Contractor dossier
124 projects on file, including joint ventures this contractor is part of.
Total projects
124
Total budget
₱5.8B
Average progress
86.0%
Completion rate
63.7%
Below 70%
Average risk score
53.4
Medium risk on average, out of 100
Flagged as unusual
8
6.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 124 | ₱5.8B | 53.4 | 8 | 86.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 69 | ₱2.9B | 48.7 | 0 | 87.6% |
| Buildings and Facilities | 23 | ₱844.9M | 50.2 | 1 | 93.2% |
| Bridges | 11 | ₱1B | 50.8 | 2 | 82.0% |
| GAA 2025 OO-1 | 8 | ₱590.4M | 94.0 | 5 | 65.4% |
| Flood Control and Drainage | 5 | ₱126.1M | 51.2 | 0 | 75.7% |
| GAA 2025 OO-2 | 3 | ₱123.9M | 88.9 | 0 | 70.5% |
| OTHER | 2 | ₱70.9M | 67.0 | 0 | 100.0% |
| Water Provision and Storage | 2 | ₱22M | 36.0 | 0 | 100.0% |
| Bridges, Roads | 1 | ₱98.4M | 66.0 | 0 | 60.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DG0056REHAB./RECONST. OF RDS. - SECONDARY RDS - JUANITO R. REMULLA, SR. RD. K0067+721-K0067+788 | Region IV-A | Cavite 2nd DEO | On-Going | ₱93.5M | 41% | High risk95 | Flagged0.010 |
| 25DG0022REHAB/RECONST OF RDS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERNATE-NASUGBU RD - K0069+645-K006 | Region IV-A | Cavite 2nd DEO | On-Going | ₱93.5M | 76% | High risk95 | Flagged0.001 |
| 25DG0059REHAB./RECONST. OF RDS - SECONDARY RDS - TERNATE-NASUGBU RD. K0069+976-K0070+071 | Region IV-A | Cavite 2nd DEO | On-Going | ₱140.4M | 70% | High risk95 | Flagged0.013 |
| 25DG0054REHAB/RECONST. OF RDS -SECONDARY RDS-JUANITO R. REMULLA, SR. RD. K0068+215-K0068+275, TERNATE, CAVIT | Region IV-A | Cavite 2nd DEO | On-Going | ₱65.5M | 57% | High risk94 | Flagged0.002 |
| 25DG0057REHAB/RECONST OF RDS,-SECONDARY RDS-TERNATE-NASUGBU RD. K0069+926-K0069+976 | Region IV-A | Cavite 2nd DEO | On-Going | ₱74.9M | 37% | High risk94 | Flagged0.008 |
| 25DG0002REHAB/RECONST OF RD W/ SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-TAGAYTAY-TAAL LAKE RD-K0060+290 -K0060+3 | Region IV-A | Cavite 2nd DEO | On-Going | ₱49.1M | 62% | High risk93 | —-0.003 |
| 25DG0005REHAB/RECONST OR RDS W/ SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TAG.-TAAL LAKE RD - K0063+396-K0063+ | Region IV-A | Cavite 2nd DEO | On-Going | ₱33.7M | 91% | High risk93 | —-0.016 |
| 25DG0003REHAB/RECONST OF RD W/SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-TAGAYTAT TAAL LAKE RD-K0061+563-K0061+607 | Region IV-A | Cavite 2nd DEO | On-Going | ₱39.9M | 89% | High risk93 | —-0.016 |
| 25DG0020CONST./MAINT. OF FLOOD MITIGATION STRUCT. AND DRAINAGE SYSTEMS - CONST. OF REVETMENT, CONVENTO BR. N | Region IV-A | Cavite 2nd DEO | On-Going | ₱47.7M | 56% | High risk91 | —-0.022 |
| 25DG0026CONST. OF FLOOD CONTROL STRUCTURE (REVETMENT), ALONG MARAGONDON RIVER, PHASE II, TERNATE, CAVITE | Region IV-A | Cavite 2nd DEO | On-Going | ₱38.1M | 75% | High risk88 | —-0.026 |
| 25DG0025CONST. OF FLOOD CONTROL STRUCTURE (REVETMENT) ALONG MARAGONDON RIVER, PHASE I, TERNATE, CAVITE | Region IV-A | Cavite 2nd DEO | On-Going | ₱38.1M | 80% | High risk88 | —-0.027 |
| 25DG0060REHAB./RECONST. OF RD-SECONDARY RDS - JUANITO R. REMULLA SR. RD. K0069+306-K0069+367, TERNATE, CAVIT | Region IV-A | Cavite 2nd DEO | On-Going | ₱93.8M | 0% | High risk73 | —-0.009 |
| 25DG0021REHAB./RECONST. OF RDS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE -TERNATE-NASUGBU RD - K0068+762-K00 | Region IV-A | Cavite 2nd DEO | On-Going | ₱93.6M | 61% | High risk73 | —-0.026 |
| 25DG0055REHAB./RECONS. OF RDS. - SECONDARY RDS - JUANITO R. REMULLA, SR. K0069+139 - K0069+186, TERNATE, CAV | Region IV-A | Cavite 2nd DEO | On-Going | ₱65.7M | 0% | High risk70 | —-0.012 |
| 25DG0017CONST. OF FLOOD CONTROL STRUCTURE (REVETMENT) ALONG MABACAO BR., PHASE II, MARAGONDON, CAVITE | Region IV-A | Cavite 2nd DEO | On-Going | ₱28.6M | 0% | High risk68 | —-0.000 |
| 20DG0003ROAD WIDENING - ALONG MARAGONDON-MAGALLANES-AMUYONG RD. (SO1776LZ) - K0073+167-K0073+790,K0084+016-K | Region IV-A | Cavite 2nd DEO | Completed | ₱29.4M | 100% | High risk67 | —-0.042 |
| 24DG0076CONST OF ROAD SLOPE PROTECTION STRUCTURE-TAG-TAAL LAKE RD (S01907LZ) K0062+000-K0062+099 | Region IV-A | Cavite 2nd DEO | Completed | ₱41.5M | 100% | High risk67 | —-0.043 |
| 23D00160CONSTRUCTION OF TAGAYTAY FLYOVER, BRGY. MENDEZ - CROSSING EAST JUNCTION, TAGAYTAY CITY K0061+416 - K0062+016 | Region IV-A | Region IV-A | On-Going | ₱564.3M | 68% | High risk66 | Flagged0.022 |
| 25DG0001REHAB/RECONST OF RDS W/ SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-JUANITO R. REMULLA SR. RD.-K0066+548-K0 | Region IV-A | Cavite 2nd DEO | On-Going | ₱45.6M | 31% | High risk66 | —-0.025 |
| 23D00071CONSTRUCTION OF MISSING LINKS / NEW ROADS GENERAL AGUINALDO - MAGALLANES - NASUGBU ROAD (EAST - WEST ROAD), MARAGONDON SECTION, CAVITE | Region IV-A | Region IV-A | On-Going | ₱98.4M | 60% | High risk66 | —-0.016 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23D00160CONSTRUCTION OF TAGAYTAY FLYOVER, BRGY. MENDEZ - CROSSING EAST JUNCTION, TAGAYTAY CITY K0061+416 - K0062+016 | Region IV-A | Region IV-A | On-Going | ₱564.3M | 68% | High risk66 | Flagged0.022 |
| 25DG0059REHAB./RECONST. OF RDS - SECONDARY RDS - TERNATE-NASUGBU RD. K0069+976-K0070+071 | Region IV-A | Cavite 2nd DEO | On-Going | ₱140.4M | 70% | High risk95 | Flagged0.013 |
| 25DG0056REHAB./RECONST. OF RDS. - SECONDARY RDS - JUANITO R. REMULLA, SR. RD. K0067+721-K0067+788 | Region IV-A | Cavite 2nd DEO | On-Going | ₱93.5M | 41% | High risk95 | Flagged0.010 |
| 25DG0057REHAB/RECONST OF RDS,-SECONDARY RDS-TERNATE-NASUGBU RD. K0069+926-K0069+976 | Region IV-A | Cavite 2nd DEO | On-Going | ₱74.9M | 37% | High risk94 | Flagged0.008 |
| 25DG0054REHAB/RECONST. OF RDS -SECONDARY RDS-JUANITO R. REMULLA, SR. RD. K0068+215-K0068+275, TERNATE, CAVIT | Region IV-A | Cavite 2nd DEO | On-Going | ₱65.5M | 57% | High risk94 | Flagged0.002 |
| 23D00183CONSTRUCTION OF DPWH REGION IV-A OFFICE, BARANGAY MAYAPA, CALAMBA CITY, LAGUNA (PHASE 2) | Region IV-A | Region IV-A | On-Going | ₱150.6M | 5% | High risk66 | Flagged0.002 |
| 25DG0022REHAB/RECONST OF RDS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERNATE-NASUGBU RD - K0069+645-K006 | Region IV-A | Cavite 2nd DEO | On-Going | ₱93.5M | 76% | High risk95 | Flagged0.001 |
| 25D00121CONSTRUCTION OF MISSING LINKS/ NEW ROADS GENERAL AGUINALDO-MAGALLANES-NASUGBU ROAD (EAST-WEST ROAD), MAGALLANES-GEN. AGUINALDO SECTION, PACKAGE 6, CAVITE | Region IV-A | Region IV-A | On-Going | ₱112.9M | 0% | High risk64 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 22DG0068CONST. OF ROAD SLOPE PROTECTION STRUCTURE - JUANITO R. REMULLA SR. RD., 0063+100-63+360, 63+420-63+5 | Region IV-A | Cavite 2nd DEO | Completed | ₱49M | 100% | Medium risk51 | —-0.102 |
| 52 | 22DG0004CONST OF ROAD SLOPE PROTECTION STRUCTURE-JUANITO R. REMULLA SR RD-K0066+872-K0066+930 | Region IV-A | Cavite 2nd DEO | Completed | ₱49M | 100% | Medium risk50 | —-0.102 |
| 53 | 21DG0037CONST OF MPB-CONST OF MPB (COVERED COURT),MAGALLANES ELEM SCHOOL, MAGALLANES, CAVITE | Region IV-A | Cavite 2nd DEO | Completed | ₱4.9M | 100% | Medium risk50 | —-0.103 |
| 54 | 19DG0040REHAB OF MPB (TAGAYTAY SPORTS & ACTIVITY CENTER)(TSAC)BRGY. SUNGAY WEST, TAGAYTAY CITY,CAVITE | Region IV-A | Cavite 2nd DEO | Completed | ₱9.3M | 100% | Medium risk50 | —-0.105 |
| 55 | 19DG0068CONST. OF OTHER FACILITIES - CONST. OF SKATEBOARD TRACK W/BLEACHER, TAGAYTAY CITY, CAVITE | Region IV-A | Cavite 2nd DEO | Completed | ₱14M | 100% | Medium risk50 | —-0.098 |
| 56 | 19DG0034CONST OF MPB, (OVAL BLEACHER), TAGAYTAY, CAVITE | Region IV-A | Cavite 2nd DEO | Completed | ₱9.4M | 100% | Medium risk50 | —-0.106 |
| 57 | 19DG0033CONST OF MPB (OVAL BLEACHER), TAGAYTAY CITY | Region IV-A | Cavite 2nd DEO | Completed | ₱9.4M | 100% | Medium risk50 | —-0.106 |
| 58 | 21DG0021CONST OF MPB-CONST OF MPB (BRGY HALL) BRGY PAJO, ALFONSO, CAVITE | Region IV-A | Cavite 2nd DEO | Completed | ₱4.9M | 100% | Medium risk50 | —-0.105 |
| 59 | 21DG0034CONST OF MPB-CONST OF MPB (COVERED COURT) BRGY PINAGSANJAN B, MARAGONDON, CAVITE | Region IV-A | Cavite 2nd DEO | Completed | ₱5.9M | 100% | Medium risk49 | —-0.097 |
| 60 | 21DG0035CONST OF MPB-CONST OF MPB (COVERED COURT) BRGY. STA MERCEDES, MARAGONDON, CAVITE | Region IV-A | Cavite 2nd DEO | Completed | ₱5.9M | 100% | Medium risk49 | —-0.101 |
| 61 | 25DG0018CONST. OF FLOOD CONTROL STRUCTURE, PINAGPATAYAN RIVER, BRGY. SAPANG 2, TERNATE, CAVITE | Region IV-A | Cavite 2nd DEO | On-Going | ₱47.5M | 79% | Medium risk49 | —-0.042 |
| 62 | 21DG0038CONST OF MPB CONST (COMPLETION) OF MPB (BRGY HALL), BRGY. BILOG, MUNICIPALITY OF ALFONSO, CAVITE | Region IV-A | Cavite 2nd DEO | Completed | ₱4.9M | 100% | Medium risk49 | —-0.105 |
| 63 | 21DG0036CONST OF MPB-CONST OF MPB(COVERED COURT) LUKSUHIN NHS, ALFONSO, CAVITE | Region IV-A | Cavite 2nd DEO | Completed | ₱5.9M | 100% | Medium risk49 | —-0.103 |
| 64 | 24DG0103CONC OF SITIO PALSAHINGIN, BRGY STA THERESA FMR, BRGY STA THERESA, ALFONSO, CAVITE | Region IV-A | Cavite 2nd DEO | On-Going | ₱14.9M | 97% | Medium risk48 | —-0.012 |
| 65 | 23DQ0131CONSTRUCTION OF SOLAR WATER SYSTEM, BRGY. INCHICAN, SILANG, CAVITE AND CONSTRUCTION OF SOLAR WATER SYSTEM, PHILIPPINE NATIONAL POLICE ACADEMY, CAMP GEN. MARIANO N CASTAÑEDA, BARANGAY TARTARIA, SILANG, CAVITE | Region IV-A | Cavite 3rd DEO | Completed | ₱19.2M | 100% | Medium risk48 | —-0.067 |
| 66 | 24DG0074CONST OF RD SLOPE PROTECTIONSTRUCT-TAG-TAAL LAKE RD(S01907LZ)K0058+000-K0058+036,K0058+409-K0058+460 | Region IV-A | Cavite 2nd DEO | On-Going | ₱44.4M | 97% | Medium risk48 | —-0.072 |
| 67 | 24DG0077CONST OF ROAD SLOPE PROTECTION STRUCTURE-TAG-TAAL LAKE ROAD (S01907LZ), K0062+841-K0063+028 | Region IV-A | Cavite 2nd DEO | On-Going | ₱38.6M | 97% | Medium risk47 | —-0.072 |
| 68 | 21DG0066ROAD SAFETY: STREET LIGHTNING-INST OF ST LIGHTS ALONG TAG-STA.ROSA RD FR TAG-SILANG BOUNDARY-ISAAC T | Region IV-A | Cavite 2nd DEO | Completed | ₱33.3M | 100% | Medium risk47 | —-0.102 |
| 69 | 19DG0054CONST OF CONCRETE ROAD-CONCRETING OF BANAWAN ROAD,BRGY. IRUHIN EAST-BRGY. IRUHIN CENTRAL, TAGAYTAY C | Region IV-A | Cavite 2nd DEO | Completed | ₱41.8M | 100% | Medium risk47 | —-0.104 |
| 70 | 24DG0025CONST OF ROAD SLOPE PROTECTION STRUCTURE-TAG-TALISAY ROAD K0061+000-K0061+097 | Region IV-A | Cavite 2nd DEO | Completed | ₱31.5M | 100% | Medium risk47 | —-0.108 |
| 71 | 24DG0037CONST OF ROAD SLOPE PROTECTION STRUCTURE ALONG TAG-TAAL LAKE RD K0060+539-K0060+667 | Region IV-A | Cavite 2nd DEO | On-Going | ₱39.2M | 97% | Medium risk47 | —-0.072 |
| 72 | 24DG0036CONST OF ROAD SLOPE PROTECTION STRUCTURE-ALONG TAG-TAAL LAKE ROAD-K0058+470-K0058+549 | Region IV-A | Cavite 2nd DEO | On-Going | ₱39.1M | 97% | Medium risk47 | —-0.072 |
| 73 | 25DG0036INST./APPLICATION OF ROAD SAFETY FACILITIES(ROADWAY LIGHTING) ALONG TAG.-MANILA VIA SILANG RD - K005 | Region IV-A | Cavite 2nd DEO | On-Going | ₱29.8M | 100% | Medium risk47 | —-0.078 |
| 74 | 24DG0033CONST OF ROAD SLOPE PROTECTION STRUCTURE-TAG TAAL LAKE RD K0059+208-K0059+268,K0059+467-K0059+570 | Region IV-A | Cavite 2nd DEO | Completed | ₱40.3M | 100% | Medium risk47 | —-0.107 |
| 75 | 24DG0032CONST OF ROAD SLOPE PROTECTION STRUCTURE-TAG-TAAL LAKE ROAD-K0059+570-K0059+622,K0059+629-K0059+649 | Region IV-A | Cavite 2nd DEO | Completed | ₱36.9M | 100% | Medium risk47 | —-0.108 |