Contractor dossier
18 projects on file, including joint ventures this contractor is part of.
Total projects
18
Total budget
₱115.4M
Average progress
100.0%
Completion rate
100.0%
Average risk score
33.3
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region V | 18 | ₱115.4M | 33.3 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 10 | ₱88.4M | 37.7 | 0 | 100.0% |
| Roads | 7 | ₱25.1M | 29.1 | 0 | 100.0% |
| Water Provision and Storage | 1 | ₱1.9M | 19.5 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Nothing to report.
No high-risk projects here.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 19FN0183CONSTRUCTION OF THREE (3) STOREY, TWO (2) REGULAR WORKSHOP, TWO (2) SCIENCE LABORATORY, TWO (2) ICT LABORATORY BUILDING (PHASE I), BARCELONITA, CABUSAO, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱51.3M | 100% | Medium risk57 | —-0.041 |
| 2 | 21FD0079WIDENING/CONCRETING/REBLOCKING OF BARANGAY ROAD, FROM ANDAYA HIGHWAY, BANGA CAVES TO UPPER STA. CRUZ, RAGAY, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱9.3M | 100% | Medium risk52 | —-0.101 |
| 3 | 22FD0035CONSTRUCTION OF ROAD, SITIO SAMPALOC, BARANGAY BANGA CAVES, RAGAY, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱6.9M | 100% | Medium risk52 | —-0.098 |
| 4 | 20FD0045CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. CABADISAN, RAGAY, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱4.7M | 100% | Medium risk50 | —-0.097 |
| 5 | 20FD0041CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. BAYA, RAGAY, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱4.8M | 100% | Medium risk50 | —-0.098 |
| 6 | 20FD0049CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. SAGRADA, SIPOCOT, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱4.7M | 100% | Medium risk49 | —-0.099 |
| 7 | 19FN0187CONSTRUCTION OF AUTOMOTIVE AND WELDING BUILDING, RAGAY POLYTECHNIC SKILLS INSTITUTE (RPSI) ANNEX CAMPUS, SITIO CAHUPA, AGRUPACION, RAGAY, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱9.4M | 100% | Medium risk44 | —-0.056 |
| 8 | 21FD0037CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), PINAGDAPIAN, DEL GALLEGO, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱2.9M | 100% | Low risk27 | —-0.097 |
| 9 | 20FD0015CONSTRUCTION OF MULTI-PURPOSE BUILDING, CABUYAO, SIPOCOT, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱2.9M | 100% | Low risk26 | —-0.098 |
| 10 | 21FD0038CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), UPPER OMON, RAGAY, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱2.9M | 100% | Low risk26 | —-0.097 |
| 11 | 21FD0046CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), PHASE I,LA PURISIMA, LUPI, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱2.4M | 100% | Low risk24 | —-0.098 |
| 12 | 21FD0053CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), PHASE I, SALVACION, LUPI, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱2.4M | 100% | Low risk23 | —-0.098 |
| 13 | 21FD0068CONCRETING OF BARANGAY ROAD, LOWER OMON TO UPPER OMON, RAGAY, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱1.9M | 100% | Low risk22 | —-0.096 |
| 14 | 21FD0065CONCRETING OF BARANGAY ROAD, APALE, RAGAY, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱1.5M | 100% | Low risk21 | —-0.094 |
| 15 | 21FD0076CONCRETING/REBLOCKING OF BARANGAY ROAD, BINAHAN PROPER, RAGAY, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱1.8M | 100% | Low risk20 | —-0.096 |
| 16 | 20FD0035CONSTRUCTION OF WATER SUPPLY, BGRY. UPPER AND LOWER OMON, RAGAY, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱1.9M | 100% | Low risk19 | —-0.063 |
| 17 | 20FD0036CONCRETING OF BARANGAY ROAD, COTMO TO SAN VICENTE, SIPOCOT, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱1.9M | 100% | Low risk19 | —-0.096 |
| 18 | 19FN0184REBLOCKING/WIDENING OF BARANGAY ROAD FROM ANDAYA HIGHWAY TO INTRAMUROS, BRGY. PANAYTAYAN, RAGAY, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱1.9M | 100% | Low risk19 | —-0.096 |