Contractor dossier
169 projects on file, including joint ventures this contractor is part of.
Total projects
169
Total budget
₱9.6B
Average progress
85.8%
Completion rate
69.2%
Below 70%
Average risk score
53.5
Medium risk on average, out of 100
Flagged as unusual
12
7.1% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 85 | ₱6.2B | 55.5 | 6 | 95.0% |
| National Capital Region | 61 | ₱1.9B | 48.6 | 4 | 74.4% |
| Region IV-A | 12 | ₱792.2M | 58.8 | 1 | 87.6% |
| Region IV-B | 6 | ₱350.3M | 56.1 | 1 | 60.2% |
| Region V | 2 | ₱150.6M | 62.3 | 0 | 95.8% |
| Region I | 1 | ₱96.5M | 71.1 | 0 | 100.0% |
| Region VIII | 1 | ₱95.6M | 63.3 | 0 | 74.5% |
| Negros Island Region | 1 | ₱96.5M | 61.7 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 117 | ₱8.2B | 54.4 | 6 | 93.0% |
| Roads | 27 | ₱630.1M | 46.9 | 0 | 75.3% |
| Buildings and Facilities | 18 | ₱308.4M | 47.2 | 2 | 56.7% |
| GAA 2025 SSP | 4 | ₱245.5M | 94.1 | 4 | 65.8% |
| Bridges, Roads | 1 | ₱141.1M | 73.4 | 0 | 91.6% |
| Bridges | 1 | ₱93.6M | 64.1 | 0 | 100.0% |
| Water Provision and Storage | 1 | ₱9.5M | 51.2 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DK0043CSSP - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF LANGUYIN-POBLACION ROAD, POLILLO, QUEZON | Region IV-A | Quezon 1st DEO | On-Going | ₱47.5M | 75% | High risk95 | Flagged0.002 |
| 25OA0008CONSTRUCTION OF FLOOD CONTROL STRUCTURE, PHASE 5, BARANGAY TAÑONG TO BARANGAY DAMPALIT, MALABON CITY | National Capital Region | Malabon-Navotas DEO | On-Going | ₱96M | 94% | High risk95 | Flagged0.012 |
| 25EE0058CONSTRUCTION OF SLOPE PROTECTION AT THE NEWLY BUILT CORON SPORTS COMPLEX, CORON, PALAWAN | Region IV-B | Palawan 1st DEO | On-Going | ₱78.1M | 78% | High risk94 | Flagged0.028 |
| 25OD0375CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (SPORTS COMPLEX), BARANGAY 176, CALOOCAN CITY (PHASE 3) | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱23.9M | 16% | High risk92 | Flagged0.025 |
| 24CC0593CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ANGAT RIVER, PACKAGE B, BARANGAY TAAL-BARANGAY SANTO CRISTO, PULILAN, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.5M | 94% | High risk82 | Flagged0.034 |
| 25CC0244CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BARANGAY CALERO-BARANGAY SAN JUAN-BARANGAY STO. CRISTO, CITY OF MALOLOS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.6M | 96% | High risk81 | —-0.024 |
| 24CC0399CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY SAN JUAN, WAWA AND PANGINAY, BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱151.5M | 100% | High risk81 | —-0.039 |
| 24CC0055CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE AT BARANGAY MALIS (PHASE III), GUIGUINTO, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱99M | 100% | High risk80 | —-0.050 |
| 24CC0468CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ANGAT RIVER, LUMANG BAYAN SECTION, PLARIDEL, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱96.5M | 100% | High risk79 | —-0.048 |
| 24CC0144CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ANGAT RIVER, SIPAT SECTION, PLARIDEL, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱96.5M | 100% | High risk79 | —-0.048 |
| 24CC0142CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG GUIGUINTO RIVER, MALIS SECTION, GUIGUINTO, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱96.5M | 100% | High risk79 | —-0.049 |
| 24CC0641CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BARANGAY SANTA CRUZ (SITIO TUKLAS), GUIGUINTO, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱74.1M | 90% | High risk79 | Flagged0.025 |
| 24CC0587CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KALERO RIVER, PACKAGE A, BARANGAY CALERO, MALOLOS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱69.4M | 96% | High risk77 | Flagged0.024 |
| 24CC0603CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG HAGONOY RIVER AND ITS TRIBUTARIES AT MARULAO, BARANGAY SANTA ELENA, HAGONOY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱72.4M | 0% | High risk77 | Flagged0.050 |
| 24CC0601CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PAMPANGA RIVER, PACAKGE B, BARANGAY SAN MIGUEL - BARANGAY MEYSULAO, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱69.5M | 23% | High risk76 | Flagged0.044 |
| 25CC0052CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE AT BARANGAY DAUNGAN (PUROK 3), GUIGUINTO, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱78.7M | 91% | High risk76 | —-0.028 |
| 23CC0534CONSTRUCTION/IMPROVEMENT OF FLOOD CONTROL PROJECT AND REHABILITATION OF WATERWAYS ALONG BOCAUE RIVER BRGY. BAMBANG BOCAUE, BULACAN STA. 011+280 TO STA. 011+430 | Region III | Bulacan 1st DEO | Completed | ₱72.4M | 100% | High risk76 | —-0.005 |
| 24CC0034CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE AT BARANGAY CALERO, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱77.2M | 100% | High risk76 | —-0.057 |
| 24CC0010CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE AT BARANGAY CAINGIN, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱77.2M | 100% | High risk76 | —-0.025 |
| 25CC0100CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG BOCAUE RIVER, BARANGAY BAMBANG (SITIO BAKOD), BOCAUE, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱78.7M | 86% | High risk76 | —-0.026 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24CC0603CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG HAGONOY RIVER AND ITS TRIBUTARIES AT MARULAO, BARANGAY SANTA ELENA, HAGONOY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱72.4M | 0% | High risk77 | Flagged0.050 |
| 24CC0601CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PAMPANGA RIVER, PACAKGE B, BARANGAY SAN MIGUEL - BARANGAY MEYSULAO, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱69.5M | 23% | High risk76 | Flagged0.044 |
| 24CC0593CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ANGAT RIVER, PACKAGE B, BARANGAY TAAL-BARANGAY SANTO CRISTO, PULILAN, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.5M | 94% | High risk82 | Flagged0.034 |
| 23CC0525CONSTRUCTION OF REVETMENT AND REHABILITATION OF WATERWAYS AT SITIO NAGDASIG, BRGY. SAN JOSE, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱72.4M | 95% | High risk76 | Flagged0.031 |
| 25EE0058CONSTRUCTION OF SLOPE PROTECTION AT THE NEWLY BUILT CORON SPORTS COMPLEX, CORON, PALAWAN | Region IV-B | Palawan 1st DEO | On-Going | ₱78.1M | 78% | High risk94 | Flagged0.028 |
| 24CC0641CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BARANGAY SANTA CRUZ (SITIO TUKLAS), GUIGUINTO, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱74.1M | 90% | High risk79 | Flagged0.025 |
| 25OD0375CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (SPORTS COMPLEX), BARANGAY 176, CALOOCAN CITY (PHASE 3) | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱23.9M | 16% | High risk92 | Flagged0.025 |
| 24CC0587CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KALERO RIVER, PACKAGE A, BARANGAY CALERO, MALOLOS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱69.4M | 96% | High risk77 | Flagged0.024 |
| 25OA0008CONSTRUCTION OF FLOOD CONTROL STRUCTURE, PHASE 5, BARANGAY TAÑONG TO BARANGAY DAMPALIT, MALABON CITY | National Capital Region | Malabon-Navotas DEO | On-Going | ₱96M | 94% | High risk95 | Flagged0.012 |
| 24OD0323CONSTRUCTION OF TWO-STOREY MULTI-PURPOSE BUILDING, BARANGAY 152, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱24.1M | 33% | Medium risk45 | Flagged0.007 |
| 24OD0325CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 150, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱24.1M | 43% | Medium risk46 | Flagged0.003 |
| 25DK0043CSSP - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF LANGUYIN-POBLACION ROAD, POLILLO, QUEZON | Region IV-A | Quezon 1st DEO | On-Going | ₱47.5M | 75% | High risk95 | Flagged0.002 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 126 | 25E00110FLOOD MANAGEMENT PROGRAM- CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONST. OF SLOPE PROTECTION STRUCTURE (ARUTAYAN BRIDGE), ROXAS, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱46.3M | 85% | Medium risk43 | —-0.024 |
| 127 | 25E00109FLOOD MANAGEMENT PROGRAM- CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONST. OF SLOPE PROTECTION STRUCTURE (LAMORO BR. 1), STA. 000+000-STA. 000+082.13 (LEFT SIDE), EL NIDO, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱46.3M | 0% | Medium risk43 | —-0.000 |
| 128 | 22CC0036REHABILITATION OF MAJOR RIVER SYSTEM WITH FLOOD CONTROL STRUCTURE AT MEYSULAO, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱91.7M | 100% | Medium risk42 | —-0.082 |
| 129 | 25OD0313CONSTRUCTION OF ROADS AND DRAINAGE SYSTEMS ALONG BRGY. 165, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱4.7M | 48% | Medium risk41 | —-0.053 |
| 130 | 23CC0126CONSTRUCTION OF FLOOD MITIGATION STRUCTURES ALONG BARANGAY BAMBANG, BULACAN, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱77.2M | 100% | Medium risk38 | —-0.087 |
| 131 | 21CC0281CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, STA. 0+000 - STA. 0+456 ALONG BABATNIN, MALOLOS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱82M | 100% | Medium risk38 | —-0.083 |
| 132 | 23CC0125CONSTRUCTION OF FLOOD MITIGATION STRUCTURES ALONG BARANGAY BAGUMBAYAN, BULACAN, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱77.2M | 100% | Medium risk38 | —-0.089 |
| 133 | 23CC0124CONSTRUCTION OF FLOOD MITIGATION STRUCTURES ALONG BARANGAY MATUNGAO, BULACAN, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱77.2M | 100% | Medium risk38 | —-0.089 |
| 134 | 23CC0101CONSTRUCTION OF FLOOD MITIGATION STRUCTURES ALONG BARANGAY SAN ROQUE, PAMBONG, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱77.2M | 100% | Medium risk36 | —-0.088 |
| 135 | 23CC0005CONSTRUCTION OF FLOOD MITIGATION STRUCTURES ALONG BARANGAY BABATNIN, MALOLOS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱49M | 100% | Medium risk36 | —-0.093 |
| 136 | 23CC0109CONSTRUCTION OF FLOOD MITIGATION STRUCTURES ALONG BARANGAY SAN NICOLAS, HAGONOY, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱77.2M | 100% | Medium risk36 | —-0.089 |
| 137 | 23CC0102CONSTRUCTION OF FLOOD MITIGATION STRUCTURES ALONG BARANGAY SAN AGUSTIN, HAGONOY, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱77.2M | 100% | Medium risk35 | —-0.089 |
| 138 | 23CC0110CONSTRUCTION OF FLOOD MITIGATION STRUCTURES ALONG BARANGAY SAN PABLO, HAGONOY, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱77.2M | 100% | Medium risk35 | —-0.089 |
| 139 | 23CC0111CONSTRUCTION OF FLOOD MITIGATION STRUCTURES ALONG BARANGAY STA. MONICA, HAGONOY, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱77.1M | 100% | Medium risk35 | —-0.089 |
| 140 | 23CC0107CONSTRUCTION OF FLOOD MITIGATION STRUCTURES ALONG BARANGAY PINALAGDAN, PAMBONG, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱77.2M | 100% | Medium risk35 | —-0.090 |
| 141 | 23CC0103CONSTRUCTION OF FLOOD MITIGATION STRUCTURES ALONG BARANGAY SAN JUAN, HAGONOY, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱77.2M | 100% | Medium risk35 | —-0.090 |
| 142 | 22CC0265CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BOCAUE RIVER, CAINGIN SECTION STA. 00+527 TO STA. 00+850, BOCAUE, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱49M | 100% | Medium risk35 | —-0.090 |
| 143 | 23CC0108CONSTRUCTION OF FLOOD MITIGATION STRUCTURES ALONG BARANGAY SAN MIGUEL, HAGONOY, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱77.2M | 100% | Medium risk35 | —-0.089 |
| 144 | 24CC0051CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY SANTA CRUZ, GUIGUINTO, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱72.4M | 100% | Medium risk35 | —-0.089 |
| 145 | 23CC0105CONSTRUCTION OF FLOOD MITIGATION STRUCTURES ALONG BARANGAY STA. LUCIA, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱77.2M | 100% | Medium risk35 | —-0.089 |
| 146 | 23CC0156CONSTRUCTION OF FLOOD MITIGATION STRUCTURES ALONG BARANGAY BULUSAN, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱77.2M | 100% | Medium risk35 | —-0.090 |
| 147 | 23CC0123CONSTRUCTION OF FLOOD MITIGATION STRUCTURES ALONG BARANGAY FRANCES, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱77.2M | 100% | Medium risk35 | —-0.090 |
| 148 | 23CC0255CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BARANGAY SAN ROQUE, BALIUAG, BULACAN (K001+300 TO K001+600), BALIUAG, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱72.4M | 100% | Medium risk35 | —-0.088 |
| 149 | 23CC0254CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BARANGAY SAN ROQUE, BALIUAG, BULACAN (K001+062 TO K001+362), BALIUAG, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱72.4M | 100% | Medium risk35 | —-0.088 |
| 150 | 22CC0136IMPROVEMENT OF MAJOR RIVER SYSTEM AND CONSTRUCTION OF SPUR DIKE ALONG ANGAT RIVER, STA. 0+532 - STA. 0+867, BINTOG SECTION, PLARIDEL, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱62.7M | 100% | Medium risk34 | —-0.090 |