Contractor dossier
140 projects on file, including joint ventures this contractor is part of.
Total projects
140
Total budget
₱5.8B
Average progress
98.6%
Completion rate
92.9%
Average risk score
35.9
Medium risk on average, out of 100
Flagged as unusual
7
5.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-B | 140 | ₱5.8B | 35.9 | 7 | 98.6% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 59 | ₱278.4M | 20.4 | 0 | 100.0% |
| Roads | 42 | ₱2.2B | 43.3 | 0 | 99.1% |
| Flood Control and Drainage | 14 | ₱1.9B | 57.0 | 2 | 98.6% |
| Bridges | 14 | ₱829.7M | 47.0 | 1 | 96.0% |
| Bridges, Roads | 4 | ₱295.8M | 49.9 | 1 | 83.0% |
| Water Provision and Storage | 4 | ₱22.8M | 33.3 | 0 | 100.0% |
| OTHER | 2 | ₱289.5M | 64.4 | 2 | 100.0% |
| GAA 2025 OO-1 | 1 | ₱36.1M | 90.2 | 1 | 90.2% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25EE0048WIDENING OF PERMANENT BRIDGES-LINAPAWAN BRIDGE (B00214PW) ALONG PUERTO PRINCESA NORTH ROAD, ROXAS, PALAWAN | Region IV-B | Palawan 1st DEO | On-Going | ₱36.1M | 90% | High risk90 | Flagged0.007 |
| 23E00095SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF RIZAL AVENUE EXTENSION BOARDWALK, BRGY. BANCAO-BANCAO, PTO. PRINCESA CITY, | Region IV-B | Region IV-B | On-Going | ₱186.1M | 32% | High risk67 | Flagged0.024 |
| 25E00131CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ABORLAN RIVER WATERWAY, PTO. PRINCESA SOUTH ROAD, DOWNSTREAM RIGHTSIDE, ABORLAN, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱229.9M | 85% | High risk67 | Flagged0.011 |
| 25E00130CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ABORLAN RIVER WATERWAY, PTO. PRINCESA SOUTH ROAD, UPSTREAM LEFTSIDE, ABORLAN, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱229.9M | 95% | High risk67 | Flagged0.008 |
| 24E00133SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ABORLAN RIVER WATERWAY,PTO. PRINCESA SOUTH ROAD (DOWNSTREAM LEFTYSIDE), ABORLAN, PALAWAN | Region IV-B | Region IV-B | Completed | ₱154.4M | 100% | High risk66 | —-0.033 |
| 24E00180SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF RIVER BANK PROTECTION STRUCTURE ALONG IRAWAN RIVER UPSTREAM, BRGY. IRAWAN, PTO. PRINCESA CITY, PALA | Region IV-B | Region IV-B | Completed | ₱194.9M | 100% | High risk66 | —-0.025 |
| 24E00172SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITUIES- CONST. OF PUNANG RIVER FLOOD CONTROL STRUCTURE, SOFRONIO, ESPANOLA, PALAWAN | Region IV-B | Region IV-B | Completed | ₱193M | 100% | High risk66 | —-0.021 |
| 23E00187SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF FLOOD CONTROL STRUCTURE ALONG IRAAN RIVER UPSTREAM, BRGY. IRAAN, ABORLAN, PALAWAN | Region IV-B | Region IV-B | Completed | ₱212.3M | 100% | High risk65 | —-0.020 |
| 23E00188SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF RIVER BANK PROTECTION STRUCTURES ALONG IRAWAN RIVER DOWNSTREAM (R/S), BRGY. IRAWAN, PTO. PRINCESA CITY, PALAW | Region IV-B | Region IV-B | Completed | ₱212.3M | 100% | High risk65 | —-0.023 |
| 20E00023CONST. OF MISSING LINKS/NEW ROADS, PALAWAN CIRCUMFERENTIAL ROAD (LATUD-CANIPAAN SECTION), PACKAGE D, STA. 304+565.00-STA. 313+166.00, PALAWAN | Region IV-B | Region IV-B | Completed | ₱144.7M | 100% | High risk65 | Flagged0.028 |
| 20E00024CONST. OF MISSING LINKS/NEW ROADS, PALAWAN CIRCUMFERENTIAL ROAD (LATUD-CANIPAAN SECTION), PACKAGE E, ROAD 1: STA. 294+850-STA. 295+776; ROAD 2: STA. 294+864-STA. 303+246 & ROAD 3: STA. 303+334-STA. 304+565; BRIDGE 1: STA. 295+776-STA. 295+864 & BRIDGE 2: | Region IV-B | Region IV-B | Completed | ₱144.7M | 100% | High risk64 | Flagged0.025 |
| 23E00076SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONSTRUCTION OF MARABAHAY SHORE PROTECTION STRUCTURE/CAUSEWAY, BATARAZA, PALAWAN | Region IV-B | Region IV-B | Completed | ₱193M | 100% | High risk63 | —-0.013 |
| 23E00090WIDENING OF PERMANENT BRIDGES- BABUYAN BRIDGE (B00095PW) ALONG PUERTO PRINCESA NORTH ROAD, PALAWAN | Region IV-B | Region IV-B | Completed | ₱159.2M | 100% | High risk62 | —-0.012 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 20E00023CONST. OF MISSING LINKS/NEW ROADS, PALAWAN CIRCUMFERENTIAL ROAD (LATUD-CANIPAAN SECTION), PACKAGE D, STA. 304+565.00-STA. 313+166.00, PALAWAN | Region IV-B | Region IV-B | Completed | ₱144.7M | 100% | High risk65 | Flagged0.028 |
| 20E00024CONST. OF MISSING LINKS/NEW ROADS, PALAWAN CIRCUMFERENTIAL ROAD (LATUD-CANIPAAN SECTION), PACKAGE E, ROAD 1: STA. 294+850-STA. 295+776; ROAD 2: STA. 294+864-STA. 303+246 & ROAD 3: STA. 303+334-STA. 304+565; BRIDGE 1: STA. 295+776-STA. 295+864 & BRIDGE 2: | Region IV-B | Region IV-B | Completed | ₱144.7M | 100% | High risk64 | Flagged0.025 |
| 23E00095SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF RIZAL AVENUE EXTENSION BOARDWALK, BRGY. BANCAO-BANCAO, PTO. PRINCESA CITY, | Region IV-B | Region IV-B | On-Going | ₱186.1M | 32% | High risk67 | Flagged0.024 |
| 25E00131CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ABORLAN RIVER WATERWAY, PTO. PRINCESA SOUTH ROAD, DOWNSTREAM RIGHTSIDE, ABORLAN, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱229.9M | 85% | High risk67 | Flagged0.011 |
| 25E00130CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ABORLAN RIVER WATERWAY, PTO. PRINCESA SOUTH ROAD, UPSTREAM LEFTSIDE, ABORLAN, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱229.9M | 95% | High risk67 | Flagged0.008 |
| 25EE0048WIDENING OF PERMANENT BRIDGES-LINAPAWAN BRIDGE (B00214PW) ALONG PUERTO PRINCESA NORTH ROAD, ROXAS, PALAWAN | Region IV-B | Palawan 1st DEO | On-Going | ₱36.1M | 90% | High risk90 | Flagged0.007 |
| 25E00136COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF RIZAL AVENUE EXTENSION BOARDWALK, PHASE II, BRGY. BANCAO-BANCAO, PTO. PRINCESA CITY, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱92.3M | 44% | Medium risk57 | Flagged0.004 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 76 | 21EE0078CONSTRUCTION/IMPROVEMENT OF NEW AGUTAYA-ALIMANGUAN TOURISM ROAD LEADING TO SAN VICENET LONG BEACH SAN VICENTE, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱7.3M | 100% | Medium risk38 | —-0.070 |
| 77 | 22EE0049CONSTRUCTION/IMPROVEMENT OF MAMPIO ROAD FROM SEAPORT TO CAGAYANCILO POBLACION BRGY. MAMPIO,CAGAYANCILLO,PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱9.6M | 100% | Medium risk38 | —-0.089 |
| 78 | 21EE0099CONSTRUCTION OF MULTI-PURPOSE BUILDING (TEC-VOC CENTER AND CAMPUS DORMITORY ) PALAWAN STATE UNIVERSITY SAN VICENTE CAMPUS, SAN VICENTE , PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱19.6M | 100% | Medium risk38 | —-0.064 |
| 79 | 24EF0070CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (MUNICIPAL LEGISLATIVE BUILDING), BRGY. PUNTA BAJA, JOSE P. RIZAL, PALAWAN | Region IV-B | Palawan 2nd DEO | Completed | ₱7.9M | 100% | Medium risk36 | —-0.061 |
| 80 | 18EE0044CONSTRUCTION OF MULTI-PURPOSE BUILDING, BGY. POBLACION, ARACELI, PALAWAN ( LGU COMPOUND ) | Region IV-B | Palawan 1st DEO | Completed | ₱6.8M | 100% | Medium risk35 | —-0.075 |
| 81 | 18EE0045CONSTRUCTION OF MULTI-PURPOSE BUILDING, BGY. POBLACION, TAYTAY, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱6.8M | 100% | Medium risk35 | —-0.069 |
| 82 | 22EE0017CONSTRUCTION OF TWO-STOREY MULTI-PURPOSE BUILDING BARANGAY PASADENA EL NIDO PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱4.9M | 100% | Medium risk35 | —-0.070 |
| 83 | 22EE0018CONSTRUCTION OF TWO-STOREY MULTI-PURPOSE BUILDINGBARANGAY LUNGSOD, CUYO, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱4.8M | 100% | Medium risk35 | —-0.082 |
| 84 | 18EE0185CONSTRUCTION OF 2-STOREY 4 CLASSROOM (2 UNITS ICT LABORATORY BUILDING) DANAWAN NATIONAL HIGH SCHOOL, MAGSAYSAY, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱10.2M | 100% | Medium risk35 | —-0.044 |
| 85 | 23EG0002CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BANCAO-BANCAO, PUERTO PRINCESA CITY, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱5.4M | 100% | Medium risk33 | —-0.068 |
| 86 | 23EG0005CONSTRUCTION OF LANGOGAN PEDESTRIAN HANGING BRIDGE, BARANGAY LANGOGAN, PUERTO PRINCESA CITY, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱6.4M | 100% | Medium risk33 | —-0.069 |
| 87 | 18EE0155CONSTRUCTION OF 2-STOREY 4 CLASSROOM (2 UNITS ICT LABORATORY BUILDING) BAROTUAN NATIONAL HIGH SCHOOL, EL NIDO (BACUIT), PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱9.2M | 100% | Medium risk31 | —-0.031 |
| 88 | 18EE0168CONSTRUCTION OF 2-STOREY 4 CLASSROOM (2 UNITS ICT LABORATORY BUILDING) SANDOVAL NATIONAL HIGH SCHOOL, TAYTAY, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱9.4M | 100% | Medium risk31 | —-0.032 |
| 89 | 18EE0220CONSTRUCTION OF TWO STOREY 4 CL (2 REGULAR WORKSHOPS) BATO NATIONAL HIGHSCHOOL TAYTAY, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱9M | 100% | Medium risk30 | —-0.030 |
| 90 | 18EG0128CONSTRUCTION OF 2STY12CL, PALAWAN NATIONAL SCHOOL, PUERTO PRINCESA CITY, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱22.2M | 100% | Medium risk30 | —-0.022 |
| 91 | 18EE0244CONSTRUCTION OF 3 STOREY 6 CL (3 REGULAR WORKSHOP) CARURAY NATIONAL HIGH SCHOOL, SAN VICENTE, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱13.5M | 100% | Low risk30 | —-0.022 |
| 92 | 18EE0157CONSTRUCTION OF 2-STOREY 4 CLASSROOM (2 UNITS ICT LABORATORY BUILDING) CENTRAL TAYTAY SENIOR HIGH SCHOOL, TAYTAY, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱9M | 100% | Low risk30 | —-0.031 |
| 93 | 17EE0026RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES LABANGAN BR. 1 (B00033CR) ALONG CORON-BUSUANGA RD.CORON,PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱2.3M | 100% | Low risk29 | —-0.018 |
| 94 | 18EE0158CONSTRUCTION OF 2-STOREY 4 CLASSROOM (2 UNITS ICT LABORATORY BUILDING) MAGARA SCHOOL FOR PHILIPPINE CRAFTSMEN, ROXAS, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱9M | 100% | Low risk28 | —-0.029 |
| 95 | 17EE0045CLUSTER 1-CONSTRUCTION OF RAINWATER COLLECTION SYSTEMS(RWCS); 1.PEDRO BACQUIAO MEMORIAL ES,MINARA ES,SAN NICOLAS ES,TRINIDAD CARIO ES,ABAROAN NATIONAL HS,TAGUMPAY NATIONAL HS,TINITIAN ES,ROXAS PALAWAN,DPWH IBANGLEY RESTHOUSE,ABONGAN TAYTAY PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱1.5M | 100% | Low risk27 | —-0.011 |
| 96 | 17EE0055CLUSTER 2 - CONSTRUCTION OF RAINWATER COLLECTION SYSTEMS(RWCS); 1.TUMARBONG NHS,BGY. TUMARBONG ROXAS PALAWAN 2.PORT BARTON ES BGY.PORT BARTON SAN VICENTE PALAWAN 3.MONTEVISTA ES,CEZAR RODRIGUEZ MEMORIAL ES,TAYTAY CENTRAL NHS,ALACALIAN NHS,ABONGAN NHS,DPWH | Region IV-B | Palawan 1st DEO | Completed | ₱1.7M | 100% | Low risk27 | —-0.011 |
| 97 | 21EE0096CONCRETING OF ROADS-SOCRATES STREET CORNER RIZAL STREET | Region IV-B | Palawan 1st DEO | Completed | ₱2M | 100% | Low risk20 | —-0.076 |
| 98 | 21EE0059CONCRETING OF ROADS-NATIONAL HIGHWAY ROAD LEADING TO SANTAN STREET BARANGAY VILLA LIBERTAD, EL NIDO, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱2M | 100% | Low risk20 | —-0.068 |
| 99 | 21EE0057CONCRETING OF ROADS - TIOLTIOL STREET BARANGAY PROPER IN BARANGAY SIBALTAN, EL NIDO, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱2M | 100% | Low risk20 | —-0.069 |
| 100 | 21EE0058CONCRETING OF ROADS-SITIO MENIGUID (PUROK 1) LEADING TO PANCOL NATIONAL HIGH SCHOOL BARANGAY PANCOL, TAYTAY, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱2M | 100% | Low risk20 | —-0.068 |