Opening the dossier…
Opening the dossier…
Contractor dossier
18 projects on file, including joint ventures this contractor is part of.
Total projects
18
Total budget
₱63.4M
Average progress
100.0%
Completion rate
100.0%
Average risk score
13.4
Low risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XII | 18 | ₱63.4M | 13.4 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 15 | ₱47.5M | 8.0 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱4.9M | 88.1 | 0 | 100.0% |
| Flood Control and Drainage | 1 | ₱9.8M | 24.0 | 0 | 100.0% |
| Water Provision and Storage | 1 | ₱1.2M | 9.5 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25MG0055CONSTRUCTION OF TWO (2) STOREY MULTI-PURPOSE BUILDING, BRGY. SAJANEBA, STO. NIÑO, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱4.9M | 100% | High risk88 | —-0.019 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25MG0055CONSTRUCTION OF TWO (2) STOREY MULTI-PURPOSE BUILDING, BRGY. SAJANEBA, STO. NIÑO, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱4.9M | 100% | High risk88 | —-0.019 |
| 2 | 17ME0007CONST. OF GYMNASIUM/COVERED COURT, BRGY. KIHAN, MALAPATAN, SARANGANI PROVINCE | Region XII | Sarangani DEO | Completed | ₱5.6M | 100% | Medium risk34 | —-0.052 |
| 3 | 18ME0020CONST./REHAB. OF FLOOD CONTROL MITIGATION FACILITIES ALONG PRINCIPAL RIVER (BUAYAN RIVER), ALABEL, SARANGANI PROVINCE | Region XII | Sarangani DEO | Completed | ₱9.8M | 100% | Low risk24 | —-0.067 |
| 4 | 24MG0088CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. LIBAS, TANTANGAN, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱4.9M | 100% | Low risk20 | —-0.087 |
| 5 | 16ME0175CONST. OF (2) UNITS, (1) STOREY, (4) CL SCHOOL BLDG, SAN JOSE ES, GLAN, SARANGANI PROVINCE | Region XII | Sarangani DEO | Completed | ₱8.5M | 100% | Low risk15 | —-0.009 |
| 6 | 22ME0158CLUSTER VII: 1. CONST/REHAB. OF WATER SUPPLY/SEPTAGE & SEWERAGE/RAINWATER COLLECTOR SYSTEM F. K CONSTANTINO ES; 2 CONST/REHAB. OF WATER SUPPLY/SEPTAGE & SEWERAGE/RAINWATER COLLECTOR SYSTEM BRGY. KINABALAN (BRGY. HALL), KINABALAN IS; 3. CONST/REHAB. OF WAT | Region XII | Sarangani DEO | Completed | ₱1.2M | 100% | Low risk10 | —-0.046 |
| 7 | 18MB0108CONSTRUCTION OF A MULTI-PURPOSE BUILDING, (COVERED COURT), PUROK EMB HOMES, BARANGAY LABANGAL, GENERAL SANTOS CITY | Region XII | South Cotabato 1st DEO | Completed | ₱3M | 100% | Low risk6 | —-0.080 |
| 8 | 20MB0076CONSTRUCTION OF MULTI-PURPOSE BUILDING, PUROK BLAGAN, SAN JOSE, GENERAL SANTOS CITY | Region XII | South Cotabato 1st DEO | Completed | ₱2.9M | 100% | Low risk6 | —-0.080 |
| 9 | 19MB0090CONSTRUCTION OF MPB (COVERED COURT), PUROK DOÑA SOLEDAD, PHASE 1 WEST, BRGY. LABANGAL, GEN. SANTOS CITY | Region XII | South Cotabato 1st DEO | Completed | ₱2.9M | 100% | Low risk5 | —-0.076 |
| 10 | 20MG0003CONSTRUCTION OF MULTI-PURPOSE BUILDING, SITIO UPPER MALIGAYA, BRGY. POBLACION, TANTANGAN, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱2.5M | 100% | Low risk5 | —-0.086 |
| 11 | 20MG0092CONSTRUCTION OF MULTI-PURPOSE BUILDING (NEW GYM), DUMADALIG ELEMENTARY SCHOOL, DUMADALIG, TANTANGAN, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱2.4M | 100% | Low risk5 | —-0.086 |
| 12 | 19MG0085CONSTRUCTION OF MULTI-PURPOSE BUILDING (NEW GYM) AGAN NORTH, BRGY. MORALES, KORONADAL CITY, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱2.5M | 100% | Low risk5 | —-0.085 |
| 13 | 21MG0119CONSTRUCTION/REHABILITATION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY MANGILALA, TANTANGAN, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱1.6M | 100% | Low risk5 | —-0.086 |
| 14 | 21MG0057CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY SAN ISIDRO, KORONADAL CTIY, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱1.4M | 100% | Low risk3 | —-0.086 |
| 15 | 18MG0018CONSTRUCTION OF BARANGAY HALL, BRGY. LIBAS, TANTANGAN, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱1.3M | 100% | Low risk3 | —-0.087 |
| 16 | 18MG0003CONSTRUCTION OF NEW BARANGAY HALL, BRGY. CINCO, BANGA, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱1.4M | 100% | Low risk3 | —-0.087 |
| 17 | 17MG0143CONSTRUCTION OF 1 UNIT-1STY 3CL AT MANGGA ES, KORONADAL CITY | Region XII | South Cotabato 2nd DEO | Completed | ₱3.9M | 100% | Low risk3 | —-0.017 |
| 18 | 17MG0137CONSTRUCTION OF 1 UNIT-1STY 2CL AT MANGGA ES, KORONADAL CITY | Region XII | South Cotabato 2nd DEO | Completed | ₱2.7M | 100% | Low risk3 | —-0.017 |