Contractor dossier
85 projects on file, including joint ventures this contractor is part of.
Total projects
85
Total budget
₱709.9M
Average progress
95.0%
Completion rate
78.8%
Average risk score
39.4
Medium risk on average, out of 100
Flagged as unusual
2
2.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 85 | ₱709.9M | 39.4 | 2 | 95.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 41 | ₱262.9M | 39.9 | 0 | 95.6% |
| Roads | 31 | ₱334.7M | 33.8 | 0 | 100.0% |
| Water Provision and Storage | 5 | ₱29.4M | 40.3 | 0 | 82.3% |
| Flood Control and Drainage | 4 | ₱63.4M | 34.6 | 0 | 87.5% |
| GAA 2025 SSP | 2 | ₱9.7M | 93.4 | 2 | 46.5% |
| OTHER | 2 | ₱9.9M | 67.6 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CN0132CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 5, BALER, AURORA | Region III | Aurora DEO | On-Going | ₱4.9M | 42% | High risk94 | Flagged0.011 |
| 25CN0154CONSTRUCTION OF MULTI-PURPOSE BUILDING, POBLACION 2, SAN LUIS, AURORA | Region III | Aurora DEO | On-Going | ₱4.8M | 51% | High risk93 | Flagged0.009 |
| 25CN0148CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY OBLIGACION, BALER, AURORA | Region III | Aurora DEO | On-Going | ₱4.8M | 0% | High risk72 | —-0.011 |
| 25CN0061CONSTRUCTION OF MULTI-PURPOSE BUILDING (DAY CARE CENTER), BARANGAY 2, MARIA AURORA, AURORA | Region III | Aurora DEO | On-Going | ₱4.8M | 69% | High risk72 | —-0.031 |
| 25CN0115CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY 4, MARIA AURORA, AURORA | Region III | Aurora DEO | On-Going | ₱4.8M | 83% | High risk72 | —-0.039 |
| 24CN0104REHABILITATION OF MULTI-PURPOSE FACILITY (MUNICIPAL TRANSPORT TERMINAL), POBLACION ZONE II, DINALUNGAN, AURORA | Region III | Aurora DEO | On-Going | ₱43.6M | 100% | High risk72 | —-0.036 |
| 25CN0056CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), LEON DIAZ ELEMENTARY SCHOOL, BARANGAY SAN JOAQUIN, MARIA AURORA, AURORA | Region III | Aurora DEO | On-Going | ₱6.9M | 98% | High risk71 | —-0.044 |
| 25CN0119CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) BARANGAY DECOLIAT, MARIA AURORA, AURORA | Region III | Aurora DEO | On-Going | ₱6.9M | 90% | High risk70 | —-0.041 |
| 25CN0128CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), GALINTUJA ELEMENTARY SCHOOL, BARANGAY GALINTUJA, MARIA AURORA, AURORA | Region III | Aurora DEO | On-Going | ₱6.9M | 94% | High risk70 | —-0.041 |
| 25CN0051CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), DIKILDIT ELEMENTARY SCHOOL, BARANGAY DIKILDIT, MARIA AURORA, AURORA | Region III | Aurora DEO | On-Going | ₱6.9M | 98% | High risk70 | —-0.045 |
| 25CN0048CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), CALABUANAN ELEMENTARY SCHOOL, BARANGAY CALABUANAN, BALER, AURORA | Region III | Aurora DEO | On-Going | ₱6.8M | 92% | High risk70 | —-0.042 |
| 24CN0164CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. DAVILDAVILAN, DINGALAN, AURORA | Region III | Aurora DEO | Completed | ₱5M | 100% | High risk70 | —-0.074 |
| 17CN0033CONCRETING OF ROAD, BRGY. IPIL, DIPACULAO, AURORA | Region III | Aurora DEO | Completed | ₱5M | 100% | High risk68 | —-0.039 |
| 17CN0003CONCRETING OF ROAD, BRGY. SUKLAYIN, BALER, AURORA | Region III | Aurora DEO | Completed | ₱5M | 100% | High risk67 | —-0.040 |
| 17CN0096CONCRETING OF ROAD FROM BRGY. BUENAVISTA ROAD TO BRGY. SAPANGKAWAYAN ROAD, DIPACULAO, AURORA | Region III | Aurora DEO | Completed | ₱5M | 100% | High risk65 | —-0.068 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CN0132CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 5, BALER, AURORA | Region III | Aurora DEO | On-Going | ₱4.9M | 42% | High risk94 | Flagged0.011 |
| 25CN0154CONSTRUCTION OF MULTI-PURPOSE BUILDING, POBLACION 2, SAN LUIS, AURORA | Region III | Aurora DEO | On-Going | ₱4.8M | 51% | High risk93 | Flagged0.009 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25CN0132CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 5, BALER, AURORA | Region III | Aurora DEO | On-Going | ₱4.9M | 42% | High risk94 | Flagged0.011 |
| 2 | 25CN0154CONSTRUCTION OF MULTI-PURPOSE BUILDING, POBLACION 2, SAN LUIS, AURORA | Region III | Aurora DEO | On-Going | ₱4.8M | 51% | High risk93 | Flagged0.009 |
| 3 | 25CN0148CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY OBLIGACION, BALER, AURORA | Region III | Aurora DEO | On-Going | ₱4.8M | 0% | High risk72 | —-0.011 |
| 4 | 25CN0061CONSTRUCTION OF MULTI-PURPOSE BUILDING (DAY CARE CENTER), BARANGAY 2, MARIA AURORA, AURORA | Region III | Aurora DEO | On-Going | ₱4.8M | 69% | High risk72 | —-0.031 |
| 5 | 25CN0115CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY 4, MARIA AURORA, AURORA | Region III | Aurora DEO | On-Going | ₱4.8M | 83% | High risk72 | —-0.039 |
| 6 | 24CN0104REHABILITATION OF MULTI-PURPOSE FACILITY (MUNICIPAL TRANSPORT TERMINAL), POBLACION ZONE II, DINALUNGAN, AURORA | Region III | Aurora DEO | On-Going | ₱43.6M | 100% | High risk72 | —-0.036 |
| 7 | 25CN0056CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), LEON DIAZ ELEMENTARY SCHOOL, BARANGAY SAN JOAQUIN, MARIA AURORA, AURORA | Region III | Aurora DEO | On-Going | ₱6.9M | 98% | High risk71 | —-0.044 |
| 8 | 25CN0119CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) BARANGAY DECOLIAT, MARIA AURORA, AURORA | Region III | Aurora DEO | On-Going | ₱6.9M | 90% | High risk70 | —-0.041 |
| 9 | 25CN0128CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), GALINTUJA ELEMENTARY SCHOOL, BARANGAY GALINTUJA, MARIA AURORA, AURORA | Region III | Aurora DEO | On-Going | ₱6.9M | 94% | High risk70 | —-0.041 |
| 10 | 25CN0051CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), DIKILDIT ELEMENTARY SCHOOL, BARANGAY DIKILDIT, MARIA AURORA, AURORA | Region III | Aurora DEO | On-Going | ₱6.9M | 98% | High risk70 | —-0.045 |
| 11 | 25CN0048CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), CALABUANAN ELEMENTARY SCHOOL, BARANGAY CALABUANAN, BALER, AURORA | Region III | Aurora DEO | On-Going | ₱6.8M | 92% | High risk70 | —-0.042 |
| 12 | 24CN0164CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. DAVILDAVILAN, DINGALAN, AURORA | Region III | Aurora DEO | Completed | ₱5M | 100% | High risk70 | —-0.074 |
| 13 | 17CN0033CONCRETING OF ROAD, BRGY. IPIL, DIPACULAO, AURORA | Region III | Aurora DEO | Completed | ₱5M | 100% | High risk68 | —-0.039 |
| 14 | 17CN0003CONCRETING OF ROAD, BRGY. SUKLAYIN, BALER, AURORA | Region III | Aurora DEO | Completed | ₱5M | 100% | High risk67 | —-0.040 |
| 15 | 17CN0096CONCRETING OF ROAD FROM BRGY. BUENAVISTA ROAD TO BRGY. SAPANGKAWAYAN ROAD, DIPACULAO, AURORA | Region III | Aurora DEO | Completed | ₱5M | 100% | High risk65 | —-0.068 |
| 16 | 23CN0207CONSTRUCTION OF MULTI-PURPOSE BUILDING (SENIOR CITIZEN BUILDING), BRGY. BANCO, MARIA AURORA, AURORA | Region III | Aurora DEO | Completed | ₱4.8M | 100% | Medium risk44 | —-0.026 |
| 17 | 25CN0066CONSTRUCTION OF WATER SYSTEM, BARANGAY PUNGLO, MARIA AURORA, AURORA | Region III | Aurora DEO | On-Going | ₱4.8M | 84% | Medium risk42 | —-0.037 |
| 18 | 24CN0184CONSTRUCTION OF WATER SYSTEM, MALASIN, MARIA AURORA, AURORA | Region III | Aurora DEO | On-Going | ₱5M | 98% | Medium risk41 | —-0.032 |
| 19 | 25CN0067CONSTRUCTION OF WATER SYSTEM, BARANGAY REAL, SAN LUIS, AURORA | Region III | Aurora DEO | On-Going | ₱9.7M | 30% | Medium risk41 | —-0.019 |
| 20 | 18CN0066CONSTRUCTION OF 1 STOREY 4 CL SCHOOL BUILDING, FLORIDA ELEMENTARY SCHOOL, BRGY. FLORIDA, MARIA AURORA, AURORA PROVINCE | Region III | Aurora DEO | Completed | ₱4.9M | 100% | Medium risk39 | —-0.102 |
| 21 | 20CN0119IMPROVEMENT OF WATER SYSTEM, BRGY. HACIENDA 1 & 2, BRGY. NONONG SR., SAN LUIS, AURORA | Region III | Aurora DEO | Completed | ₱5M | 100% | Medium risk39 | —-0.067 |
| 22 | 23CN0058CONSTRUCTION OF WATER SYSTEM, MATAWE, DINGALAN, AURORA | Region III | Aurora DEO | Completed | ₱5M | 100% | Medium risk39 | —-0.068 |
| 23 | 21CN0050CONSTRUCTION OF MULTI-PURPOSE HALL, BRGY. 05, BALER, AURORA | Region III | Aurora DEO | Completed | ₱4.8M | 100% | Medium risk39 | —-0.095 |
| 24 | 24CN0107CONSTRUCTION OF MULTI-PURPOSE BUILDING (COMELEC), DIPACULAO, AURORA | Region III | Aurora DEO | Completed | ₱9.7M | 100% | Medium risk39 | —-0.101 |
| 25 | 20CN0094CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. LABOY, DIPACULAO, AURORA | Region III | Aurora DEO | Completed | ₱5.4M | 100% | Medium risk38 | —-0.102 |