAYAN | Region II | Cagayan 1st DEO | On-Going | ₱96.5M | 100% | High risk84 | Flagged0.018 |
| 25B00115OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES - LENGUA BR. (B01087LZ) ALONG MAHARLIKA HIGHWAY (CAGAYAN VALLEY RD) | Region II | Region II | On-Going | ₱4.2M | 8% | High risk78 | Flagged0.016 |
| 25B00019ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGES: NAGANTATAPIAN BR. (B01094LZ) ALONG MAHARLIKA HIGHWAY ( CAGAYAN VALLEY RD) (PHASE II) | Region II | Region II | On-Going | ₱14.4M | 49% | High risk90 | Flagged0.007 |
| 25BB0064CSSP- SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, TANGLAGAN - BOLOS POINT ROAD, GATTARAN, CAGAYAN | Region II | Cagayan 1st DEO | On-Going | ₱9.8M | 100% | High risk94 | Flagged0.005 |
| 23B00038OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE - BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGES - NAGANTATAPIAN BRIDGE (B01094LZ) ALONG CAGAYAN VALLEY ROAD | Region II | Region II | On-Going | ₱119.7M | 98% | High risk66 | Flagged0.003 |
| 25BB0084OO2: PROTECT LIVES & PROPERTIES AGAINST MAJ FLDS - FLD MANAG'T PROG - CONST/REHAB OF FLD MITIGATN FACILITIES W/N MAJ RIVER BASINS & PRINCIPAL RIVERS - CONST OF FLD CONTL STRUCTURE ALONG CAGAYAN RIVER PACKAGE 8, BARANGAY AGUIGUICAN, GATTARAN, CAGAYAN | Region II | Cagayan 1st DEO | On-Going | ₱93.5M | 79% | High risk93 | Flagged0.003 |
| 25BB0074OO2: PROTECT LIVES PROPERTIES AGAINST MAJ FLDS - FLD MANAGT PROG - CONST/REHAB OF FLD MITIGATN FACILITIES WITHIN MAJ. RIVER BASINS & PRINCIPAL RIVERS - CFMS - CONST. OF FLD CONTRL STRUCTURE ALONG CAG. RIVER, PACKAGE 6, BRGY. AGUIGUICAN, GATTARAN, CAGAYAN | Region II | Cagayan 1st DEO | On-Going | ₱96.5M | 96% | High risk92 | Flagged0.000 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 226 | 23BB0041CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SAN CARLOS, GATTARAN, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱3M | 100% | Low risk27 | —-0.081 |
| 227 | 23BB0031CSSP - BASIC INFRASTRUCTURE PROGRAM - MULTI- PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICE - CONST. (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY AGUIGUICAN, GATTARAN, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱3M | 100% | Low risk27 | —-0.082 |
| 228 | 23BB0083CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDING/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY TALIGAN, GATTARAN, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱3M | 100% | Low risk27 | —-0.083 |
| 229 | 23BB0020CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INSFRASTRUCTURE PROGRAM MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY STA. MARIA, GATTARAN, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱3M | 100% | Low risk27 | —-0.083 |
| 230 | 22BB0153CSSP-CONS./REHAB.OFWTRSUPLY/SEPTEAGE &SEWERAGE/RNWATRCOLECTR SYS- RAINWTER COLECTOR INPBLC FCILIT'S,ARIDOWENES;MABANGUC ES;GONZAGA NHS-STA.CLARA; PATENG PS,GONZAGA; PARUDDUN NORTE ES;PLAZA PS; SAN MARIANO ES; LICERIO ANTIPORDASR. NHS-STA.ISABELEXTENSN | Region II | Cagayan 1st DEO | Completed | ₱4.4M | 100% | Low risk26 | —-0.047 |
| 231 | 20DG0030CONSTRUCTION OF MULTI-PURPOSE BRGY. HALL, BRGY. MARAHAN II, ALFONSO, CAVITE | Region IV-A | Cavite 2nd DEO | Completed | ₱3.5M | 100% | Low risk26 | —-0.104 |
| 232 | 20DG0032CONST. OF MULTI-PURPOSE BLDG., BRGY. PANTIHAN 3, MARAGONDON, CAVITE | Region IV-A | Cavite 2nd DEO | Completed | ₱3.5M | 100% | Low risk26 | —-0.104 |
| 233 | 23BC0203CONSTRUCTION OF FARM-TO-MILL ROAD, SITIO MALASAT, STO. DOMINGO TO STA. BARBARA, PIAT, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱4.1M | 100% | Low risk24 | —-0.033 |
| 234 | 23BB0040CSSP- BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICE - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY PATENG, GONZAGA, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱2M | 100% | Low risk23 | —-0.078 |
| 235 | 23BB0011CSSP - CONST./IMPROV'T OF ACCESS RDS LEADING TO TRADES, INDUSTRIES & ECONOMICS ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRA. PROG. - ROLL-IT) - CONST. OF CONC. RD - JGCCSMBPR TO PIÑA WESTE LEADING TO BANANA PLANTATION, GATTARAN, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱2.4M | 100% | Low risk23 | —-0.080 |
| 236 | 23BB0009CSSP - CONST./IMPROVEMENT OF ACCESS RDS LEADING TO TRADES, INDUSTRIES AND ECONOMICS ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRA. PROG - ROLL-IT) - JGCCSMBPR TO CAPISSAYAN NORTE - SIBUGA LEADING TO BANANA PLANTATION, GATTARAN, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱2.4M | 100% | Low risk23 | —-0.080 |
| 237 | 22BB0067CSSP - CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE IN SUPPORT OF NATIONAL SECURITY (TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM - (TIKAS) - CONSTRUCTION OF SUPPLY STORAGE, STANDARD, LAL-LO, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱1.1M | 100% | Low risk18 | —-0.049 |
| 238 | 18BD0067CONSTRUCTION OF CONCRETE ROAD, BRGY. NANGUILATTAN, PENABLANCA, CAGAYAN | Region II | Cagayan 3rd DEO | Completed | ₱1.9M | 100% | Low risk18 | —-0.081 |
| 239 | 23BB0035OO1: ENSURE SAFE & RELIABLE NAT'L RD SYSTEM - ASSET PRESERVATION PROGRAM -PREVENTIVE MAINTENANCE - PRIMARY RD -CONCRETE REBLOCKING - CVR - K0549+004 - K0550+922, GATTARAN, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱1.5M | 100% | Low risk18 | —-0.081 |
| 240 | 21BB0190CONSTRUCTION OF CLASSROOMS - CONSTRUCTION/COMPLETION OF 3STY9CL AT CALAOAGAN DACKEL, NHS, GATTARAN, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱4.1M | 100% | Low risk14 | —-0.037 |
| 241 | 21BB0177CONSTRUCTION OF CLASSROOMS-CONSTRUCTION/COMPLETION OF 3STY12CL (2-REG WORKSHOP, 2-SCIENCE LAB, 2-ICT LAB), PATTAO NHS, BUGUEY, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱1.5M | 100% | Low risk9 | —-0.037 |
| 242 | 21BB0185CONSTRUCTION OF SCHOOL BUILDINGS- CONSTRUCTION/COMPLETION OF 2STY8CL (2-SCIENCE LAB, 2-ICT LAB), LICERIO ANTIPORDA SR. NHS, BUGUEY, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱929K | 100% | Low risk8 | —-0.036 |
| 243 | 21BB0184CONSTRUCTION OF CLASSROOMS - CONSTRUCTION/COMPLETION OF 2STY10CL (4-REG. WORKSHOP, 2-ACAD RM), LICERIO ANTIPORDA SR. NHS, BUGUEY, CAGAYAN | Region II | Cagayan 1st DEO | Completed | ₱987K | 100% | Low risk8 | —-0.036 |