Contractor dossier
298 projects on file, including joint ventures this contractor is part of.
Total projects
298
Total budget
₱17.3B
Average progress
92.6%
Completion rate
80.5%
Average risk score
54.4
Medium risk on average, out of 100
Flagged as unusual
11
3.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 124 | ₱7.3B | 52.4 | 6 | 92.9% |
| Region IV-A | 121 | ₱6.8B | 56.2 | 2 | 95.4% |
| National Capital Region | 49 | ₱2.7B | 53.5 | 1 | 88.1% |
| Central Office | 3 | ₱422.5M | 73.4 | 1 | 66.7% |
| Region II | 1 | ₱71.3M | 70.1 | 1 | 2.5% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 187 | ₱11.2B | 53.0 | 6 | 95.9% |
| Roads | 67 | ₱3.8B | 55.3 | 2 | 84.7% |
| Buildings and Facilities | 20 | ₱949.1M | 51.1 | 0 | 93.7% |
| OTHER | 16 | ₱1B | 70.0 | 3 | 89.8% |
| Bridges | 5 | ₱159.5M | 47.4 | 0 | 80.0% |
| GAA 2025 OO-2 | 1 | ₱93.6M | 93.1 | 0 | 91.2% |
| GAA 2025 OO-1 | 1 | ₱30.7M | 89.3 | 0 | 69.7% |
| Water Provision and Storage | 1 | ₱9.6M | 36.7 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CD0197CONSTRUCTION OF VALENZUELA - OBANDO - MEYCAUAYAN (VOM) FLOOD CONTROL STRUCTURE ALONG MEYCAUAYAN RIVER, STA. 5+750 - STA. 6+100, BARANGAY SALUYSOY, MEYCAUAYAN CITY, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱93.6M | 91% | High risk93 | —-0.017 |
| 25OH0066ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION- RECONSTRUCTION- UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS-PRES. DIOSDADO MACAPAGAL BLVD. - (S04019LZ) CHAINAGE 000 - CHAINAGE 278 | National Capital Region | South Manila DEO | On-Going | ₱30.7M | 70% | High risk89 | —-0.011 |
| 24CC0027CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG BOCAUE RIVER, BARANGAY BAMBANG, BOCAUE, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱96.5M | 100% | High risk79 | —-0.051 |
| 24CC0026CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG BOCAUE RIVER (PHASE II), BARANGAY BAMBANG, BOCAUE, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱96.5M | 100% | High risk79 | —-0.051 |
| 25CD0223CONCRETING OF BRGY. STO. CRISTO FMR, BRGY. STO. CRISTO, SAN JOSE DEL MONTE, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱28.9M | 0% | High risk79 | Flagged0.060 |
| 25DF0117ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS FLOOD MANAGEMENT PROG CONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS & PRINCIPAL RIVERS CONST OF REVETMENT ALONG ILANG-ILANG RIVER BRGY. SAN FRANCISCO, GEN. | Region IV-A | Cavite 1st DEO | On-Going | ₱93.6M | 45% | High risk79 | —-0.008 |
| 24CD0251CONSTRUCTION OF MULTI - PURPOSE BUILDING (GAD BUILDING), BARANGAY POBLACION, SAN JOSE DEL MONTE, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱96M | 100% | High risk79 | —-0.030 |
| 24CC0659CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BALAGTAS RIVER, BARANGAY MALIBONG BATA (PUROK 3), PANDI, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱74.1M | 7% | High risk78 | Flagged0.048 |
| 23CC0564CONSTRUCTION OF REVETMENT AND REHABILITATION OF WATERWAYS AT BRGY. TIKAY, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱72.4M | 86% | High risk77 | Flagged0.033 |
| 24CC0663CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG HALANG RIVER AT PARONG PARONG, BARANGAY SAN PEDRO, HAGONOY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱69.4M | 92% | High risk77 | Flagged0.026 |
| 23CC0517CONSTRUCTION OF REVETMENT AND REHABILITATION OF WATERWAYS AT BRGY. NAMAYAN, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱72.4M | 73% | High risk77 | Flagged0.035 |
| 21O00087CONSTRUCTION OF REVETMENT ALONG MARIBLO CREEK, STA. 0+010.000 TO STA. 0+524.458 (LEFT AND RIGHT RIVER BANK), QUEZON CITY | Central Office | Flood Control Management Cluster | Completed | ₱195M | 100% | High risk76 | —-0.025 |
| 25CD0048CONSTRUCTION OF MUZON - GAYA-GAYA BY-PASS ROAD, PHASE VI, CITY OF SAN JOSE DEL MONTE, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱93.6M | 0% | High risk76 | —-0.008 |
| 24CD0151CONSTRUCTION OF BYPASS (ALTERNATE) ROAD, BARANGAY GAYA-GAYA (PHASE IV), SAN JOSE DEL MONTE CITY, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱95M | 100% | High risk76 | —-0.056 |
| 25CC0051CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE AT BARANGAY DAUNGAN (PUROK 2), GUIGUINTO, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱78.7M | 78% | High risk76 | —-0.022 |
| 24CC0191CONSTRUCTION OF REINFORCED CONCRETE FLOOD CONTROL STRUCTURE, BARANGAY SAN MIGUEL (PUROK 7 TO PUROK 8), HAGONOY, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱77.2M | 100% | High risk76 | —-0.058 |
| 23CC0522CONSTRUCTION OF REVETMENT AND REHABILITATION OF WATERWAYS AT BRGY. SANTO ROSARIO, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱64.8M | 65% | High risk76 | Flagged0.041 |
| 25CC0312CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE AT BARANGAY SAN AGUSTIN (PARONG PARONG), HAGONOY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱69.3M | 92% | High risk76 | —-0.028 |
| 25CC0076CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE AT BARANGAY IBA-IBAYO (PUROK 1 TO PUROK 2), HAGONOY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱69.4M | 90% | High risk76 | —-0.028 |
| 25CC0081CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PAMPANGA RIVER AT BARANGAY SANTA LUCIA (PUROK 5 TO PUROK 6), CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱82M | 89% | High risk76 | —-0.026 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CD0223CONCRETING OF BRGY. STO. CRISTO FMR, BRGY. STO. CRISTO, SAN JOSE DEL MONTE, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱28.9M | 0% | High risk79 | Flagged0.060 |
| 24CC0659CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BALAGTAS RIVER, BARANGAY MALIBONG BATA (PUROK 3), PANDI, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱74.1M | 7% | High risk78 | Flagged0.048 |
| 23CC0522CONSTRUCTION OF REVETMENT AND REHABILITATION OF WATERWAYS AT BRGY. SANTO ROSARIO, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱64.8M | 65% | High risk76 | Flagged0.041 |
| 23CC0517CONSTRUCTION OF REVETMENT AND REHABILITATION OF WATERWAYS AT BRGY. NAMAYAN, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱72.4M | 73% | High risk77 | Flagged0.035 |
| 23CC0564CONSTRUCTION OF REVETMENT AND REHABILITATION OF WATERWAYS AT BRGY. TIKAY, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱72.4M | 86% | High risk77 | Flagged0.033 |
| 24CC0663CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG HALANG RIVER AT PARONG PARONG, BARANGAY SAN PEDRO, HAGONOY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱69.4M | 92% | High risk77 | Flagged0.026 |
| 24DF0303CONVERGENCE AND SPECIAL SUPPORT PROGRAMSPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239INSTALLATION OF ROADWAY LIGHTING STRUCTURES ALONG TANZA-TMC-INDANG ROAD, TANZA, CAVITE | Region IV-A | Cavite 1st DEO | On-Going | ₱47.8M | 100% | High risk69 | Flagged0.015 |
| 21O00088CONSTRUCTION OF REVETMENT ALONG DARIO CREEK, STA. 0+020.000 TO STA. 0+351.894 (LEFT AND RIGHT RIVER BANK), QUEZON CITY | Central Office | Flood Control Management Cluster | On-Going | ₱135.7M | 0% | High risk75 | Flagged0.015 |
| 24DF0024ORG OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS FLOOD MANAGEMENT PROGRAM CONST/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMSCONST OF REVETMENT ALONG ILANG-ILANG RIVER, BUENAVISTA, PHASE IV, GEN TRIAS,CAVITE | Region IV-A | Cavite 1st DEO | On-Going | ₱86.9M | 69% | High risk71 | Flagged0.009 |
| 24OH0055ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM-OFF-CARRIAGEWAY IMPROVEMENT-PRIMARY ROADS-CONSTRUCTION OF LOADING AND UNLOADING BAY AT ROXAS BOULEVARD CORNER EDSA, PASAY CITY PHASE II | National Capital Region | South Manila DEO | On-Going | ₱94.5M | 82% | High risk68 | Flagged0.006 |
| 25BH0242SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - REHABILITATION OF ROAD, SAN ISIDRO - ECHAGUE ROAD, SAN ISIDRO AND ECHAGUE, ISABE | Region II | Isabela 4th DEO | On-Going | ₱71.3M | 3% | High risk70 | Flagged0.002 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 126 | 24CC0028CONSTRUCTION OF RIVER PROTECTION STRUCTURE ALONG BOCAUE RIVER, BARANGAY TURO, BOCAUE, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱96.5M | 100% | Medium risk55 | —-0.080 |
| 127 | 21OE0123CONSTRUCTION OF NORTH MANILA DISTRICT ENGINEERING OFFICE (PERMANENT OFFICE), MANILA CITY, PHASE II | National Capital Region | North Manila DEO | Completed | ₱48.2M | 100% | Medium risk55 | —-0.098 |
| 128 | 22DF0033ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGRAMCONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMSCONSTRUCTION OF ROAD DIKE ALONG JULIAN RIVER, BRGY, MALAGASANG II-A, EAST | Region IV-A | Cavite 1st DEO | Completed | ₱90.7M | 100% | Medium risk55 | —-0.079 |
| 129 | 22DF0008ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGRAMCONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERSCONSTRUCTION OF REVETMENT ALONG ILANG-ILANG R | Region IV-A | Cavite 1st DEO | Completed | ₱90.7M | 100% | Medium risk55 | —-0.078 |
| 130 | 23OE0150CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY 599, ZONE 59, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱49M | 100% | Medium risk55 | —-0.086 |
| 131 | 22DF0061ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGRAMCONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMSCONSTRUCTION OF REVETMENT ALONG MANILA BAY, BRGY. WAWA 1, ROSARIO, CAVITE | Region IV-A | Cavite 1st DEO | Completed | ₱89.7M | 100% | Medium risk54 | —-0.074 |
| 132 | 22DF0065ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGRAMCONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMSCONSTRUCTION OF REVETMENT ALONG MANILA BAY, BRGY. SAN SALCEDO, NOVELETA, C | Region IV-A | Cavite 1st DEO | Completed | ₱89.7M | 100% | Medium risk54 | —-0.076 |
| 133 | 21DF0216LOCAL PROGRAM, CONST./ REPAIR./ REHAB./ IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS,LOCAL ROADS AND BRIDGES LOCAL ROADS WIDENING OF DON PLACIDO CAMPOS AVE., BRGY. MALAGASANG, IMUS, CAVITE | Region IV-A | Cavite 1st DEO | Completed | ₱86.9M | 100% | Medium risk54 | —-0.098 |
| 134 | 18DF0085ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM,ASSET PRESERVATION PROGRAM, CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONGNATIONAL ROADS, SECONDARY ROADS, CAVITE-BATANGAS ROAD - K0021+000 - K0023+200,K0025+709 - K002 | Region IV-A | Cavite 1st DEO | Completed | ₱71.6M | 100% | Medium risk54 | —-0.101 |
| 135 | 22DF0075ORGANIZATIONAL OUTCOME 1: ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM ROAD WIDENING- TERTIARY ROAD LABANAN SA BINAKAYAN DIV. RD. K0021+674 - K0023+426 | Region IV-A | Cavite 1st DEO | On-Going | ₱65.8M | 47% | Medium risk54 | —-0.027 |
| 136 | 20DF0177LOCAL PROGRAM - LOCAL INFRASTRUCTURE PROGRAM, LOCAL ROADS AND BRIDGES, LOCAL ROADS - CONCRETING OF ROADS WITH DRAINAGE, BINAKAYAN INTERCHANGE CONNECTING CAVITEX AND COVELANDIA ROAD WITH RROW ACQUISITION, PHASE 2, KAWIT, CAVITE | Region IV-A | Cavite 1st DEO | Completed | ₱79.2M | 100% | Medium risk54 | —-0.098 |
| 137 | 20DF0176LOCAL PROGRAM - LOCAL INFRASTRUCTURE PROGRAM, LOCAL ROADS AND BRIDGES, LOCAL ROADS - CONCRETING OF ROADS WITH DRAINAGE, BINAKAYAN INTERCHANGE CONNECTING CAVITEX AND COVELANDIA ROAD WITH RROW ACQUISITION, PHASE 1, KAWIT, CAVITE | Region IV-A | Cavite 1st DEO | Completed | ₱79.2M | 100% | Medium risk54 | —-0.099 |
| 138 | 25DF0034ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMASSET PRESERVATION PROGRAMREHAB/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADSKAWIT-NOVELETA DIV RD. - K0023 + 750 - K0024 + 280, K0024 + 290 - K0024+495 | Region IV-A | Cavite 1st DEO | On-Going | ₱81.2M | 100% | Medium risk54 | —-0.073 |
| 139 | 22DF0127CONVERGENCE AND SPECIAL SUPPORT PROGRAMSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIESCONSTRUCTION OF PASONG CAMACHILE II (OPEN C | Region IV-A | Cavite 1st DEO | Completed | ₱72.4M | 100% | Medium risk54 | —-0.097 |
| 140 | 22DF0180ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMNETWORK DEVELOPMENT PROGRAMCONSTRUCTION OF BY-PASS AND DIVERSION ROADSMALABON GRANDE- SAN JUAN - MULAWIN DIVERSION ROAD, LAVANYA SECTION, SEGMENT IV, GEN TRIAS, CAVITE | Region IV-A | Cavite 1st DEO | Completed | ₱58.9M | 100% | Medium risk54 | —-0.102 |
| 141 | 23CD0193REHABILITATION OF FLOOD CONTROL ALONG MARILAO AND MEYCAUAYAN RIVER, BRGY. SALUYSOY, CITY OF MEYCAUAYAN, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱48.2M | 100% | Medium risk53 | —-0.031 |
| 142 | 23OI0020CONSTRUCTION OF FLOOD CONTROL STRUCTURE, TUKLAS RIVER, BARANGAY CUPANG, MUNTINLUPA CITY | National Capital Region | Las Piñas-Muntinlupa DEO | Completed | ₱81.9M | 100% | Medium risk53 | —-0.081 |
| 143 | 22OE0034CONSTRUCTION OF RCBC ALONG PUREZA STREET, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱64.6M | 100% | Medium risk53 | —-0.081 |
| 144 | 22OH0023ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM-DRAINAGE IMPROVEMENT ALONG REMEDIOS ST FROM M.H, DEL PILAR ST TO REMEDIOS CIRC | National Capital Region | South Manila DEO | Completed | ₱77.1M | 100% | Medium risk53 | —-0.084 |
| 145 | 22OH0019ORGANIZATIONAL OUTCOME 2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM-DRAINAGE IMPROVEMENT ALONG REMEDIOS ST. FROM REMEDIOS CIRCLE TO SINGALONG ST. M | National Capital Region | South Manila DEO | Completed | ₱77.2M | 100% | Medium risk53 | —-0.085 |
| 146 | 22OH0016ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM-IMPROVEMENT/REHABILITATION/REPLACEMENT OF DAMAGED LIBERTAD DRAINAGE MAIN (BOX | National Capital Region | South Manila DEO | Completed | ₱64.5M | 100% | Medium risk53 | —-0.086 |
| 147 | 18OH0063CONSTRUCTION OF SLOPE PROTECTION STRUCTURES-VILLAMOR GOLF COURSE,PASAY CITY | National Capital Region | South Manila DEO | Completed | ₱65.2M | 100% | Medium risk53 | —-0.084 |
| 148 | 19OH0013ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-CONST. OF SLOPE PROTECTI | National Capital Region | South Manila DEO | Completed | ₱77.2M | 100% | Medium risk53 | —-0.084 |
| 149 | 19OH0014ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-CONST. OF SLOPE PROTECTI | National Capital Region | South Manila DEO | Completed | ₱61.5M | 100% | Medium risk53 | —-0.086 |
| 150 | 21CD0127CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG MARILAO RIVER AND ITS TRIBUTARIES (POBLACION SEC.) LEFT SIDE, STA. 006+763 STA. 007+463, MARILAO, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱92.6M | 100% | Medium risk53 | —-0.079 |