203 projects on file, including joint ventures this contractor is part of.
Total projects
203
Total budget
₱6.8B
Average progress
93.7%
Completion rate
86.2%
Average risk score
46.7
Medium risk on average, out of 100
Flagged as unusual
1
0.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region I | 203 | ₱6.8B | 46.7 | 1 | 93.7% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 104 | ₱3.4B | 46.1 | 1 | 92.9% |
| Flood Control and Drainage | 68 | ₱2.8B | 48.8 | 0 | 92.7% |
| Buildings and Facilities | 26 | ₱172.3M | 41.5 | 0 | 100.0% |
| Bridges | 5 | ₱381.9M | 56.5 | 0 | 88.9% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 17AI0103CONSTN/UPGRADING/REHAB OF DRAINAGE ALONG NATL RD-PRIMARY MNR, STA. 170+042-STA. 170+202, KO 170+975- | Region I | Pangasinan 3rd DEO | Completed | ₱6.3M | 100% | High risk65 | —-0.056 |
| 17AI0165REPAIR/REHAB/IMPVT (ADDITIONAL PAVEMENT WIDTH) ALONG BINALONAN-ASINGAN-STA. MARIA RD, KO 209+020 - K | Region I | Pangasinan 3rd DEO | Completed | ₱14.1M | 100% | High risk62 | —-0.000 |
| 23A00138REHABILITATION/ MAJOR REPAIR OF PERMANENT BRIDGES, BUED BR. (B00735LZ) ALONG MANILA NORTH RD | Region I | Region I | Completed | ₱115.8M | 100% | High risk61 | —-0.037 |
| 24A00160SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - CONSTRUCTION OF PERMANENT BRIDGE ALONG SAN JACINTO-POZORRUBIO ROAD, BARANGAY DILAN, POZORRUBIO, PANGASINAN | Region I | Region I | On-Going | ₱106.1M | 85% | High risk61 | —-0.011 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 176 | 25AI0034CONSTRUCTION OF ROAD, BARANGAY ATAINAN, ALCALA, PANGASINAN | Region I | Pangasinan 3rd DEO | On-Going | ₱9.7M | 0% | Medium risk44 | —-0.025 |
| 177 | 19AI0373CONCRETING OF BRGY. LOMBOY FMR, BRGY. LOMBOY, VILLASIS, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱4.8M | 100% | Medium risk43 | —-0.037 |
| 178 | 19AI0396CONCRETING OF BRGY. CARAYUNGAN SUR-BRGY. NAMPALCAN FMR, BRGY. CARAYUNGAN SUR AND BRGY. NAMPALCAN, UMINGAN, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱4.7M | 100% | Medium risk41 | —-0.037 |
| 179 | 21AI0171CONCRETING OF BRGY. CALMAY FMR, BRGY. CALMAY, LAOAC, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱11.7M | 100% | Medium risk40 | —-0.036 |
| 180 | 17AI0666CONSTN OF TWO STRY FOR CL SB (W/ MICROPILE) BULANGIT E/S, SAN NICOLAS, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱11.4M | 100% | Medium risk38 | —-0.019 |
| 181 | 17AI0384CONSTN OF TWO STRY SIX CL SB AT STO. TOMAS NHS, SAN NICOLAS, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱12.5M | 100% | Medium risk38 | —-0.020 |
| 182 | 17AI0314CONSTN OF TWO STRY SIX CL SB AT ROSALES NORTH CENTRAL SCH, ROSALES, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱12.5M | 100% | Medium risk38 | —-0.018 |
| 183 | 17AI0049CONSTN OF TWO (2) STOREY SIX (6) CL SB AT SAN RAFAEL E/S, SAN NICOLAS, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱7.9M | 100% | Medium risk38 | —-0.021 |
| 184 | 17AI0570CONSTN OF TWO STRY FOUR CL SB CAPITAN TOMAS PINE E/S, ROSALES, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱9.6M | 100% | Medium risk38 | —-0.019 |
| 185 | 17AI0372CONSTN OF TWO STRY FOUR CL SB BALINCANNAWAY E/S, ROSALES, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱9.6M | 100% | Medium risk38 | —-0.019 |
| 186 | 17AI0164REPAIR/REHAB/IMPVT (ADDITIONAL PAVEMENT WIDTH) ALONG PNER, KO 176+(-639) - KO 176+(-400) | Region I | Pangasinan 3rd DEO | Completed | ₱4.7M | 100% | Medium risk30 | —-0.001 |
| 187 | 20AI0147CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. LAPAZ, UMINGAN, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱3.8M | 100% | Low risk27 | —-0.089 |
| 188 | 20AI0170CONSTRUCTION AND/OR REPAIR/REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. POBLACION, URDANETA CITY, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱2.9M | 100% | Low risk27 | —-0.088 |
| 189 | 20AI0127CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. BALINCANAWAY, ROSALES, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱2.9M | 100% | Low risk27 | —-0.088 |
| 190 | 18AI0188CONCRETING OF ROAD AT BRGY. SAN PABLO, UMINGAN, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱2.9M | 100% | Low risk27 | —-0.090 |
| 191 | 20AI0109CONSTRUCTION OF ROAD, BRGY. STA. MARIA-CACABUGAOAN, SAN NICOLAS, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱3.8M | 100% | Low risk26 | —-0.092 |
| 192 | 17AI0125CONCRETING OF SAN PEDRO ILI ROAD, BRGY. SAN PEDRO ILI, ALCALA, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱1.9M | 100% | Low risk26 | —-0.055 |
| 193 | 21AI0011CONSTRUCTION OF ROAD, BARANGAY VILLEGAS, POZORRUBIO, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱2.9M | 100% | Low risk26 | —-0.090 |
| 194 | 19AI0194CONSTRUCTION/IMPROVEMENT OF MULTI-PURPOSE BUILDING, ASINGAN, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱1.9M | 100% | Low risk24 | —-0.088 |
| 195 | 18AI0171CONCRETING OF ROADS AT CABULOAN-PATAQUID, STA. MARIA, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱1.9M | 100% | Low risk22 | —-0.089 |
| 196 | 19AI0278CONCRETING OF BARANGAY ROAD IN BARANGAY STA. ROSA, STA. MARIA, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱1.9M | 100% | Low risk22 | —-0.088 |
| 197 | 18AI0180CONCRETING OF ROAD, BRGY. BANTUG, UMINGAN, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱1.9M | 100% | Low risk22 | —-0.088 |
| 198 | 18AI0172CONCRETING OF ROADS AT SAN ISIDRO, ROSALES, PANGASINAN` | Region I | Pangasinan 3rd DEO | Completed | ₱1.9M | 100% | Low risk22 | —-0.090 |
| 199 | 18AI0192CONCRETING OF ROADS, BRGY. PILAR STA. MARIA, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱1.9M | 100% | Low risk21 | —-0.088 |
| 200 | 18AI0170CONCRETING OF ROADS AT CABALOANGAN SUR, ROSALES, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱1.9M | 100% | Low risk21 | —-0.089 |