Opening the dossier…
Opening the dossier…
Contractor dossier
37 projects on file, including joint ventures this contractor is part of.
Total projects
37
Total budget
₱196.5M
Average progress
97.0%
Completion rate
91.9%
Average risk score
34.5
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VI | 37 | ₱196.5M | 34.5 | 0 | 97.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 17 | ₱119.2M | 35.8 | 0 | 100.0% |
| Buildings and Facilities | 14 | ₱42.9M | 30.5 | 0 | 93.3% |
| Flood Control and Drainage | 3 | ₱16.4M | 36.4 | 0 | 100.0% |
| Bridges | 2 | ₱3.5M | 22.0 | 0 | 100.0% |
| GAA 2025 OO-2 | 1 | ₱14.5M | 88.7 | 0 | 83.8% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25GF0070IMPROVEMENT AND CANAL LINING OF DRAINAGE CANAL, TIGBANABA COMMUNAL IRRIGATION SYSTEM (CIS), IGBARAS, ILOILO | Region VI | Iloilo 1st DEO | On-Going | ₱14.5M | 84% | High risk89 | —-0.009 |
| 25GH0158CONSTRUCTION OF MUNICIPAL HALL BUILDING AT BARANGAY POBLACION SUR, BALASAN, ILOILO | Region VI | Iloilo 3rd DEO | On-Going | ₱4.9M | 52% | High risk69 | —-0.010 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 21GG0043CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - ILOILO - CAPIZ (NEW ROUTE) - K0050 + 195 - K0050 + 285 | Region VI | Iloilo 2nd DEO | Completed | ₱2.5M | 100% | Low risk23 | —-0.086 |
| 27 | 24GG0082CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - PASSI - SN RAFAEL - LEMERY - SARA RD. K0062 + 200 - K0062 + 210 | Region VI | Iloilo 2nd DEO | Completed | ₱2.4M | 100% | Low risk23 | —-0.086 |
| 28 | 22GG0008CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY BALAGIAO, LAMBUNAO, ILOILO | Region VI | Iloilo 2nd DEO | Completed | ₱3M | 100% | Low risk23 | —-0.085 |
| 29 | 19GG0136RENOVATION OF PUBLIC MARKET, BRGY. POBLACION, BANATE, ILOILO | Region VI | Iloilo 2nd DEO | Completed | ₱2.8M | 100% | Low risk22 | —-0.081 |
| 30 | 21GG0144CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING OF BARANGAY MAITE GRANDE, LAMBUNAO, ILOILO | Region VI | Iloilo 2nd DEO | Completed | ₱2M | 100% | Low risk22 | —-0.083 |
| 31 | 21GG0082CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING OF BARANGAY HIPGOS, LAMBUNAO, ILOILO | Region VI | Iloilo 2nd DEO | Completed | ₱2M | 100% | Low risk22 | —-0.084 |
| 32 | 21GG0083CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING OF BARANGAY MADARAG, LAMBUNAO, ILOILO | Region VI | Iloilo 2nd DEO | Completed | ₱2M | 100% | Low risk22 | —-0.084 |
| 33 | 20GG0127CONSTRUCTION OF MULTI - PURPOSE BUILDING, BRGY. YUGOT, MINA, ILOILO | Region VI | Iloilo 2nd DEO | Completed | ₱2.8M | 100% | Low risk21 | —-0.085 |
| 34 | 21GI0061COMPLETION OF HANGING FOOT BRIDGE, BALABAG STA. BARBARA, ILOILO | Region VI | Iloilo 4th DEO | Completed | ₱994.9K | 100% | Low risk19 | —-0.052 |
| 35 | 20GJ0022CONSTRUCTION OF DRAINAGE STRUCTURE - CONSTRUCTION OF DRAINAGE - FRONT OF WVMC HOSPITAL (FROM MC DO MEGAWORLD TO PLAZA) AT Q. ABETO, MANDURRIAO, ILOILO CITY | Region VI | Iloilo City DEO | Completed | ₱1.9M | 100% | Low risk18 | —-0.070 |
| 36 | 22GG0028CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY PASIG, LAMBUNAO, ILOILO | Region VI | Iloilo 2nd DEO | Completed | ₱1.8M | 100% | Low risk14 | —-0.084 |
| 37 | 19GG0138CONSTRUCTION OF COVERED COURT OF BRGY. LU-AG, DUEÑAS, ILOILO | Region VI | Iloilo 2nd DEO | Completed | ₱949.3K | 100% | Low risk13 | —-0.083 |