145 projects on file, including joint ventures this contractor is part of.
Total projects
145
Total budget
₱4.9B
Average progress
91.4%
Completion rate
74.5%
Average risk score
49.4
Medium risk on average, out of 100
Flagged as unusual
12
8.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VII | 143 | ₱4.9B | 49.5 | 12 | 91.3% |
| Region X | 2 | ₱19.2M | 44.1 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 46 | ₱1.2B | 42.8 | 1 | 86.9% |
| Buildings and Facilities | 36 | ₱713M | 42.5 | 1 | 93.8% |
| Flood Control and Drainage | 23 | ₱1.8B | 55.8 | 1 | 95.5% |
| Bridges | 17 | ₱210.9M | 46.0 | 0 | 98.0% |
| OTHER | 12 | ₱410.8M | 69.0 | 3 | 93.7% |
| GAA 2025 SSP | 5 | ₱210.6M | 93.6 | 4 | 68.2% |
| Water Provision and Storage | 4 | ₱13.3M | 28.3 | 0 | 100.0% |
| GAA 2025 OO-2 | 2 | ₱423.5M | 93.2 | 2 | 76.6% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25H00094CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG JUBAY RIVER, LILOAN, CEBU | Region VII | Region VII | On-Going | ₱97M | 97% | High risk96 | Flagged0.017 |
| 25HG0091CONSTRUCTION OF ROAD, BRGY. DAKIT TO BRGY. PANDAN LEADING TO FIRING RANGE AND NATURE PARK, BOGO CITY, CEBU | Region VII | Cebu 4th DEO | On-Going | ₱48M | 81% | High risk95 | Flagged0.016 |
| 25HN0106SSP: SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF NANGKA-TUGBONGGAN ROAD WITH SLOPE PROTECTION SYSTEM (PACKAGE 1), CONSOLACION, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱49M | 31% | High risk95 | Flagged0.029 |
| 25H00049OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONST. OF FLOOD CONTROL STRUCTURE ALONG COTCOT RIVER (UPSTREAM), LILOAN, CEBU | Region VII | Region VII | On-Going | ₱269.2M | 69% | High risk93 | Flagged0.020 |
| 25H00048OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG COTCOT RIVER, PHASE 2, LILOAN, CEBU | Region VII | Region VII | On-Going | ₱154.3M | 84% | High risk93 | Flagged0.002 |
| 25HN0108SSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - REHABILITATION OF ROAD AT BARANGAY. PILIPOG, CORDOVA, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱11.7M | 33% | High risk93 | Flagged0.027 |
| 25HN0031SSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES -REHABILITATION OF ROAD WITH DRAINAGE FACILITIES, BARANGAY PANOYPOY, CONSOLACION, CEBU | Region VII | Cebu 6th DEO | Completed | ₱4.9M | 100% | High risk89 | —-0.023 |
| 24H00158CONSTRUCTION/COMPLETION OF ACADEMIC BUILDINGS, CEBU TECHNOLOGICAL UNIVERSITY (CTU) - LILOAN CAMPUS, CEBU TECHNOLOGICAL UNIVERSITY | Region VII | Region VII | On-Going | ₱49.7M | 68% | High risk88 | Flagged0.062 |
| 24HN0228CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - IMPROVEMENT OF ROAD, BARANGAY LAMAC, CONSOLACION, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱48.2M | 63% | High risk88 | Flagged0.058 |
| 24H00188CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONST. OF FLOOD CONTROL STRUCTURE ALONG BUTUANON RIVER BRGY. CASUNTINGAN TO BRG. CABANCALAN (PHASE III | Region VII | Region VII | On-Going | ₱48.2M | 67% | High risk76 | Flagged0.047 |
| 23H00123OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST./ REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BAGATAYAM RIVER, SOGOD, CEBU | Region VII | Region VII | On-Going | ₱79.5M | 94% | High risk71 | Flagged0.004 |
| 23HN0099CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD WITH DRAINAGE FACILITIES, BRGY UMAPAD, MANDAUE CITY, CEBU | Region VII | Cebu 6th DEO | Completed | ₱98.9M | 100% | High risk70 | —-0.016 |
| 21HN0021LP - LOCAL INFRASTRUCTURE PROGRAM-LOCAL ROADS AND BRIDGES-LOCAL ROADS - CONCRETING OF POLOG - PANOYPOY ROAD 3, INCLUDING DRAINAGE, CONNECTING TO CEBU NORTH HAGNAYA WHARF ROAD, POLOG & PANOYPOY, CONSOLACION, CEBU | Region VII | Cebu 6th DEO | Completed | ₱74.3M | 100% | High risk68 | —-0.027 |
| 25HI0018OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG COTCOT RIVER (DOWNSTREAM), LILOAN, CEBU | Region VII | Cebu 5th DEO | On-Going | ₱144.7M | 73% | High risk67 | —-0.014 |
| 24HN0032OO2: -FLOOD MANAGEMENT PROGRAM - CONST./ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONST. OF FLOOD CONTROL STRUCTURE ALONG CANSAGA RIVER, BARANGAY POLOG TO BARANGAY PANOYPOY, CONSOLACION, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱135.1M | 100% | High risk66 | —-0.019 |
| 25HN0090OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM- CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONST. OF FLOOD MITIGATION RIVERBANK FACILITIES ALONG CANSAGA RIVER, PACKAGE I, GARING, CONSOLACION, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱135M | 89% | High risk66 | —-0.022 |
| 24HI0061CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG COTCOT RIVER, COMPOSTELA, CEBU | Region VII | Cebu 5th DEO | Completed | ₱140.2M | 100% | High risk66 | —-0.056 |
| 21HI0009CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG DANAO BRIDGE I, DANAO CITY, CEBU | Region VII | Cebu 5th DEO | Completed | ₱94.9M | 100% | High risk65 | —-0.061 |
| 23HN0063CSSP: BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD AT BARANGAY PILIPOG, CORDOVA, CEBU | Region VII | Cebu 6th DEO | Completed | ₱4.9M | 100% | High risk64 | —-0.034 |
| 25H00057OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROG., CONST./ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONST. OF FLOOD CONTROL STRUCTURE ALONG PANOYPOY RIVER LEADING TO SANITARY LANDFILL AND CRUSHING PLANT | Region VII | Region VII | On-Going | ₱96.4M | 69% | High risk64 | —-0.024 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24H00158CONSTRUCTION/COMPLETION OF ACADEMIC BUILDINGS, CEBU TECHNOLOGICAL UNIVERSITY (CTU) - LILOAN CAMPUS, CEBU TECHNOLOGICAL UNIVERSITY | Region VII | Region VII | On-Going | ₱49.7M | 68% | High risk88 | Flagged0.062 |
| 24HN0228CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - IMPROVEMENT OF ROAD, BARANGAY LAMAC, CONSOLACION, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱48.2M | 63% | High risk88 | Flagged0.058 |
| 24H00188CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONST. OF FLOOD CONTROL STRUCTURE ALONG BUTUANON RIVER BRGY. CASUNTINGAN TO BRG. CABANCALAN (PHASE III | Region VII | Region VII | On-Going | ₱48.2M | 67% | High risk76 | Flagged0.047 |
| 24HI0100CONSTRUCTION OF LILOAN CHILDRENS HOSPITAL, LILOAN, CEBU | Region VII | Cebu 5th DEO | On-Going | ₱35.8M | 0% | Medium risk47 | Flagged0.034 |
| 25HN0106SSP: SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF NANGKA-TUGBONGGAN ROAD WITH SLOPE PROTECTION SYSTEM (PACKAGE 1), CONSOLACION, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱49M | 31% | High risk95 | Flagged0.029 |
| 25HN0108SSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - REHABILITATION OF ROAD AT BARANGAY. PILIPOG, CORDOVA, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱11.7M | 33% | High risk93 | Flagged0.027 |
| 25H00049OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONST. OF FLOOD CONTROL STRUCTURE ALONG COTCOT RIVER (UPSTREAM), LILOAN, CEBU | Region VII | Region VII | On-Going | ₱269.2M | 69% | High risk93 | Flagged0.020 |
| 25H00094CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG JUBAY RIVER, LILOAN, CEBU | Region VII | Region VII | On-Going | ₱97M | 97% | High risk96 | Flagged0.017 |
| 25HG0091CONSTRUCTION OF ROAD, BRGY. DAKIT TO BRGY. PANDAN LEADING TO FIRING RANGE AND NATURE PARK, BOGO CITY, CEBU | Region VII | Cebu 4th DEO | On-Going | ₱48M | 81% | High risk95 | Flagged0.016 |
| 23H00123OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST./ REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BAGATAYAM RIVER, SOGOD, CEBU | Region VII | Region VII | On-Going | ₱79.5M | 94% | High risk71 | Flagged0.004 |
| 25H00048OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG COTCOT RIVER, PHASE 2, LILOAN, CEBU | Region VII | Region VII | On-Going | ₱154.3M | 84% | High risk93 | Flagged0.002 |
| 24HH0106CONCRETING OF SITIO LUTON BRGY. MABINI FMR, BRGY. MABINI, CEBU CITY | Region VII | Cebu City DEO | On-Going | ₱16.9M | 100% | Medium risk46 | Flagged0.002 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 101 | 23HI0063REHABILITATION OF FC STRUCTURE ALONG COTCOT RIVER, COMPOSTELA SIDE (UPSTREAM), BRGY. CABADIANGAN, COMPOSTELA, CEBU | Region VII | Cebu 5th DEO | Completed | ₱31M | 100% | Medium risk46 | —-0.080 |
| 102 | 24H00180ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING - SECONDARY ROADS, CONSOLACION-TAYUD-LILOAN RD - K0015 + 448 - K0015 +869 | Region VII | Region VII | On-Going | ₱26.9M | 0% | Medium risk46 | —-0.031 |
| 103 | 22H00048ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING - SECONDARY ROADS, CONSOLACION-TAYUD- LILOAN RD - K0018 + 000 - K0019 + 668, CEBU PROVINCE | Region VII | Region VII | Completed | ₱25.1M | 100% | Medium risk46 | —-0.087 |
| 104 | 24HI0140NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS CEBU NORTH HAGNAYA WHARF RD - K0055+500 - K0055+630, K0055+725 - K0055+925 | Region VII | Cebu 5th DEO | On-Going | ₱26.4M | 7% | Medium risk46 | —-0.025 |
| 105 | 23HI0062REHABILITATION OF FC STRUCTURE ALONG COTCOT RIVER, LILOAN, CEBU | Region VII | Cebu 5th DEO | Completed | ₱15.5M | 100% | Medium risk46 | —-0.079 |
| 106 | 19HD0031CONSTRUCTION/IMPROVEMENT OF ACCESS RAODS LEADING TO DECLARED TOURISM DESTINATIONS, ACCESS ROAD LEADING TO GUIWANON SPRING, BARANGAY TAPUL, TABOGON, CEBU | Region VII | Cebu 4th DEO | Completed | ₱19.6M | 100% | Medium risk46 | —-0.096 |
| 107 | 19HI0043ROAD CONCRETING OF BARANGAY SAN ROQUE, LILOAN, CEBU | Region VII | Cebu 5th DEO | Completed | ₱9.4M | 100% | Medium risk46 | —-0.097 |
| 108 | 23HN0191OO1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - MACTAN CIRCUMFERENTIAL RD - K0026 + 647 - K0026 + 551, CORDOVA CEBU | Region VII | Cebu 6th DEO | Completed | ₱9.1M | 100% | Medium risk45 | —-0.096 |
| 109 | 24HI0005CONSTRUCTION OF ROAD, BARANGAY ADELA, PORO, CEBU | Region VII | Cebu 5th DEO | Completed | ₱9.9M | 100% | Medium risk45 | —-0.098 |
| 110 | 20HD0052CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LEADING TO GUIWANON SPRING BARANGAY TAPUL, TABOGON, CEBU STA. 0+000-STA. 0+156 | Region VII | Cebu 4th DEO | Completed | ₱4.9M | 100% | Medium risk45 | —-0.096 |
| 111 | 24HI0010CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - CONCRETING OF ROAD LEADING TO TANGUB CAVE, PORO, CEBU | Region VII | Cebu 5th DEO | On-Going | ₱28.9M | 100% | Medium risk45 | —-0.054 |
| 112 | 20HI0017CONSTRUCTION OF CONCRETE ROAD - BARANGAY ROAD ALONG SABANG IN SUPPORT OF MITSUMI AND REPUBLIC CEMENT, DANAO CITY, CEBU | Region VII | Cebu 5th DEO | Completed | ₱9.3M | 100% | Medium risk45 | —-0.097 |
| 113 | 24HI0077CONSTRUCTION OF ROAD, BARANGAY UNION, SAN FRANCISCO, CEBU | Region VII | Cebu 5th DEO | On-Going | ₱19.6M | 98% | Medium risk44 | —-0.054 |
| 114 | 23HI0136CONSTRUCTION OF 3STY6CL (PHASE 1) , LATABAN ES, LILOAN, CEBU | Region VII | Cebu 5th DEO | Completed | ₱10M | 100% | Medium risk44 | —-0.052 |
| 115 | 18HI0059CONSTRUCTION OF 3 STOREY, 6 CLASSROOM SB AT MASLOG NHS, DANAO CITY, CEBU | Region VII | Cebu 5th DEO | Completed | ₱13.5M | 100% | Medium risk44 | —-0.052 |
| 116 | 24HI0076CONSTRUCTION OF ROAD, BARANGAY ESPERANZA, SAN FRANCISCO, CEBU | Region VII | Cebu 5th DEO | Completed | ₱9.8M | 100% | Medium risk44 | —-0.095 |
| 117 | 24HI0068IMPROVEMENT OF ROAD, BARANGAY MERCEDES, PORO, CEBU | Region VII | Cebu 5th DEO | Completed | ₱4.9M | 100% | Medium risk43 | —-0.093 |
| 118 | 24HI0072ROAD CONCRETING, BRGY. ESPERANZA, PORO, CEBU | Region VII | Cebu 5th DEO | Completed | ₱4.9M | 100% | Medium risk43 | —-0.095 |
| 119 | 20HN0078CONSTRUCTION OF 3-STOREY, 6-CL SCHOOL BUILDING AT GABI ES, CORDOVA, CEBU | Region VII | Cebu 6th DEO | Completed | ₱18.2M | 100% | Medium risk43 | —-0.043 |
| 120 | 18HI0061CONSTRUCTION OF 3 STOREY 9 CLASSROOM SB AT ESPERANZA ES, SAN FRANCISCO, CEBU | Region VII | Cebu 5th DEO | Completed | ₱24M | 100% | Medium risk43 | —-0.039 |
| 121 | 24HN0233CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, CORDOVA, CEBU | Region VII | Cebu 6th DEO | Completed | ₱4.9M | 100% | Medium risk42 | —-0.054 |
| 122 | 22HI0061CONCRETING OF FARM-TO-MARKET ROAD AT BRGY. TABLA, LILOAN, CEBU | Region VII | Cebu 5th DEO | Completed | ₱10M | 100% | Medium risk42 | —-0.045 |
| 123 | 22HN0091CONCRETING OF BRGY. DANGLAG TO BRGY. GARING FMR, BRGY. DANGLAG AND BRGY. GARING, CONSOLACION, CEBU | Region VII | Cebu 6th DEO | Completed | ₱11.9M | 100% | Medium risk42 | —-0.044 |
| 124 | 18HN0054CONCRETING OF PUROK AVOCADO, BRGY. TOLOTOLO FMR, BRGY.TOLOTOLO, CONSOLACION, CEBU | Region VII | Cebu 6th DEO | Completed | ₱6.6M | 100% | Medium risk42 | —-0.043 |
| 125 | 16KJ0001REHABILITAITON/MAJOR REPAIR OF PERMANENT BRIDGES, H. RAMIRO BR (B01500MN) ALONG OZAMIZ-OROQUIETA RD; HINAGDONG BR (B00359MN), LITAPAN BR (B00357MN) & PULOT BR (B01640MN) ALONG OZAMIZ-PAGADIAN RD (CLUSTER VII), LAPASAN, CLARIN; TABID, PULOT, OZAMIZ CITY | Region X | Region X | Completed | ₱9.5M | 100% | Medium risk41 | —-0.043 |