Contractor dossier
54 projects on file, including joint ventures this contractor is part of.
Total projects
54
Total budget
₱6B
Average progress
68.8%
Completion rate
35.2%
Below 70%
Average risk score
65.9
High risk on average, out of 100
Flagged as unusual
10
18.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 18 | ₱1.9B | 65.1 | 2 | 61.8% |
| Region I | 12 | ₱1.4B | 59.6 | 1 | 89.8% |
| Region IV-B | 10 | ₱807.3M | 76.4 | 2 | 84.1% |
| Region II | 8 | ₱569.4M | 67.3 | 4 | 10.4% |
| Cordillera Administrative Region | 6 | ₱1.3B | 61.9 | 1 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 30 | ₱3.4B | 58.4 | 1 | 58.6% |
| Flood Control and Drainage | 11 | ₱1B | 65.6 | 3 | 70.8% |
| GAA 2025 OO-1 | 5 | ₱419.8M | 85.5 | 1 | 96.3% |
| GAA 2025 SSP | 4 | ₱426.7M | 95.7 | 4 | 85.4% |
| Bridges | 2 | ₱330M | 65.0 | 1 | 100.0% |
| GAA 2025 OO-2 | 1 | ₱28.6M | 86.2 | 0 | 52.5% |
| Buildings and Facilities | 1 | ₱289.5M | 60.1 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25BH0279CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR STREETLIGHTS ALONG JCT. IPIL-QUIRINO BRDY. RD., BARANGAY IPIL TO BARANGAY VILLA VICTORIA, SECTION 1, ECHAGUE, ISABELA | Region II | Isabela 4th DEO | On-Going | ₱93.6M | 61% | High risk96 | Flagged0.029 |
| 25DK0074CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR STREETLIGHTS ALONG LUCENA-TAYABAS-LUCBAN-SAMPALOC-MAUBAN PORT RD K0129 + (-302) - K0140 + 000 | Region IV-A | Quezon 1st DEO | On-Going | ₱143M | 100% | High risk96 | Flagged0.008 |
| 25DM0123INSTALLATION OF SOLAR STREET LIGHTS ALONG MULANAY - SN FRANCISCO RD - K0295 + 509 - K0302 + 000 | Region IV-A | Quezon 3rd DEO | On-Going | ₱93.6M | 97% | High risk96 | Flagged0.002 |
| 25ED0147REHABILITATION OF ROAD, BARANGAY STA. ISABEL - BARANGAY TAWAGAN, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱96.5M | 84% | High risk95 | Flagged0.019 |
| 25ED0126PREVENTIVE MAINTENANCE ALONG CALAPAN SOUTH ROAD K0052+246 - K0053+511, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱57.9M | 97% | High risk92 | —-0.004 |
| 25ED0125PREVENTIVE MAINTENANCE ALONG CALAPAN SOUTH ROAD K0050+765 - K0052+246, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱86.8M | 85% | High risk92 | Flagged0.003 |
| 25ED0018CONSTRUCTION OF SEAWALL STRUCTURE, BARANGAY PACHOCA, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱28.6M | 52% | High risk86 | —-0.005 |
| 25ED0122PREVENTIVE MAINTENANCE ALONG CALAPAN SOUTH RD (S00007MR) - K0044+575- K0045+198, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱96.5M | 100% | High risk82 | —-0.018 |
| 25ED0127PREVENTIVE MAINTENANCE ALONG CALAPAN SOUTH ROAD K0061+129 - K0062+000, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱72.4M | 100% | High risk82 | —-0.024 |
| 25ED0123PREVENTIVE MAINTENANCE ALONG CALAPAN SOUTH ROAD - K0062+000 -K0063+015, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱106.1M | 100% | High risk80 | —-0.016 |
| 25BH0260BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDING/ FACILITIES - CONSTRUCTION OF GUAYABAL FLOOD CONTROL STRUCTURE STA. 0+000 - STA. 0+200, CAUAYAN CITY, ISABELA | Region II | Isabela 4th DEO | On-Going | ₱96M | 0% | High risk80 | Flagged0.017 |
| 25BH0261BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS / FACILITIES - CONSTRUCTION OF GUAYABAL FLOOD CONTROL STRUCTURE STA. 0+200 - STA. 0+400, CAUAYAN CITY, ISABELA | Region II | Isabela 4th DEO | On-Going | ₱96M | 1% | High risk79 | Flagged0.016 |
| 25AF0108CONST/REHAB OF FLOOD MIT. FACI W/IN MAJOR RIVER BASINS & PRINCIPAL RIVERS - CONST. OF FLOOD MIT. STRUCTURE ALONG ARINGAY RIVER BASIN, BRGY. SAN SIMON WEST, ARINGAY, LU (PHASE 4) | Region I | La Union 2nd DEO | On-Going | ₱93.6M | 61% | High risk77 | Flagged0.008 |
| 25DK0082CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR STREETLIGHTS ALONG TAYABAS-MAINIT-MAUBAN ROAD, K0152+000-K0163+000 | Region IV-A | Quezon 1st DEO | On-Going | ₱145.2M | 52% | High risk72 | —-0.017 |
| 25BH0281CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR STREETLIGHTS, BARANGAY STA. LUCIANA - BARANGAY AMOBOCAN, CAUAYAN CITY, ISABELA | Region II | Isabela 4th DEO | On-Going | ₱93.6M | 2% | High risk72 | Flagged0.007 |
| 25BH0273CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR STREETLIGHTS, BARANGAY NUNGNUGAN II - BARANGAY SAN FRANCISCO, CAUAYAN CITY, ISABELA | Region II | Isabela 4th DEO | On-Going | ₱47.5M | 6% | High risk68 | —-0.002 |
| 23P00051CONSTRUCTION (COMPLETION) OF SALNEC-MADALIPAY-DUGONG BRIDGE, SALNEC AND DUGONG, BUCAY, ABRA | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱159.2M | 100% | High risk67 | Flagged0.006 |
| 25DI0105INSTALLATION OF SOLAR STREETLIGHTS AT BARANGAYS BALIBAGO AND DILA, SANTA ROSA CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱142M | 27% | High risk66 | —-0.034 |
| 25DI0106INSTALLATION OF SOLAR STREETLIGHTS AT BARANGAYS POOC AND CAINGIN, SANTA ROSA CITY, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱142.1M | 30% | High risk66 | —-0.035 |
| 25DM0124INSTALLATION OF SOLAR STREET LIGHTS ALONG MULANAY - SN FRANCISCO RD - K0302 + 000 - K0308 + 500 | Region IV-A | Quezon 3rd DEO | On-Going | ₱93.6M | 100% | High risk64 | —-0.070 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25BH0279CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR STREETLIGHTS ALONG JCT. IPIL-QUIRINO BRDY. RD., BARANGAY IPIL TO BARANGAY VILLA VICTORIA, SECTION 1, ECHAGUE, ISABELA | Region II | Isabela 4th DEO | On-Going | ₱93.6M | 61% | High risk96 | Flagged0.029 |
| 25ED0147REHABILITATION OF ROAD, BARANGAY STA. ISABEL - BARANGAY TAWAGAN, CALAPAN CITY, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱96.5M | 84% | High risk95 | Flagged0.019 |
| 25BH0260BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDING/ FACILITIES - CONSTRUCTION OF GUAYABAL FLOOD CONTROL STRUCTURE STA. 0+000 - STA. 0+200, CAUAYAN CITY, ISABELA | Region II | Isabela 4th DEO | On-Going | ₱96M | 0% | High risk80 | Flagged0.017 |
| 25BH0261BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS / FACILITIES - CONSTRUCTION OF GUAYABAL FLOOD CONTROL STRUCTURE STA. 0+200 - STA. 0+400, CAUAYAN CITY, ISABELA | Region II | Isabela 4th DEO | On-Going | ₱96M | 1% | High risk79 | Flagged0.016 |
| 25AF0108CONST/REHAB OF FLOOD MIT. FACI W/IN MAJOR RIVER BASINS & PRINCIPAL RIVERS - CONST. OF FLOOD MIT. STRUCTURE ALONG ARINGAY RIVER BASIN, BRGY. SAN SIMON WEST, ARINGAY, LU (PHASE 4) | Region I | La Union 2nd DEO | On-Going | ₱93.6M | 61% | High risk77 | Flagged0.008 |
| 25DK0074CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR STREETLIGHTS ALONG LUCENA-TAYABAS-LUCBAN-SAMPALOC-MAUBAN PORT RD K0129 + (-302) - K0140 + 000 | Region IV-A | Quezon 1st DEO | On-Going | ₱143M | 100% | High risk96 | Flagged0.008 |
| 25BH0281CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR STREETLIGHTS, BARANGAY STA. LUCIANA - BARANGAY AMOBOCAN, CAUAYAN CITY, ISABELA | Region II | Isabela 4th DEO | On-Going | ₱93.6M | 2% | High risk72 | Flagged0.007 |
| 23P00051CONSTRUCTION (COMPLETION) OF SALNEC-MADALIPAY-DUGONG BRIDGE, SALNEC AND DUGONG, BUCAY, ABRA | Cordillera Administrative Region | Cordillera Administrative Region | On-Going | ₱159.2M | 100% | High risk67 | Flagged0.006 |
| 25ED0125PREVENTIVE MAINTENANCE ALONG CALAPAN SOUTH ROAD K0050+765 - K0052+246, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | On-Going | ₱86.8M | 85% | High risk92 | Flagged0.003 |
| 25DM0123INSTALLATION OF SOLAR STREET LIGHTS ALONG MULANAY - SN FRANCISCO RD - K0295 + 509 - K0302 + 000 | Region IV-A | Quezon 3rd DEO | On-Going | ₱93.6M | 97% | High risk96 | Flagged0.002 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 25BH0269CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR STREETLIGHTS, BARANGAY SAN FERMIN TO CAUAYAN - CABATUAN BYPASS ROAD, CAUAYAN CITY, ISABELA | Region II | Isabela 4th DEO | On-Going | ₱47.5M | 4% | Medium risk48 | —-0.026 |
| 52 | 25BH0280CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR STREETLIGHTS IN BARANGAY GOMEZ - BARANGAY VILLAFLOR - BARANGAY NAGBUKEL, SAN ISIDRO, ISABELA | Region II | Isabela 4th DEO | On-Going | ₱47.5M | 6% | Medium risk48 | —-0.027 |
| 53 | 25BH0272CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR STREETLIGHTS IN BARANGAY QUEZON TO BARANGAY RIZAL WEST, SAN ISIDRO, ISABELA | Region II | Isabela 4th DEO | On-Going | ₱47.5M | 3% | Medium risk48 | —-0.027 |
| 54 | 25ED0124PREVENTIVE MAINTENANCE ALONG CALAPAN SOUTH ROAD K0042+198 - K0042+908, ORIENTAL MINDORO | Region IV-B | Mindoro Oriental DEO | Completed | ₱72.4M | 100% | Medium risk47 | —-0.087 |