Contractor dossier
71 projects on file, including joint ventures this contractor is part of.
Total projects
71
Total budget
₱3B
Average progress
82.5%
Completion rate
62.0%
Below 70%
Average risk score
54.6
Medium risk on average, out of 100
Flagged as unusual
12
16.9% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VI | 65 | ₱2.8B | 55.0 | 12 | 81.1% |
| Negros Island Region | 6 | ₱206.2M | 50.1 | 0 | 98.2% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 43 | ₱1.8B | 51.2 | 2 | 86.2% |
| Buildings and Facilities | 16 | ₱597.4M | 56.0 | 6 | 70.0% |
| Flood Control and Drainage | 8 | ₱349.7M | 52.0 | 1 | 92.0% |
| OTHER | 2 | ₱136.2M | 86.6 | 2 | 79.0% |
| GAA 2025 SSP | 1 | ₱29.7M | 95.0 | 1 | 57.9% |
| GAA 2025 OO-2 | 1 | ₱52.7M | 92.3 | 0 | 84.1% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25GG0162CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY BUENAFLOR - EMBARKADERO, DUMANGAS, ILOILO | Region VI | Iloilo 2nd DEO | On-Going | ₱29.7M | 58% | High risk95 | Flagged0.026 |
| 25GF0095CONSTRUCTION OF SHORELINE PROTECTION STRUCTURE INCLUDING FACILITES, BARANGAY LANUTAN, MIAGAO, ILOILO | Region VI | Iloilo 1st DEO | On-Going | ₱52.7M | 84% | High risk92 | —-0.005 |
| 25GG0213CONCRETING OF FMR AT BRGY. MALAPULA TO BITA-OGAN, SITIO LIBTOG, PASSI CITY, ILOILO | Region VI | Iloilo 2nd DEO | On-Going | ₱39.7M | 70% | High risk89 | Flagged0.056 |
| 24GG0144CONSTRUCTION OF ROAD IN BRGY. BINOLUSAN - BRGY. HILWAN, CALINOG, ILOILO | Region VI | Iloilo 2nd DEO | On-Going | ₱96.5M | 88% | High risk84 | Flagged0.014 |
| 24GA0152REHABILITATION OF MULTI-PURPOSE BUILDING, MUNICIPALITY OF KALIBO, AKLAN | Region VI | Aklan DEO | On-Going | ₱49.7M | 60% | High risk74 | —-0.009 |
| 17G00101PROPOSED CONSTRUCTION OF THREE (3) STOREY DA REGIONAL OFFICE VI PLUS PENTHOUSE/ROOFDECK | Region VI | Region VI | Completed | ₱120M | 100% | High risk71 | Flagged0.016 |
| 17G00065ROAD WIDENING - ILOILO - CAPIZ RD (OLD ROUTE) INCLUDING RROW K0061+512 - K0063+840 | Region VI | Region VI | Completed | ₱75M | 100% | High risk70 | —-0.043 |
| 25GR0019CONSTRUCTION OF FLOOD CONTROL/SLOPE PROTECTION ALONG TIGUM RIVER, MAASIN ILOILO | Region VI | Iloilo 6th DEO | On-Going | ₱39.1M | 36% | High risk70 | Flagged0.003 |
| 17GF0025CONSTRUCTION OF CONCRETE ROAD - ACCESS ROAD LEADING TO GUIMBAL PORT, GUIMBAL, ILOILO, STA. 0+544.282 TO STA. 0+884.282 (SHORELINE); STA. 0+000 - STA. 0+558.92 (GENEROSA RD.); STA. 0+000 - STA. 0+532 (TORREBLANCA RD); STA. 0+000 - STA. 0+458.87 (GARIEL RD. | Region VI | Iloilo 1st DEO | Completed | ₱90.6M | 100% | High risk69 | —-0.042 |
| 25GG0217CONCRETING OF BRGY. NUEVA UNION FMR, BRGY. NUEVA UNION, PASSI CITY, ILOILO | Region VI | Iloilo 2nd DEO | On-Going | ₱34.8M | 52% | High risk69 | Flagged0.040 |
| 25GR0044OFF-CARRIAGEWAY IMPROVEMENT - JANIUAY DIVERSION ROAD, ILOILO | Region VI | Iloilo 6th DEO | On-Going | ₱38.9M | 25% | High risk67 | —-0.007 |
| 24GH0140CONSTRUCTION OF ROAD, BRGY. GEN. LUNA, BAROTAC VIEJO- BRGY. AGBOBOLO- BRGY. PROGRESO, AJUY, ILOILO (PHASE 2) | Region VI | Iloilo 3rd DEO | Completed | ₱29.7M | 100% | High risk67 | —-0.054 |
| 17GH0041ROAD WIDENING - BALASAN - CARLES RD INCLUDING RROW - K0175+621 - K0177+061, BALASAN, ILOILO | Region VI | Iloilo 3rd DEO | Completed | ₱41.7M | 100% | High risk66 | —-0.052 |
| 20GA0064AKLAN RIVER FLOOD CONTROL PROJECTS, NUMANCIA, AKLAN | Region VI | Aklan DEO | Completed | ₱96.5M | 100% | High risk64 | —-0.056 |
| 23GJ0122CONSTRUCTION OF 3STY6CL AT ILOILO CENTRAL ES | Region VI | Iloilo City DEO | On-Going | ₱17.8M | 72% | High risk63 | Flagged0.033 |
| 24G00066SHARED PROCESSING FACILITY - VIRGIN COCONUT OIL (PREMIUM BUILDING) | Region VI | Region VI | On-Going | ₱19M | 95% | High risk62 | Flagged0.016 |
| 23GJ0123CONSTRUCTION OF 2STY4CL AT I. ARROYO ES, BRGY. NORTH FUNDIDOR, MOLO, ILOILO CITY | Region VI | Iloilo City DEO | On-Going | ₱15.1M | 95% | High risk62 | Flagged0.026 |
| 24G00139LGU HOSPITALS- KALIBO COMMUNITY HOSPITAL, AKLAN | Region VI | Region VI | On-Going | ₱29.8M | 2% | High risk62 | Flagged0.047 |
| 24GH0172CONSTRUCTION OF MULTI-PURPOSE BUILDING, NORTHERN ILOILO STATE UNIVERSITY (NISU), SARA, ILOILO | Region VI | Iloilo 3rd DEO | On-Going | ₱98.8M | 28% | High risk62 | —-0.004 |
| 20G00024CONSTRUCTION OF CONCRETE ROAD - MAAYON - SARA ROAD, CAPIZ | Region VI | Region VI | Completed | ₱96M | 100% | High risk60 | —-0.070 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25GG0213CONCRETING OF FMR AT BRGY. MALAPULA TO BITA-OGAN, SITIO LIBTOG, PASSI CITY, ILOILO | Region VI | Iloilo 2nd DEO | On-Going | ₱39.7M | 70% | High risk89 | Flagged0.056 |
| 24G00139LGU HOSPITALS- KALIBO COMMUNITY HOSPITAL, AKLAN | Region VI | Region VI | On-Going | ₱29.8M | 2% | High risk62 | Flagged0.047 |
| 25GG0217CONCRETING OF BRGY. NUEVA UNION FMR, BRGY. NUEVA UNION, PASSI CITY, ILOILO | Region VI | Iloilo 2nd DEO | On-Going | ₱34.8M | 52% | High risk69 | Flagged0.040 |
| 24GF0144CONCRETING OF BRGY. QUI-ANAN TO BRGY. DACDACANAN FMR, BRGY. QUI-ANAN AND BRGY. DACDACANAN, SAN JOAQUIN, ILOILO | Region VI | Iloilo 1st DEO | On-Going | ₱29.7M | 0% | Medium risk48 | Flagged0.035 |
| 23GJ0122CONSTRUCTION OF 3STY6CL AT ILOILO CENTRAL ES | Region VI | Iloilo City DEO | On-Going | ₱17.8M | 72% | High risk63 | Flagged0.033 |
| 25GG0162CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY BUENAFLOR - EMBARKADERO, DUMANGAS, ILOILO | Region VI | Iloilo 2nd DEO | On-Going | ₱29.7M | 58% | High risk95 | Flagged0.026 |
| 23GJ0123CONSTRUCTION OF 2STY4CL AT I. ARROYO ES, BRGY. NORTH FUNDIDOR, MOLO, ILOILO CITY | Region VI | Iloilo City DEO | On-Going | ₱15.1M | 95% | High risk62 | Flagged0.026 |
| 24G00140LGU HOSPITALS- MADALAG DISTRICT HOSPITAL, AKLAN | Region VI | Region VI | On-Going | ₱19.9M | 1% | Medium risk44 | Flagged0.025 |
| 17G00101PROPOSED CONSTRUCTION OF THREE (3) STOREY DA REGIONAL OFFICE VI PLUS PENTHOUSE/ROOFDECK | Region VI | Region VI | Completed | ₱120M | 100% | High risk71 | Flagged0.016 |
| 24G00066SHARED PROCESSING FACILITY - VIRGIN COCONUT OIL (PREMIUM BUILDING) | Region VI | Region VI | On-Going | ₱19M | 95% | High risk62 | Flagged0.016 |
| 24GG0144CONSTRUCTION OF ROAD IN BRGY. BINOLUSAN - BRGY. HILWAN, CALINOG, ILOILO | Region VI | Iloilo 2nd DEO | On-Going | ₱96.5M | 88% | High risk84 | Flagged0.014 |
| 25GR0019CONSTRUCTION OF FLOOD CONTROL/SLOPE PROTECTION ALONG TIGUM RIVER, MAASIN ILOILO | Region VI | Iloilo 6th DEO | On-Going | ₱39.1M | 36% | High risk70 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25GG0162CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY BUENAFLOR - EMBARKADERO, DUMANGAS, ILOILO | Region VI | Iloilo 2nd DEO | On-Going | ₱29.7M | 58% | High risk95 | Flagged0.026 |
| 2 | 25GF0095CONSTRUCTION OF SHORELINE PROTECTION STRUCTURE INCLUDING FACILITES, BARANGAY LANUTAN, MIAGAO, ILOILO | Region VI | Iloilo 1st DEO | On-Going | ₱52.7M | 84% | High risk92 | —-0.005 |
| 3 | 25GG0213CONCRETING OF FMR AT BRGY. MALAPULA TO BITA-OGAN, SITIO LIBTOG, PASSI CITY, ILOILO | Region VI | Iloilo 2nd DEO | On-Going | ₱39.7M | 70% | High risk89 | Flagged0.056 |
| 4 | 24GG0144CONSTRUCTION OF ROAD IN BRGY. BINOLUSAN - BRGY. HILWAN, CALINOG, ILOILO | Region VI | Iloilo 2nd DEO | On-Going | ₱96.5M | 88% | High risk84 | Flagged0.014 |
| 5 | 24GA0152REHABILITATION OF MULTI-PURPOSE BUILDING, MUNICIPALITY OF KALIBO, AKLAN | Region VI | Aklan DEO | On-Going | ₱49.7M | 60% | High risk74 | —-0.009 |
| 6 | 17G00101PROPOSED CONSTRUCTION OF THREE (3) STOREY DA REGIONAL OFFICE VI PLUS PENTHOUSE/ROOFDECK | Region VI | Region VI | Completed | ₱120M | 100% | High risk71 | Flagged0.016 |
| 7 | 17G00065ROAD WIDENING - ILOILO - CAPIZ RD (OLD ROUTE) INCLUDING RROW K0061+512 - K0063+840 | Region VI | Region VI | Completed | ₱75M | 100% | High risk70 | —-0.043 |
| 8 | 25GR0019CONSTRUCTION OF FLOOD CONTROL/SLOPE PROTECTION ALONG TIGUM RIVER, MAASIN ILOILO | Region VI | Iloilo 6th DEO | On-Going | ₱39.1M | 36% | High risk70 | Flagged0.003 |
| 9 | 17GF0025CONSTRUCTION OF CONCRETE ROAD - ACCESS ROAD LEADING TO GUIMBAL PORT, GUIMBAL, ILOILO, STA. 0+544.282 TO STA. 0+884.282 (SHORELINE); STA. 0+000 - STA. 0+558.92 (GENEROSA RD.); STA. 0+000 - STA. 0+532 (TORREBLANCA RD); STA. 0+000 - STA. 0+458.87 (GARIEL RD. | Region VI | Iloilo 1st DEO | Completed | ₱90.6M | 100% | High risk69 | —-0.042 |
| 10 | 25GG0217CONCRETING OF BRGY. NUEVA UNION FMR, BRGY. NUEVA UNION, PASSI CITY, ILOILO | Region VI | Iloilo 2nd DEO | On-Going | ₱34.8M | 52% | High risk69 | Flagged0.040 |
| 11 | 25GR0044OFF-CARRIAGEWAY IMPROVEMENT - JANIUAY DIVERSION ROAD, ILOILO | Region VI | Iloilo 6th DEO | On-Going | ₱38.9M | 25% | High risk67 | —-0.007 |
| 12 | 24GH0140CONSTRUCTION OF ROAD, BRGY. GEN. LUNA, BAROTAC VIEJO- BRGY. AGBOBOLO- BRGY. PROGRESO, AJUY, ILOILO (PHASE 2) | Region VI | Iloilo 3rd DEO | Completed | ₱29.7M | 100% | High risk67 | —-0.054 |
| 13 | 17GH0041ROAD WIDENING - BALASAN - CARLES RD INCLUDING RROW - K0175+621 - K0177+061, BALASAN, ILOILO | Region VI | Iloilo 3rd DEO | Completed | ₱41.7M | 100% | High risk66 | —-0.052 |
| 14 | 20GA0064AKLAN RIVER FLOOD CONTROL PROJECTS, NUMANCIA, AKLAN | Region VI | Aklan DEO | Completed | ₱96.5M | 100% | High risk64 | —-0.056 |
| 15 | 23GJ0122CONSTRUCTION OF 3STY6CL AT ILOILO CENTRAL ES | Region VI | Iloilo City DEO | On-Going | ₱17.8M | 72% | High risk63 | Flagged0.033 |
| 16 | 24G00066SHARED PROCESSING FACILITY - VIRGIN COCONUT OIL (PREMIUM BUILDING) | Region VI | Region VI | On-Going | ₱19M | 95% | High risk62 | Flagged0.016 |
| 17 | 23GJ0123CONSTRUCTION OF 2STY4CL AT I. ARROYO ES, BRGY. NORTH FUNDIDOR, MOLO, ILOILO CITY | Region VI | Iloilo City DEO | On-Going | ₱15.1M | 95% | High risk62 | Flagged0.026 |
| 18 | 24G00139LGU HOSPITALS- KALIBO COMMUNITY HOSPITAL, AKLAN | Region VI | Region VI | On-Going | ₱29.8M | 2% | High risk62 | Flagged0.047 |
| 19 | 24GH0172CONSTRUCTION OF MULTI-PURPOSE BUILDING, NORTHERN ILOILO STATE UNIVERSITY (NISU), SARA, ILOILO | Region VI | Iloilo 3rd DEO | On-Going | ₱98.8M | 28% | High risk62 | —-0.004 |
| 20 | 20G00024CONSTRUCTION OF CONCRETE ROAD - MAAYON - SARA ROAD, CAPIZ | Region VI | Region VI | Completed | ₱96M | 100% | High risk60 | —-0.070 |
| 21 | 20G00061ROAD WIDENING - AT SPECIFIC LOCATIONS ALONG ILOILO - ANTIQUE RD K0121+639 - K0124+835 | Region VI | Region VI | Completed | ₱96.6M | 100% | Medium risk59 | —-0.063 |
| 22 | 25GA0011CONSTRUCTION OF MULTI-PURPOSE BUILDING, CALANGCANG, MAKATO, AKLAN | Region VI | Aklan DEO | On-Going | ₱86.4M | 6% | Medium risk57 | —-0.006 |
| 23 | 24HM0011CONVERGENCE AND SPECIAL SUPPORT PROGRAM, CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT), LAMBOJON ROAD CONNECTING TO MANUFACTURI | Negros Island Region | Siquijor DEO | On-Going | ₱57.3M | 89% | Medium risk55 | —-0.051 |
| 24 | 18GK0113RECONSTRUCTION FROM PAVED TO CONCRETE - JCT NATL RD SAGAY-BATO-DIAN-MARCELO-BALEA JCT RD - K0084+000-K0085+000, K0084+-807-K0084+-508, K0098+022-K0098+391, K0099+000-K0099+194, K0084+-508-K0084+-375 | Negros Island Region | Negros Occidental 1st DEO | Completed | ₱70.8M | 100% | Medium risk53 | —-0.085 |
| 25 | 18GF0040RECONSTRUCTION FROM PAVED TO CONCRETE - ILOILO - ANTIQUE ROAD, MIAG-AO & SAN JOAQUIN, ILOILO (K0041+747-K0042+279, K0042+330- K0042+548, K0047+942-K0049+941, K0050+020-K0050+803, K0050+834-K0051+000, K0052+879-K0053+276, K0054+725-K0055+195, K0055+383-K00 | Region VI | Iloilo 1st DEO | Completed | ₱84.2M | 100% | Medium risk52 | —-0.072 |