Contractor dossier
62 projects on file, including joint ventures this contractor is part of.
Total projects
62
Total budget
₱619.8M
Average progress
93.6%
Completion rate
88.7%
Average risk score
43.2
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| National Capital Region | 58 | ₱596.2M | 43.2 | 0 | 93.2% |
| Region IV-A | 2 | ₱16.7M | 45.8 | 0 | 100.0% |
| Region III | 2 | ₱6.8M | 40.7 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 29 | ₱265.1M | 45.0 | 0 | 93.1% |
| Roads | 27 | ₱275M | 41.0 | 0 | 92.8% |
| Flood Control and Drainage | 5 | ₱70.3M | 37.7 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱9.3M | 81.2 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25OB0307REHABILITATION OF RANCHO 3 ROAD NETWORK, BARANGAY CONCEPCION DOS, MARIKINA CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱9.3M | 100% | High risk81 | —-0.034 |
| 24CC0417CONSTRUCTION OF ROAD WITH DRAINAGE STRUCTURE IN JOSE P. RIZAL, POBLACION, PANDI, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱4.9M | 100% | High risk70 | —-0.070 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 23OB0223REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY FORTUNE, MARIKINA CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱4.8M | 100% | Medium risk47 | —-0.098 |
| 27 | 24OB0339INSTALLATION OF ROAD SAFETY DEVICES AT BARANGAY TUMANA, MARIKINA CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱28.3M | 100% | Medium risk47 | —-0.099 |
| 28 | 19OB0054CONSTRUCTION/REHABILITATION (EXTENSION) OF MULTI-PURPOSE BUILDING INCLUDING UPGRADING OF FACILITIES WITH GROUND IMPROVEMENT AT BARANGAY HULO (PEOPLES LYING IN) MANDALUYONG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱4.8M | 100% | Medium risk46 | —-0.102 |
| 29 | 25OB0286INSTALLATION OF ROAD SAFETY DEVICES ALONG PARAISO STREET, PANDAY PIRA STREET, PALARIS STREET, PILAPIL STREET, PINGKIAN STREET, PARNASO STREET, CRUZ AND VICTORIA COMPOUND, BARANGAY PARANG, MARIKINA CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱18.6M | 100% | Medium risk46 | —-0.099 |
| 30 | 23DB0058CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY PANTAY, CALACA, BATANGAS | Region IV-A | Batangas 1st DEO | Completed | ₱6.9M | 100% | Medium risk46 | —-0.085 |
| 31 | 24OB0338INSTALLATION OF ROAD SAFETY DEVICES AT BARANGAY PARANG, MARIKINA CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱14.3M | 100% | Medium risk46 | —-0.100 |
| 32 | 23OB0298REPAIR/REHABILITATION OF ROAD NETWORK, MARIKINA CITY, SECOND DISTRICT | National Capital Region | Metro Manila 1st DEO | Completed | ₱14.1M | 100% | Medium risk46 | —-0.095 |
| 33 | 23OB0232IMPROVEMENT OF TWINRIVER SUBDIVISION ROAD NETWORK, BARANGAY NANGKA, MARIKINA CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱14.1M | 100% | Medium risk46 | —-0.099 |
| 34 | 25OB0054REHABILITATION OF ROAD, SECOND DISTRICT, MARIKINA CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱14.1M | 100% | Medium risk46 | —-0.100 |
| 35 | 22OB0337CONSTRUCTION OF DRAINAGE OUTFALL, BARANGAY TUMANA, MARIKINA CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱46.5M | 100% | Medium risk46 | —-0.087 |
| 36 | 24OB0266REHABILITATION OF DRAINAGE SYSTEM AT BARANGAY BAGONG ILOG, PASIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱8.6M | 100% | Medium risk46 | —-0.089 |
| 37 | 23DB0020CONVERGENCE & SPECIAL SUPPORT PROG-SUSTAINABLE INFRASTRUCTURE PROJ ALLEVIATING GAPS (SIPAG)-ACCESS RDS &/OR BR. FROM THE NATIONAL RD/S LEADING TO MAJOR/STRATEGIC PUBLIC BLDG/FAC.-CONSTRUCTION OF ROAD WITH SLOPE PROTECTION, BARANGAY PANTAY,CALACA,BATANNGAS | Region IV-A | Batangas 1st DEO | Completed | ₱9.8M | 100% | Medium risk46 | —-0.108 |
| 38 | 23OB0295REHABILITATION OF ROAD NETWORK, SECOND DISTRICT, MARIKINA CITY | National Capital Region | Metro Manila 1st DEO | On-Going | ₱9.4M | 100% | Medium risk46 | —-0.055 |
| 39 | 23OB0224REHABILITATION OF APITONG STREET ROAD NETWORK, BARANGAY MARIKINA HEIGHTS, MARIKINA CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱9.3M | 100% | Medium risk46 | —-0.095 |
| 40 | 23OB0266REPAIR/REHABILITATION OF ROAD NETWORK PHASE 1, MARIKINA CITY, SECOND DISTRICT | National Capital Region | Metro Manila 1st DEO | Completed | ₱11.2M | 100% | Medium risk46 | —-0.095 |
| 41 | 23OB0217IMPROVEMENT OF ROAD, BARANGAY MARIKINA HEIGHTS, MARIKINA CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱9.3M | 100% | Medium risk46 | —-0.095 |
| 42 | 23OB0257REHABILITATION OF BARANGAY CONCEPCION UNO ROAD NETWORK, BARANGAY CONCEPCION UNO, MARIKINA CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱9.3M | 100% | Medium risk46 | —-0.095 |
| 43 | 24OB0336INSTALLATION OF ROAD SAFETY DEVICES AT BARANGAY MARIKINA HEIGHTS, MARIKINA CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱11.5M | 100% | Medium risk46 | —-0.098 |
| 44 | 23OB0296REHABILITATION OF BARANGAY TUMANA ROAD NETWORK, BARANGAY TUMANA, MARIKINA CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱9.4M | 100% | Medium risk46 | —-0.098 |
| 45 | 23OB0258REHABILITATION OF BARANGAY TUMANA ROAD NETWORK, SECOND DISTRICT, MARIKINA CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱14M | 100% | Medium risk46 | —-0.098 |
| 46 | 24OB0333INSTALLATION OF ROAD SAFETY DEVICES AT BARANGAY CONCEPCION DOS, MARIKINA CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱9.5M | 100% | Medium risk46 | —-0.099 |
| 47 | 25OD0236STREETLIGHTING ALONG F.A. SEBASTIAN ST. TO (POLO) G. FELICIANO ST/ F. RIVERA ST., VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱7.7M | 53% | Medium risk45 | —-0.055 |
| 48 | 23OB0248REHABILITATION OF KUIBI MULTI-PURPOSE BUILDING INCLUDING SITE DEVELOPMENT, BARANGAY FORTUNE, MARIKINA CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱4.7M | 100% | Medium risk45 | —-0.101 |
| 49 | 23OB0281REHABILITATION OF ST. MARY ELEMENTARY SCHOOL, BARANGAY NANGKA, MARIKINA CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱4.7M | 100% | Medium risk45 | —-0.103 |
| 50 | 23OB0247REHABILITATION OF PACHECO COMPOUND MULTI-PURPOSE BUILDING INCLUDING SITE DEVELOPMENT, BARANGAY FORTUNE, MARIKINA CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱4.7M | 100% | Medium risk45 | —-0.101 |