Opening the dossier…
Opening the dossier…
Contractor dossier
6 projects on file, including joint ventures this contractor is part of.
Total projects
6
Total budget
₱140.2M
Average progress
97.1%
Completion rate
50.0%
Below 70%
Average risk score
26.7
Low risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XII | 6 | ₱140.2M | 26.7 | 0 | 97.1% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 6 | ₱140.2M | 26.7 | 0 | 97.1% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Nothing to report.
No high-risk projects here.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 24M00118ROAD WIDENING - MARBEL-MAKAR RD - K1661+(-551) - K1661+348, K1663+825 - K1665+492, K1666+120 - K1666+700, POLOMOLOK, SOUTH COTABATO | Region XII | Region XII | On-Going | ₱51.9M | 100% | Medium risk31 | —-0.050 |
| 2 | 25MG0023CONSTRUCTION OF CONCRETE ROAD, JCT. NATIONAL HIGHWAY, SURALLAH-LAKE SEBU-MAITUM ROAD, SITIO KULUSTOLI, BARANGAY LAMFUGON, LAKE SEBU, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱19.6M | 100% | Low risk26 | —-0.089 |
| 3 | 25M00020REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - MAHARLIKA HIGHWAY (MARBEL-MAKAR RD) - K1666 + 481 - K1667 + 698, POLOMOLOK, SOUTH COTABATO | Region XII | Region XII | On-Going | ₱19.5M | 100% | Low risk26 | —-0.058 |
| 4 | 24MB0067CONCRETING OF BARANGAY POBLACION TO DOLE AGRI AREA BARANGAY CANNERY ROAD, POLOMOLOK, SOUTH COTABATO | Region XII | South Cotabato 1st DEO | Completed | ₱9.9M | 100% | Low risk26 | —-0.087 |
| 5 | 23MB0014CONST./IMP. OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL- IT) - UPPER KLINAN JUNCTION TO POLO ROAD LEADING TO PROCESSING CENTERS, POLOMOLOK, SOUTH COTABATO | Region XII | South Cotabato 1st DEO | Completed | ₱24.5M | 100% | Low risk26 | —-0.087 |
| 6 | 25MB0057CONSTRUCTION OF ROAD FROM PUROK 2, BARANGAY RUBBER TO BARANGAY LUMAKIL, POLOMOLOK, SOUTH COTABATO | Region XII | South Cotabato 1st DEO | On-Going | ₱14.8M | 83% | Low risk26 | —-0.050 |