Contractor dossier
347 projects on file, including joint ventures this contractor is part of.
Total projects
347
Total budget
₱10.4B
Average progress
91.9%
Completion rate
85.6%
Average risk score
46.3
Medium risk on average, out of 100
Flagged as unusual
6
1.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 343 | ₱10.1B | 46.2 | 6 | 91.9% |
| Region VIII | 2 | ₱162.2M | 62.5 | 0 | 100.0% |
| Region XIII | 1 | ₱149.6M | 53.2 | 0 | 100.0% |
| Region III | 1 | ₱9.6M | 31.1 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 186 | ₱6.6B | 46.0 | 4 | 91.8% |
| Buildings and Facilities | 58 | ₱665.7M | 43.3 | 0 | 93.2% |
| Flood Control and Drainage | 51 | ₱2.3B | 49.5 | 0 | 91.4% |
| Bridges | 32 | ₱492.3M | 42.1 | 0 | 100.0% |
| Water Provision and Storage | 14 | ₱103.2M | 48.1 | 0 | 75.7% |
| OTHER | 6 | ₱229.5M | 75.3 | 2 | 83.3% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24DE0247CLUSTER - CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES: 1. CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY BAGONG TUBIG, SAN LUIS, BATANGAS (PHA | Region IV-A | Batangas 2nd DEO | On-Going | ₱5.8M | 0% | High risk85 | Flagged0.059 |
| 23DE0179CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY MUZON, SAN L | Region IV-A | Batangas 2nd DEO | On-Going | ₱7.1M | 100% | High risk85 | Flagged0.041 |
| 17I00001IMPRVT./WIDENING OF NAT'L. ROADS, ALLEN-CATARMAN ROAD (S00005SM), KO729+000-KO731+300; KO731+350-KO732+949; KO722+751-KO723+480, NORTHERN SAMAR, 1ST LD | Region VIII | Region VIII | Completed | ₱141.7M | 100% | High risk80 | —-0.015 |
| 20DB0007ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - TERNATE-NASUGBU RD - K0085+288 - K0085+433 | Region IV-A | Batangas 1st DEO | Completed | ₱96.5M | 100% | High risk72 | —-0.062 |
| 20DB0027FLOOD MANAGEMENT PROGRAM-CONSTRUCTION /MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF REVETMENT ALONG SINISIAN RIVER AT BRGY. SINISIAN WEST, LEMERY, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱19.6M | 100% | High risk68 | —-0.055 |
| 25DE0183CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (HEALTH CENTER), BRGY. GASANG, MABINI, BATANGAS | Region IV-A | Batangas 2nd DEO | On-Going | ₱19.2M | 14% | High risk68 | —-0.010 |
| 16DE0184MFO-1 NATIONAL ROAD NETWORK SERVICES, NETWORK DEVELOPMENT IMPROVEMENT/WIDENING OF NATIONAL ROADS, SECONDARY ROAD AT PALICO - BALAYAN- BATANGAS ROAD, K0148+709 - K0149+813, K0149+855 - K0149+1147 | Region IV-A | Batangas 2nd DEO | Completed | ₱48M | 100% | High risk67 | —-0.067 |
| 16DE0181MFO-1 NATIONAL ROAD NETWORK SERVICES, CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS, WIDENING OF PERMANENT BRIDGE 1 TO MORE THAN 2 LANES BALAGTAS BR. (B02918LZ) ALONG MANILA-BATANGAS ROAD. | Region IV-A | Batangas 2nd DEO | Completed | ₱10.8M | 100% | High risk67 | —-0.041 |
| 24DE0153CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF TESDA REGIONAL TRAINING CENTER (CALABARZON) BUILDING, P. HERRERA ST., BARANGAY 6, BATANGAS CITY | Region IV-A | Batangas 2nd DEO | Completed | ₱59.4M | 100% | High risk67 | —-0.039 |
| 20DB0123CONCRETING & RIPRAPPING OF LOCAL ROAD OF BRGY. TUBUAN, LEMERY, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱4.8M | 100% | High risk67 | —-0.042 |
| 17DB0050ASSET PRESERVATION OF NATIONAL ROADS - REHAB./RECONST. OF NATIONAL ROADS WITH SLIPS, COLLAPSE, AND LANDSLIDE - SECONDARY, P00103564LZ, TERNATE-NASUGBU RD, S01859LZ, K0075+(-176)-K0075+(-076) NASUGBU, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱12.3M | 100% | High risk66 | —-0.071 |
| 17DB0004ASSET PRESERVATION OF NATIONAL ROADS - PREVENTIVE MAINTENANCE BASED ON PAVEMENT MANAGEMENT SYSTEM/HIGHWAY DEVELOPMENT AND MANAGEMENT-4 (HDM-4) - SECONDARY, P00100529LZ, TAGAYTAY-NASUGBU RD., S05790LZ, K0102+224-K0102+499 | Region IV-A | Batangas 1st DEO | Completed | ₱5.1M | 100% | High risk66 | —-0.064 |
| 17DB0023NETWORK DEVELOPMENT-IMPROVEMENT/WIDENING OF NATIONAL ROADS-TERTIARY, P00109152LZ, TALISAY-LAUREL-AGONCILLO RD., S00515LZ, K0122+(-974)-K0122+(-334), LEMERY, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱22M | 100% | High risk66 | —-0.075 |
| 24DE0241CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF CIRCUMFERENTIAL ROAD, TINGL | Region IV-A | Batangas 2nd DEO | On-Going | ₱93.7M | 0% | High risk65 | Flagged0.026 |
| 24DE0242CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF CIRCUMFERENTIAL ROAD, TINGL | Region IV-A | Batangas 2nd DEO | On-Going | ₱93.7M | 0% | High risk65 | Flagged0.026 |
| 24DE0228ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS, BAUAN-MABINI RD - K0166+412 - K0166+474, K0167+272 - K0 | Region IV-A | Batangas 2nd DEO | On-Going | ₱93.6M | 8% | High risk65 | Flagged0.026 |
| 25DE0068ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF SEAWALL STRUCTURE ALONG MABINI-BAUAN-SAN LUIS-TAAL-LEMERY | Region IV-A | Batangas 2nd DEO | On-Going | ₱93.6M | 31% | High risk65 | —-0.025 |
| 25DE0031ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURES AL | Region IV-A | Batangas 2nd DEO | On-Going | ₱93.6M | 20% | High risk65 | —-0.021 |
| 25DE0030ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOOD, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRU | Region IV-A | Batangas 2nd DEO | On-Going | ₱93.6M | 21% | High risk65 | —-0.021 |
| 24DE0227ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF MISSING LINKS/NEW ROADS, TINGLOY CIRCUMFERENTIAL ROAD, PACKAGE O, SECTION 1-A, TINGLOY, BATANGAS | Region IV-A | Batangas 2nd DEO | On-Going | ₱98.3M | 0% | High risk65 | Flagged0.028 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24DE0247CLUSTER - CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES: 1. CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY BAGONG TUBIG, SAN LUIS, BATANGAS (PHA | Region IV-A | Batangas 2nd DEO | On-Going | ₱5.8M | 0% | High risk85 | Flagged0.059 |
| 23DE0179CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY MUZON, SAN L | Region IV-A | Batangas 2nd DEO | On-Going | ₱7.1M | 100% | High risk85 | Flagged0.041 |
| 24DE0227ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF MISSING LINKS/NEW ROADS, TINGLOY CIRCUMFERENTIAL ROAD, PACKAGE O, SECTION 1-A, TINGLOY, BATANGAS | Region IV-A | Batangas 2nd DEO | On-Going | ₱98.3M | 0% | High risk65 | Flagged0.028 |
| 24DE0228ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS, BAUAN-MABINI RD - K0166+412 - K0166+474, K0167+272 - K0 | Region IV-A | Batangas 2nd DEO | On-Going | ₱93.6M | 8% | High risk65 | Flagged0.026 |
| 24DE0241CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF CIRCUMFERENTIAL ROAD, TINGL | Region IV-A | Batangas 2nd DEO | On-Going | ₱93.7M | 0% | High risk65 | Flagged0.026 |
| 24DE0242CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF CIRCUMFERENTIAL ROAD, TINGL | Region IV-A | Batangas 2nd DEO | On-Going | ₱93.7M | 0% | High risk65 | Flagged0.026 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 126 | 22DB0083CONSTRUCTION OF WATER SUPPLY SYSTEM IN BARANGAY LUYA, CALATAGAN, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱4.8M | 100% | Medium risk49 | —-0.069 |
| 127 | 23DB0037CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES -CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) IN LEMERY PILOT SCHOOL, BARANGAY BAGONG SIKAT, LEMERY, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱6.4M | 100% | Medium risk48 | —-0.106 |
| 128 | 24DE0129CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY GASANG, MABINI, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱9.9M | 100% | Medium risk48 | —-0.105 |
| 129 | 25DE0174CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION OF WATER SYSTEM AT BARANGAY GELERANG KAWAYAN, SAN PASCUAL, BATANGAS | Region IV-A | Batangas 2nd DEO | On-Going | ₱4.8M | 24% | Medium risk48 | —-0.017 |
| 130 | 20DE0127LOCAL INFRASTRUCTURE PROGRAM CONSTRUCTION OF MULTI-PURPOSE COVERED COURT/EVACUATION CENTER, BRGY. SAGUING, MABINI, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱7.9M | 100% | Medium risk48 | —-0.105 |
| 131 | 25DE0061CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION OF WATER SUPPLY SYSTEM (WATER WORKS), BARANGAY BALATBAT, LOBO, BATANGAS | Region IV-A | Batangas 2nd DEO | On-Going | ₱4.8M | 10% | Medium risk48 | —-0.012 |
| 132 | 22DB0081CONSTRUCTION OF PUBLIC WATER SUPPLY SYSTEM IN CALATAGAN, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱4.8M | 100% | Medium risk48 | —-0.067 |
| 133 | 23DE0061CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY BALAGTASIN, SAN LUIS, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱5.9M | 100% | Medium risk48 | —-0.105 |
| 134 | 23DE0062CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY TUNGAL, SAN LUIS, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱5.9M | 100% | Medium risk48 | —-0.105 |
| 135 | 19DE0086ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, BRIDGE PROGRAM, WIDENING OF PERMANENT BRIDGES, CALANSAYAN BR. (B02917LZ) (LEFT SIDE) ALONG MANILA-BATANGAS RD | Region IV-A | Batangas 2nd DEO | Completed | ₱32.9M | 100% | Medium risk48 | —-0.063 |
| 136 | 18DE0135ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, BRIDGE PROGRAM, WIDENING OF PERMANENT BRIDGES, CALANSAYAN BR. (B02917LZ) ALONG MANILA-BATANGAS RD. | Region IV-A | Batangas 2nd DEO | Completed | ₱29.4M | 100% | Medium risk48 | —-0.066 |
| 137 | 19DE0209ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, BRIDGE PROGRAM, WIDENING OF PERMANENT BRIDGES, STA. MARIA BR. (B02924LZ) ALONG BAUAN-MABINI RD | Region IV-A | Batangas 2nd DEO | Completed | ₱40.1M | 100% | Medium risk48 | —-0.062 |
| 138 | 20DE0038ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - PATAY BR. (B03046LZ) ALONG BATANGAS-QUEZON RD | Region IV-A | Batangas 2nd DEO | Completed | ₱34.5M | 100% | Medium risk48 | —-0.067 |
| 139 | 18DE0200CONCRETING OF BRGY. BALAGTASIN FMR, BRGY. BALAGTASIN, SAN LUIS, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱16.7M | 100% | Medium risk48 | —-0.053 |
| 140 | 22DB0075CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN DIEGO, LIAN, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱5M | 100% | Medium risk48 | —-0.097 |
| 141 | 22DB0160CONCRETING OF SITIO IMUS, BRGY. AGA FMR IN NASUGBU, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱14.7M | 100% | Medium risk48 | —-0.055 |
| 142 | 23DE0060CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY BAGONG TUBIG, SAN LUIS, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱5.9M | 100% | Medium risk48 | —-0.104 |
| 143 | 24DB0134CONCRETING OF BRGY. CALUANGAN FMR, BRGY. CALUANGAN, CALACA, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱14.9M | 100% | Medium risk48 | —-0.052 |
| 144 | 20DE0129LOCAL INFRASTRUCTURE PROGRAM CONSTRUCTION OF MULTI-PURPOSE COVERED COURT AT BRGY. MAINIT, MABINI, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱7.9M | 100% | Medium risk48 | —-0.104 |
| 145 | 23DE0142CONCRETING OF BRGY. MALIMATOC I FMR, BRGY. MALIMATOC I, MABINI, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱25.9M | 100% | Medium risk48 | —-0.050 |
| 146 | 18DB0181CONSTRUCTION OF MALARUHATAN BRIDGE, LIAN, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱40.6M | 100% | Medium risk48 | —-0.064 |
| 147 | 23DE0141CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE FACILITY (PIER) IN CORONA, TINGLOY, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱19.8M | 100% | Medium risk48 | —-0.099 |
| 148 | 21DE0125LOCAL PROGRAM - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY CUMBA, BATANGAS CITY, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱4.9M | 100% | Medium risk48 | —-0.106 |
| 149 | 24DE0102CONVERGENCE AND SPECIAL SUPPORT PROGRAM, CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS, WATER SUPPLY SYSTEM, CONSTRUCTION OF WATER SUPPLY SYSTEM, BRGY. SAN ISIDRO, SAN LUIS, BATANGAS | Region IV-A | Batangas 2nd DEO | Completed | ₱5.9M | 100% | Medium risk48 | —-0.070 |
| 150 | 23DE0164CLUSTER - CONVERGENCE AND SPECIAL SUPPORT PROGRAM, CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS, WATER SUPPLY SYSTEM, 1. CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY STO. NIÑO, BATANGAS CITY, BATANGAS 2. CONSTRUCT | Region IV-A | Batangas 2nd DEO | Completed | ₱19.6M | 100% | Medium risk48 | —-0.066 |