Opening the dossier…
Opening the dossier…
Contractor dossier
51 projects on file, including joint ventures this contractor is part of.
Total projects
51
Total budget
₱3.3B
Average progress
93.8%
Completion rate
78.4%
Average risk score
53.0
Medium risk on average, out of 100
Flagged as unusual
8
15.7% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region II | 10 | ₱297.7M | 53.2 | 2 | 100.0% |
| Region XI | 7 | ₱784.6M | 60.9 | 2 | 74.1% |
| Region VI | 7 | ₱335.3M | 44.7 | 1 | 93.5% |
| Region VII | 6 | ₱387.8M | 55.0 | 0 | 100.0% |
| National Capital Region | 5 | ₱65.6M | 43.6 | 0 | 100.0% |
| Region XII | 5 | ₱755.5M | 36.8 | 0 | 100.0% |
| Region VIII | 3 | ₱155.2M | 72.7 | 1 | 100.0% |
| Region V | 3 | ₱201.7M | 68.4 | 2 | 69.9% |
| Region IV-A | 2 | ₱78.1M | 47.9 | 0 | 100.0% |
| Region I | 1 | ₱37.7M | 72.1 | 0 | 100.0% |
| Cordillera Administrative Region | 1 | ₱121.2M | 62.8 | 0 | 100.0% |
| Region X | 1 | ₱47.9M | 47.3 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 17 | ₱1.2B | 52.8 | 3 | 92.1% |
| Buildings and Facilities | 14 | ₱906.9M | 47.0 | 1 | 93.3% |
| Flood Control and Drainage | 13 | ₱772M | 51.4 | 0 | 95.8% |
| OTHER | 4 | ₱222.7M | 76.8 | 2 | 91.1% |
| Bridges | 2 | ₱57M | 55.3 | 2 | 100.0% |
| Bridges, Roads | 1 | ₱121.2M | 62.8 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 18II0087CONSTRUCTION OF RCDG BRIDGE (DOUBLE LANE) AT SANTA POTENCIANA, MAPANAS, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱35.3M | 100% | High risk87 | Flagged0.020 |
| 24F00354CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING (TRAINING AND INSTRUCTIONAL FACILITY/MEETINGS INCENTIVES CONFERENCES FOR ED | Region V | Region V | On-Going | ₱98M | 64% | High risk82 | Flagged0.009 |
| 17II0019CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS, SAN POLICARPO ARTECHE-LAPINIG ROAD, K0854+000-KO855+000, K0858+000-K0860+000, K0866+300-K0867+400, 2ND DISTRIT, NORTHERN SAMAR II | Region VIII | Northern Samar 2nd DEO | Completed | ₱44M | 100% | High risk76 | —-0.036 |
| 18AA0099CONST. OF MANGATO ARANIW FC, HIGHWAY DRAINAGE SYSTEM OF MANGATO BRIDGE ALONG BALACAD NSR, LAOAG | Region I | Ilocos Norte 1st DEO | Completed | ₱37.7M | 100% | High risk72 | —-0.065 |
| 24LG0118CONSTRUCTION/IMPROVEMENT OF ROAD, BARANGAY DON SALVADOR LOPEZ, CITY OF MATI, DAVAO ORIENTAL | Region XI | Davao Oriental 2nd DEO | On-Going | ₱143.3M | 32% | High risk67 | Flagged0.047 |
| 22L00044CONSTRUCTION OF POBLACION, MARAGUSAN - PALOC ROAD, PACKAGE 5, DAVAO DE ORO | Region XI | Region XI | On-Going | ₱140M | 80% | High risk66 | Flagged0.001 |
| 18F00126CONSTRUCTION OF TWO EVACUATION CENTERS, A-SITIO TUBOG, ZONE 1, LIBON, ALBAY AND B-BRGY. CALILIOG, TINAMBAC, CAMARINES SUR | Region V | Region V | Completed | ₱68.8M | 100% | High risk65 | —-0.081 |
| 24L00326CONSTRUCTION OF BANK PROTECTION STRUCTURE ALONG LASANA RIVER PROTECTING PANABO CITY COASTAL ROAD, CARMEN, DAVAO DEL NORTE | Region XI | Region XI | On-Going | ₱143.3M | 66% | High risk65 | —-0.005 |
| 24L00325CONSTRUCTION OF BANK PROTECTION STRUCTURE ALONG TUGANAY RIVER, PACKAGE 2, CARMEN, DAVAO DEL NORTE | Region XI | Region XI | On-Going | ₱143.3M | 80% | High risk65 | —-0.010 |
| 19G00076CONCRETING OF MALIAO - HILWAN ROAD, TAPAZ, CAPIZ | Region VI | Region VI | On-Going | ₱165.6M | 54% | High risk64 | Flagged0.015 |
| 18P00012CONVERGENCE AND SPECIALSUPPORT PROGRAM CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS GUINZADAN-CAGUBATAN-BALILI (MANKAYAN) ROAD LEADING TO MOGAO MOUNTAIN AND GAWAAN LAKE, INCL. BRIDGE, BAUKO AND TADIAN, MT. PROVINCE | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱121.2M | 100% | High risk63 | —-0.038 |
| 16HD0061CONST/UPGRADING/REHAB OF DRAINAGE, BCMDM RD, K0114+620-K0115+828 & 3-OTHER AT MEDELLIN & DAANBANTAYA | Region VII | Cebu 4th DEO | Completed | ₱45.5M | 100% | High risk63 | —-0.030 |
| 17B00062CONSTRUCTION/REHABILITATION OF ACCESSIBILITY FACILITIES FOR PHYSICALLY CHALLENGED PERSONS (VARIOUS AGENCIES), REGIONAL GOVERNMENT CENTER, CARIG SUR, TUGUEGARAO CITY, CAGAYAN | Region II | Region II | Completed | ₱17.1M | 100% | High risk63 | —-0.053 |
| 22LC0193CONSTRUCTION OF CONCRETE REVETMENT INCLUDING PUMP STATION, SADPUDON CREEK, CARMEN, DAVAO DEL NORTE | Region XI | Davao del Norte DEO | Completed | ₱99M | 100% | High risk62 | —-0.061 |
| 16B00070PROPOSED CONSTRUCTION OF REGIONAL EVACUATION CENTER, BRGY. BANGAG, LALLO, CAGAYAN | Region II | Region II | Completed | ₱32.9M | 100% | High risk60 | —-0.044 |
| 19H00019CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS -BRGY. DAPDAP-BRGY. BANCASAN-BRGY. ANAPOG-BRGY. TAMBONGON ROAD LEADING TO BEACH RESORTS AND MARINE SANCTUARES, SAN REMEGIO, CEBU | Region VII | Region VII | Completed | ₱126.5M | 100% | High risk60 | —-0.078 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24LG0118CONSTRUCTION/IMPROVEMENT OF ROAD, BARANGAY DON SALVADOR LOPEZ, CITY OF MATI, DAVAO ORIENTAL | Region XI | Davao Oriental 2nd DEO | On-Going | ₱143.3M | 32% | High risk67 | Flagged0.047 |
| 19F00103DEVELOPMENT OF SITES AND CONSTRUCTION OF EVACUATION CENTERS IN REGION V, PANGE, MATNOG, SORSOGON | Region V | Region V | On-Going | ₱34.9M | 46% | Medium risk58 | Flagged0.037 |
| 18II0087CONSTRUCTION OF RCDG BRIDGE (DOUBLE LANE) AT SANTA POTENCIANA, MAPANAS, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱35.3M | 100% | High risk87 | Flagged0.020 |
| 19G00076CONCRETING OF MALIAO - HILWAN ROAD, TAPAZ, CAPIZ | Region VI | Region VI | On-Going | ₱165.6M | 54% | High risk64 | Flagged0.015 |
| 24F00354CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING (TRAINING AND INSTRUCTIONAL FACILITY/MEETINGS INCENTIVES CONFERENCES FOR ED | Region V | Region V | On-Going | ₱98M | 64% | High risk82 | Flagged0.009 |
| 16B00076NAT'L BRIDGE CONST'N/REPLACEMENT PROGRAM (DESIGN AND BUILD BRIDGES) BRIDGE CONST'N AND REPLACEMENT PROGRAM I- DESIGN AND BUILD BRIDGES FOR LUZON, BUCAO CREEK BRIDGE AND APPROACHES ALONG JCT. ABBAG-GUINGIN BDRY. ROAD, QUIRINO, BRGYY. BUCAO, NAGTIPUNAN, QUI | Region II | Region II | Terminated | ₱35.8M | 100% | Medium risk58 | Flagged0.002 |
| 17B00025BRIDGE CONSTRUCTION REPLACEMENT PROGRAM (BCRP) 1 DESIGN AND BUILD BRIDGES FOR LUZON, MACTOL BRIDGE AND APPROACHES INCLUDES RIGHT-OF-WAY ACQUISITION ALONG ABBAG-GUINGIN BOUNDARY ROAD, QUIRINO | Region II | Region II | Terminated | ₱21.2M | 100% | Medium risk52 | Flagged0.001 |
| 22L00044CONSTRUCTION OF POBLACION, MARAGUSAN - PALOC ROAD, PACKAGE 5, DAVAO DE ORO | Region XI | Region XI | On-Going | ₱140M | 80% | High risk66 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.