Contractor dossier
6 projects on file, including joint ventures this contractor is part of.
Total projects
6
Total budget
₱489.4M
Average progress
73.0%
Completion rate
50.0%
Below 70%
Average risk score
68.9
High risk on average, out of 100
Flagged as unusual
1
16.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 6 | ₱489.4M | 68.9 | 1 | 73.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 4 | ₱344.5M | 66.1 | 0 | 73.7% |
| GAA 2025 SSP | 1 | ₱48.4M | 94.5 | 1 | 43.6% |
| Buildings and Facilities | 1 | ₱96.5M | 54.6 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CB0108CONSTRUCTION OF MULTI-PURPOSE FACILITY (PHASE II), BARANGAY CABOG CABOG, BALANGA CITY, BATAAN | Region III | Bataan 2nd DEO | On-Going | ₱48.4M | 44% | High risk94 | Flagged0.017 |
| 22CB0091CONSTRUCTION OF ROAD FROM GOVERNOR J.J. LINAO ROAD - WORLD BANK ROAD - PHILIPPINE SPORTS COMMISSION TRAINING CENTER, BALANGA CITY AND BAGAC, BATAAN | Region III | Bataan 2nd DEO | Completed | ₱51.5M | 100% | High risk73 | —-0.062 |
| 25CO0059BASIC INFRASTRUCTURE PROGRAM (BIP) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF QUINAWAN BARANGAY ROADS WITH DRAINAGE AT BARANGAT QUINAWAN, BAGAC, BATAAN | Region III | Bataan 3rd DEO | On-Going | ₱9.7M | 87% | High risk70 | —-0.035 |
| 25C00511CONVERGENCE & SPL. SUPPORT PROG.-SUSTAINABLE INFRA PROJS. ALLEVIATING GAPS (SIPAG)-ACCESS RDS. &/OR BRS. FR. THE NAT'L. RDS. LEAD. TO MAJ./STRAT. PUBLIC BLDGS/FACILITIES-ACCESS RD. CONNECTING GOV. JJ LINAO RD. TO BAGAC-MARIVELES RD. IN SUPPORT TO FREEPORT | Region III | Region III | On-Going | ₱189.3M | 7% | High risk62 | —-0.018 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CB0108CONSTRUCTION OF MULTI-PURPOSE FACILITY (PHASE II), BARANGAY CABOG CABOG, BALANGA CITY, BATAAN | Region III | Bataan 2nd DEO | On-Going | ₱48.4M | 44% | High risk94 | Flagged0.017 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25CB0108CONSTRUCTION OF MULTI-PURPOSE FACILITY (PHASE II), BARANGAY CABOG CABOG, BALANGA CITY, BATAAN | Region III | Bataan 2nd DEO | On-Going | ₱48.4M | 44% | High risk94 | Flagged0.017 |
| 2 | 22CB0091CONSTRUCTION OF ROAD FROM GOVERNOR J.J. LINAO ROAD - WORLD BANK ROAD - PHILIPPINE SPORTS COMMISSION TRAINING CENTER, BALANGA CITY AND BAGAC, BATAAN | Region III | Bataan 2nd DEO | Completed | ₱51.5M | 100% | High risk73 | —-0.062 |
| 3 | 25CO0059BASIC INFRASTRUCTURE PROGRAM (BIP) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF QUINAWAN BARANGAY ROADS WITH DRAINAGE AT BARANGAT QUINAWAN, BAGAC, BATAAN | Region III | Bataan 3rd DEO | On-Going | ₱9.7M | 87% | High risk70 | —-0.035 |
| 4 | 25C00511CONVERGENCE & SPL. SUPPORT PROG.-SUSTAINABLE INFRA PROJS. ALLEVIATING GAPS (SIPAG)-ACCESS RDS. &/OR BRS. FR. THE NAT'L. RDS. LEAD. TO MAJ./STRAT. PUBLIC BLDGS/FACILITIES-ACCESS RD. CONNECTING GOV. JJ LINAO RD. TO BAGAC-MARIVELES RD. IN SUPPORT TO FREEPORT | Region III | Region III | On-Going | ₱189.3M | 7% | High risk62 | —-0.018 |
| 5 | 19CB0081CONSTRUCTION OF ROAD LEADING TO TOURISM PORT AND FACILITIES AT FREEPORT AREA, MARIVELES, BATAAN | Region III | Bataan 2nd DEO | Completed | ₱94.1M | 100% | Medium risk60 | —-0.087 |
| 6 | 20CB0057CONSTRUCTION AND DEVELOPMENT OF FAB PORT, BUILDINGS AND FACILITIES, MARIVELES, BATAAN | Region III | Bataan 2nd DEO | Completed | ₱96.5M | 100% | Medium risk55 | —-0.078 |