Contractor dossier
82 projects on file, including joint ventures this contractor is part of.
Total projects
82
Total budget
₱2.7B
Average progress
99.7%
Completion rate
96.3%
Average risk score
48.9
Medium risk on average, out of 100
Flagged as unusual
2
2.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VII | 82 | ₱2.7B | 48.9 | 2 | 99.7% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 65 | ₱2.3B | 46.6 | 0 | 99.9% |
| Buildings and Facilities | 6 | ₱158.8M | 37.5 | 0 | 100.0% |
| Flood Control and Drainage | 5 | ₱140.1M | 60.5 | 0 | 100.0% |
| GAA 2025 OO-1 | 3 | ₱90.8M | 91.8 | 1 | 95.2% |
| OTHER | 3 | ₱30.4M | 57.9 | 1 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25HB0013ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS JCT (LIR) CARMEN-SAGBAYAN-BACANI RD - K0161 + 170 - K0161 + 407, K0161 + 416.50 - K0161 + 734, K0161 + 743 - K0162 + 3 | Region VII | Bohol 3rd DEO | On-Going | ₱57.8M | 86% | High risk94 | Flagged0.004 |
| 25HC0030ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM- CONSTRUCTION/UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS- SECONDARY ROADS- THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL RD. K0058+(-060)-K | Region VII | Bohol 2nd DEO | On-Going | ₱19.5M | 100% | High risk91 | —-0.003 |
| 25HC0009ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- ASSET PRESERVATION- REHABILITATION/RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS- SECONDARY ROADS- TAGBILARAN NORTH RD (TAGBILARAN-JETAFE SECT)- K0063+000-K0063+691, CLARIN, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱13.4M | 100% | High risk91 | —-0.032 |
| 17HA0041CONSTRUCTION OF CALUNASAN RIVER FLOOD CONTROL, CALAPE, BOHOL, STA. 1+560-STA. 1+832.350 AND STA. 2+ 020-STA. 2+273.060-PROJECT COMPONENT ID-P00121489VS-CW1 | Region VII | Bohol 1st DEO | Completed | ₱22.7M | 100% | High risk63 | —-0.050 |
| 17HA0038CONSTRUCTION OF CAHAYAG RIVER CONTROL, TUBIGON, BOHOL-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, TU | Region VII | Bohol 1st DEO | Completed | ₱18.2M | 100% | High risk63 | —-0.050 |
| 17HA0020MFO 2-FLOOD MANAGEMENT SERVICES-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE | Region VII | Bohol 1st DEO | Completed | ₱27.5M | 100% | High risk63 | —-0.050 |
| 17HA0039CONSTRUCTION OF LIBORON RIVER FLOOD CONTROL, CALAPE, BOHOL. STA. 1+065-STA. 1+700.00 PROJECT COMPONE | Region VII | Bohol 1st DEO | Completed | ₱22.7M | 100% | High risk63 | —-0.050 |
| 20HB0059ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS, JCT.(LIR) CARMEN-SAGBAYAN-BACANI RD. KO163+ | Region VII | Bohol 3rd DEO | Completed | ₱16.5M | 100% | High risk61 | —-0.031 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 19HB0217CONCRETING OF BRGY. TAWID - BRGY. BACONG FMR, BRGY. TAWID AND BRGY. BACONG, ANDA, BOHOL, STA. 0+000 - STA. 0+270 | Region VII | Bohol 3rd DEO | Completed | ₱4.4M | 100% | Medium risk52 | Flagged0.012 |
| 25HB0013ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS JCT (LIR) CARMEN-SAGBAYAN-BACANI RD - K0161 + 170 - K0161 + 407, K0161 + 416.50 - K0161 + 734, K0161 + 743 - K0162 + 3 | Region VII | Bohol 3rd DEO | On-Going | ₱57.8M | 86% | High risk94 | Flagged0.004 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 24HB0013ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS - JCT (LIR) CARMEN-SAGBAYAN-BACANI RD - K0171 + 640.00 - K0173 + 641.00 | Region VII | Bohol 3rd DEO | Completed | ₱85.1M | 100% | Medium risk52 | —-0.086 |
| 27 | 23HA0059CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - DEL CARMEN NORTE-DOROL-SAN ISIDRO (BALILIHAN) ROAD LEADING TO CAMOGAO FALLS, BALILIHAN, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱55.1M | 100% | Medium risk52 | —-0.089 |
| 28 | 17HC0001ASSET PRESERVATION OF NATIONAL ROADS-REHAB./RECONST. OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE AT JCT. (LIR) BUENAVISTA, CARMEN - DANAO - GETAFE ROAD, BUENAVISTA, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱12.7M | 100% | Medium risk52 | —-0.063 |
| 29 | 16HC0085ROAD UPGRADING (UNPAVED TO PAVED) CONCRETING OF SAGBAYAN-DANAO ROAD, KO091+892 - KO092+250, DANAO, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱9.7M | 100% | Medium risk51 | —-0.064 |
| 30 | 18HA0061CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS-CATIGBIAN-CANMANO ROAD(CATIGBIAN SECTION) LEADING TO SAGBAYAN PEAK, CHOCOLATE HILLS AND DANAO ADVENTURE PARK, CATIGBIAN, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱47M | 100% | Medium risk50 | —-0.094 |
| 31 | 23HC0052ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS- FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS -CONSTRUCTION OF BONBON SEAWALL, PHASE II, CLARIN, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱49M | 100% | Medium risk49 | —-0.075 |
| 32 | 24HC0021ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- NETWORK DEVELOPMENT PROGRAM- ROAD WIDENING- SECONDARY ROADS -TAGBILARAN NORTH ROAD (TAGBILARAN-JETAFE SECT) - K0075+880-K0076+941, INABANGA, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱47.4M | 100% | Medium risk49 | —-0.094 |
| 33 | 23HC0020CONVERGENCE AND SPECIAL SUPPORT PROGRAM- SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD, NABUAD TO CAMBITOON, | Region VII | Bohol 2nd DEO | Completed | ₱48.2M | 100% | Medium risk48 | —-0.094 |
| 34 | 18HA0097CONCRETING OF ROAD FROM TRIPLE UNION-MAITUM-CANG-IRAS ROAD, STA.00+000-STA.05+000, CATIGBIAN, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱47.3M | 100% | Medium risk48 | —-0.094 |
| 35 | 19H00026CONSTRUCTION OF EVACUATION CENTER BUILDING, BRGY. GOTOZON, LOBOC, BOHOL | Region VII | Region VII | Completed | ₱34.7M | 100% | Medium risk48 | —-0.087 |
| 36 | 22HA0037OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS - TAGBILARAN CITY - CORELLA - SIKATUNA - LOBOC RD - K0012+000 - K0013+957 | Region VII | Bohol 1st DEO | Completed | ₱38.2M | 100% | Medium risk47 | —-0.094 |
| 37 | 22HA0039CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - TERTIARY ROADS - JCT (TNR) CORTES-BALILIHAN-CATIGBIAN-MACAAS RD - K0013+000 - K0014+450 | Region VII | Bohol 1st DEO | Completed | ₱16.4M | 100% | Medium risk46 | —-0.087 |
| 38 | 20HA0094CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - TAGBILARAN NORTH RD (TAGBILARAN-JETAFE SECT.) K0001+619 - K0003+000 TAGBILARAN CITY, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱26M | 100% | Medium risk46 | —-0.095 |
| 39 | 19HA0166CONSTRUCTION (COMPLETION) OF ROAD ALONG TEACHER'S VILLAGE, SAN ISIDRO, TAGBILARAN CITY, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱23.3M | 100% | Medium risk46 | —-0.096 |
| 40 | 18HA0145CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS - ACCESS ROADS LEADING TO MARIBOJOC PORT, MARIBOJOC, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱23.4M | 100% | Medium risk46 | —-0.096 |
| 41 | 20HA0008CONSTRUCTON/IMPROVEMENT OF ACCESS ROADS LEDING TO DECLARED TOURISM DESTINATIONS - CATIGBIAN-CANMANO ROAD (CATIGBIAN SECTION) LEADING TO SAGBAYAN PEAK, CHOCOLATE HILLS AND DANAO ADVENTURE PARK, CATIGBIAN, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱19M | 100% | Medium risk46 | —-0.096 |
| 42 | 18HC0016CONST. OF DPWH BOHOL 2ND DEO BUILDING, BOOD, UBAY, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱33.8M | 100% | Medium risk46 | —-0.088 |
| 43 | 18HB0055CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INUSTRIES AND ECONOMIC ZONES, HINAWANA (LOAY)-CONCEPTION JCT.(SIKATUNA-LOBOC) ROAD IN SUPPORT OF THE FURNITURE AND GARMENTS INDUSTRY, LOBOC, BOHOL | Region VII | Bohol 3rd DEO | Completed | ₱17.8M | 100% | Medium risk46 | —-0.095 |
| 44 | 23HA0040OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS - TAGBILARAN CITY-CORELLA-SIKATUNA-LOBOC RD - K0010+298 - K0010+500, K0014+140 - K0014+500 | Region VII | Bohol 1st DEO | Completed | ₱11.8M | 100% | Medium risk45 | —-0.096 |
| 45 | 21HA0011REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - JCT. (TNR) CORTES - BALILIHAN - CATIGBIAN - MACAAS RD - K0035+000 - K0035+285 | Region VII | Bohol 1st DEO | Completed | ₱9.9M | 100% | Medium risk45 | —-0.097 |
| 46 | 19HA0068CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - CATIGBIAN-CANMANO ROAD (CATIGBIAN SECTION) LEADING TO SAGBAYAN PEAK, CHOCOLATE HILLS AND DANAO ADVENTURE PARK, CATIGBIAN, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱9.4M | 100% | Medium risk45 | —-0.097 |
| 47 | 20HC0014OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM -NETWORK DEVELOPMENT PROGRAM- OFF-CARRIAGEWAY IMPROVEMENT -SECONDARY ROADS -TAGBILARAN NORTH ROAD (TAGBILARAN-JETAFE SECT) -K0062+340 -K0062+436, K0067+616 - K0070+900, CLARIN AND INABANGA, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱28.5M | 100% | Medium risk45 | —-0.096 |
| 48 | 24HC0042SPECIAL ROAD FUND -MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239: REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED ROADS ALONG TAGBILARAN NORTH RD (TAGBILRAN-JETAFE SECT)- K0062+342-K0062+710, CLARIN, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱30.9M | 100% | Medium risk45 | —-0.095 |
| 49 | 18HA0137CONSTRUCTION OF 2 UNITS 3-STOREY 3 LABORATORY BUILDING, CALAPE NATIONAL HIGH SCHOOL, CALAPE, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱31M | 100% | Medium risk45 | —-0.046 |
| 50 | 19HC0064001:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT-TERTIARY ROAD AT SAGBAYAN-DANAO-RD - K0077+000 - K0077+700, K0077+700 - K0078+000, K0079+588 - K0081+000, K0082+000 - K0084+174, SAGBAYAN, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱46.5M | 100% | Medium risk45 | —-0.095 |