73 projects on file, including joint ventures this contractor is part of.
Total projects
73
Total budget
₱606.8M
Average progress
97.2%
Completion rate
79.5%
Average risk score
39.4
Medium risk on average, out of 100
Flagged as unusual
3
4.1% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VII | 73 | ₱606.8M | 39.4 | 3 | 97.2% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 58 | ₱264.1M | 35.0 | 0 | 97.8% |
| Roads | 6 | ₱39.4M | 44.3 | 0 | 100.0% |
| OTHER | 2 | ₱52.2M | 75.7 | 2 | 75.4% |
| Flood Control and Drainage | 2 | ₱91.7M | 50.2 | 0 | 100.0% |
| Bridges | 2 | ₱9.7M | 48.3 | 0 | 94.0% |
| GAA 2025 OO-2 | 1 | ₱135M | 93.0 | 0 | 98.9% |
| GAA 2025 SSP | 1 | ₱4.8M | 90.5 | 1 | 84.4% |
| Water Provision and Storage | 1 | ₱9.7M | 47.7 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25HN0104OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION RIVERBANK FACILITIES ALONG JAGOBIAO CREEK, PACKAGE I, BARANGAY SACSAC, CONSOLACION, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱135M | 99% | High risk93 | —-0.006 |
| 25H00062CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BAGASAWE, TUBURAN, CEBU | Region VII | Region VII | On-Going | ₱4.8M | 84% | High risk90 | Flagged0.012 |
| 24HN0229CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - IMPROVEMENT OF ROAD, BARANGAY TAYUD, CONSOLACION, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱47.2M | 82% | High risk87 | Flagged0.053 |
| 24HN0098CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BUAGSONG, CORDOVA, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱4.9M | 69% | High risk64 | Flagged0.016 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24HN0229CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - IMPROVEMENT OF ROAD, BARANGAY TAYUD, CONSOLACION, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱47.2M | 82% | High risk87 | Flagged0.053 |
| 24HN0098CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BUAGSONG, CORDOVA, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱4.9M | 69% | High risk64 | Flagged0.016 |
| 25H00062CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BAGASAWE, TUBURAN, CEBU | Region VII | Region VII | On-Going | ₱4.8M | 84% | High risk90 | Flagged0.012 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 22HD0026CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE 2), STA. FE, BANTAYAN, CEBU | Region VII | Cebu 4th DEO | Completed | ₱5M | 100% | Medium risk48 | —-0.093 |
| 27 | 23HN0032CSSP: BIP - MULTIPURPOSE/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (BARANGAY GYM) AT BARANGAY CASILI, CONSOLACION, CEBU | Region VII | Cebu 6th DEO | Completed | ₱4.9M | 100% | Medium risk48 | —-0.095 |
| 28 | 24HN0125CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TILHAONG, CONSOLACION, CEBU PHASE II | Region VII | Cebu 6th DEO | Completed | ₱9.9M | 100% | Medium risk48 | —-0.095 |
| 29 | 23HD0011CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY KANTUBAON, TABUELAN, CEBU | Region VII | Cebu 4th DEO | Completed | ₱5M | 100% | Medium risk48 | —-0.094 |
| 30 | 22HD0003CONSTRUCTION OF MULTI-PURPOSE BUILDING, SITIO CANAAN, BARANGAY BONGON, TABUELAN, CEBU | Region VII | Cebu 4th DEO | Completed | ₱5M | 100% | Medium risk48 | —-0.094 |
| 31 | 23HD0041CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TABUNOK, TABUNOK, TABUELAN, CEBU | Region VII | Cebu 4th DEO | Completed | ₱5M | 100% | Medium risk48 | —-0.095 |
| 32 | 23HF0073CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY LUSONG, TUBURAN, CEBU | Region VII | Cebu 3rd DEO | Completed | ₱9.7M | 100% | Medium risk48 | —-0.055 |
| 33 | 24HN0014CSSP: BASIC INFRASTRUTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING AT CORDOVA NATIONAL HIGH SCHOOL, CORDOVA, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱5M | 100% | Medium risk47 | —-0.051 |
| 34 | 25HN0034SSP: BASIC INFRASTRUTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF DRAINAGE STRUCTURE, BARANGAY SACSAC, CONSOLACION, CEBU | Region VII | Cebu 6th DEO | Completed | ₱4.9M | 100% | Medium risk47 | —-0.078 |
| 35 | 25HN0061SSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY GILUTONGAN, CORDOVA, CEBU | Region VII | Cebu 6th DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.096 |
| 36 | 24HD0048ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD, BARANGAY POOC, SANTA FE, CEBU | Region VII | Cebu 4th DEO | Completed | ₱5M | 100% | Medium risk46 | —-0.095 |
| 37 | 24H00072CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, BARANGAY STO. NIÑO, TUBURAN, CEBU | Region VII | Region VII | Completed | ₱9.9M | 100% | Medium risk46 | —-0.097 |
| 38 | 25HN0092SSP: SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - REHABILITATION OF ROAD WITH DRAINAGE FACILITIES AT BARANGAY TILHAONG, CONSOLACION, CEBU | Region VII | Cebu 6th DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.098 |
| 39 | 24HN0231CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP)- MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES- CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT) PHASE 2, BARANGAY TILHAONG, CONSOLACION, CEBU | Region VII | Cebu 6th DEO | On-Going | ₱4.8M | 100% | Medium risk46 | —-0.018 |
| 40 | 24HN0167CONSTRUCTION OF 4 STOREY 8-CLASSROOM (PHASE I) SCHOOL BUILDING IN BAGONG LIPUNAN ELEMENTARY SCHOOL, BARANGAY PULPOGAN, CONSOLACION, CEBU | Region VII | Cebu 6th DEO | Completed | ₱14.9M | 100% | Medium risk45 | —-0.053 |
| 41 | 23HD0021ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY MAYA, DAANBANTAYAN, CEBU | Region VII | Cebu 4th DEO | Completed | ₱5M | 100% | Medium risk45 | —-0.093 |
| 42 | 24HD0120CONSTRUCTION OF 2-STOREY, 4-CLASSROOM SCHOOL BUILDING IN HILOTONGAN INTEGRATED SCHOOL, BANTAYAN, CEBU | Region VII | Cebu 4th DEO | On-Going | ₱9.9M | 87% | Medium risk45 | —-0.002 |
| 43 | 24HD0121CONSTRUCTION OF 2-STOREY, 4-CLASSROOM SCHOOL BUILDING IN OKOY ELEMENTARY SCHOOL, SANTA FE, CEBU | Region VII | Cebu 4th DEO | Completed | ₱10M | 100% | Medium risk44 | —-0.053 |
| 44 | 23HD0092MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TACUP, SAN REMIGIO, CEBU | Region VII | Cebu 4th DEO | Completed | ₱4.8M | 100% | Medium risk44 | —-0.051 |
| 45 | 23HD0094MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING, CEBU TECHNOLOGICAL UNIVERSITY, TABUELAN, CEBU | Region VII | Cebu 4th DEO | Completed | ₱4.8M | 100% | Medium risk44 | —-0.051 |
| 46 | 20HF0105CONCRETING OF BRGY. SAN ROQUE TO BRGY. BOG-O FMR, BRGY. SAN ROQUE AND BRGY. BOG-O, ASTURIAS, CEBU | Region VII | Cebu 3rd DEO | Completed | ₱9.9M | 100% | Medium risk42 | —-0.045 |
| 47 | 23HF0108CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ROAD IMPROVEMENT BRGY. CARMEN TO BRGY. CAPTAIN CLAUDIO, TOLEDO, CEBU | Region VII | Cebu 3rd DEO | Completed | ₱4.8M | 100% | Medium risk42 | —-0.045 |
| 48 | 24HD0021CONSTRUCTION (COMPLETION) OF MULTIPURPOSE BUILDING, BARANGAY KANGWAYAN, MADRIDEJOS, CEBU | Region VII | Cebu 4th DEO | Completed | ₱3M | 100% | Low risk27 | —-0.093 |
| 49 | 23HD0042CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SUBA, BANTAYAN, CEBU | Region VII | Cebu 4th DEO | Completed | ₱3.5M | 100% | Low risk26 | —-0.093 |
| 50 | 23HD0047CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY PATAO, BANTAYAN, CEBU | Region VII | Cebu 4th DEO | Completed | ₱3M | 100% | Low risk26 | —-0.090 |