Opening the dossier…
Opening the dossier…
Contractor dossier
77 projects on file, including joint ventures this contractor is part of.
Total projects
77
Total budget
₱653.5M
Average progress
95.9%
Completion rate
75.3%
Average risk score
38.7
Medium risk on average, out of 100
Flagged as unusual
3
3.9% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VII | 77 | ₱653.5M | 38.7 | 3 | 95.9% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 55 | ₱354.8M | 36.2 | 1 | 96.6% |
| Roads | 16 | ₱259.5M | 44.6 | 2 | 92.8% |
| Water Provision and Storage | 5 | ₱34.3M | 46.6 | 0 | 98.2% |
| Flood Control and Drainage | 1 | ₱5M | 45.9 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Nothing to report.
No high-risk projects here.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25HG0075CONCRETING OF SITIO SANTA CRUZ, BRGY. ANTIPOLO FMR, BRGY. ANTIPOLO, MEDELLIN, CEBU | Region VII | Cebu 4th DEO | On-Going | ₱9.7M | 63% | Medium risk44 | Flagged0.007 |
| 24H00167CONSTRUCTION OF ACADEMIC BUILDING CNU-MEDELLIN CAMPUS- CEBU NORMAL UNIVERSITY | Region VII | Region VII | On-Going | ₱39.7M | 71% | Medium risk49 | Flagged0.006 |
| 25HG0074CONCRETING OF BRGY. SAB-A TO BRGY. LIBAONG FMR (PHASE II) WITH BOX CULVERT, BRGY. SAB-A LIBAONG, SAN REMIGIO, CEBU | Region VII | Cebu 4th DEO | On-Going | ₱14.5M | 67% | Medium risk48 | Flagged0.006 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25HG0061SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, BARANGAY MABULI, TABOGON, CEBU | Region VII | Cebu 4th DEO | On-Going | ₱49M | 77% | Medium risk50 | —-0.055 |
| 2 | 24HD0062CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), POBLACION, TABOGON, CEBU | Region VII | Cebu 4th DEO | Completed | ₱29.7M | 100% | Medium risk50 | —-0.090 |
| 3 | 25HG0015CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY TALANGNAN, MADRIDEJOS, CEBU | Region VII | Cebu 4th DEO | On-Going | ₱4.9M | 84% | Medium risk49 | —-0.053 |
| 4 | 25HG0017CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BUNAKAN, MADRIDEJOS, CEBU | Region VII | Cebu 4th DEO | On-Going | ₱9.6M | 91% | Medium risk49 | —-0.055 |
| 5 | 25HG0081CONSTRUCTION OF MULTI-PURPOSE BUILDING OF BRGY. MAHARUHAY, MEDELLIN, CEBU | Region VII | Cebu 4th DEO | On-Going | ₱4.9M | 65% | Medium risk49 | —-0.047 |
| 6 | 23HD0044CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TUGAS, MADRIDEJOS, CEBU | Region VII | Cebu 4th DEO | Completed | ₱7.9M | 100% | Medium risk49 | —-0.093 |
| 7 | 23HD0056COMPLETION OF TABOGON PUBLIC MARKET, TABOGON, CEBU | Region VII | Cebu 4th DEO | Completed | ₱24.8M | 100% | Medium risk49 | —-0.091 |
| 8 | 24H00167CONSTRUCTION OF ACADEMIC BUILDING CNU-MEDELLIN CAMPUS- CEBU NORMAL UNIVERSITY | Region VII | Region VII | On-Going | ₱39.7M | 71% | Medium risk49 | Flagged0.006 |
| 9 | 25HG0010CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BANTIGUE, BANTAYAN, CEBU | Region VII | Cebu 4th DEO | On-Going | ₱4.9M | 71% | Medium risk49 | —-0.048 |
| 10 | 25HG0079CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY ILIHAN, TABOGON, CEBU | Region VII | Cebu 4th DEO | On-Going | ₱4.9M | 95% | Medium risk48 | —-0.058 |
| 11 | 25HG0078CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY ILIHAN, TABOGON, CEBU | Region VII | Cebu 4th DEO | Completed | ₱4.9M | 100% | Medium risk48 | —-0.094 |
| 12 | 23HD0055CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY GIBITNGIL, MEDELLIN, CEBU | Region VII | Cebu 4th DEO | Completed | ₱5M | 100% | Medium risk48 | —-0.095 |
| 13 | 25HG0012CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY LUY-A, MEDELLIN, CEBU | Region VII | Cebu 4th DEO | Completed | ₱4.9M | 100% | Medium risk48 | —-0.093 |
| 14 | 23HD0046COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY SUNGKO, BANTAYAN, CEBU | Region VII | Cebu 4th DEO | Completed | ₱5M | 100% | Medium risk48 | —-0.093 |
| 15 | 25HG0019CONSTRUCTION OF MULTI-PURPOSE BUILDING, MANLAGTANG ELEMENTARY SCHOOL, BARANGAY MANLAGTANG, TABOGON, CEBU | Region VII | Cebu 4th DEO | On-Going | ₱4.9M | 98% | Medium risk48 | —-0.060 |
| 16 | 25HG0069CONSTRUCTION OF MULTI-PURPOSE BUILDING, PANUGNAWAN ELEMENTARY SCHOOL, MEDELLIN, CEBU | Region VII | Cebu 4th DEO | On-Going | ₱4.9M | 98% | Medium risk48 | —-0.060 |
| 17 | 25HG0044CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LABANGON, TABOGON, CEBU | Region VII | Cebu 4th DEO | On-Going | ₱4.9M | 93% | Medium risk48 | —-0.055 |
| 18 | 25HG0027CONSTRUCTION OF MULTI-PURPOSE BUILDING, LIBERTAD NATIONAL HIGH SCHOOL, BARANGAY LIBERTAD, BOGO CITY, CEBU | Region VII | Cebu 4th DEO | On-Going | ₱4.9M | 96% | Medium risk48 | —-0.058 |
| 19 | 23HD0072COMPLEETION OF MULTI-PURPOSE BUILDING IN THE BARANGAY TAMBONGAN, MUNICIPALITY OF SAN REMEGIO, CEBU | Region VII | Cebu 4th DEO | Completed | ₱5M | 100% | Medium risk48 | —-0.094 |
| 20 | 23HD0038CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY ARGAWANON, SAN REMEGIO, CEBU | Region VII | Cebu 4th DEO | Completed | ₱9.9M | 100% | Medium risk48 | —-0.094 |
| 21 | 23HD0045CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, MEDELLIN, CEBU | Region VII | Cebu 4th DEO | Completed | ₱9.9M | 100% | Medium risk48 | —-0.094 |
| 22 | 23HD0015CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BONGON, TABUELAN, CEBU | Region VII | Cebu 4th DEO | Completed | ₱5M | 100% | Medium risk48 | —-0.094 |
| 23 | 25HG0011CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LAMINTAK NORTE, MEDELLIN, CEBU | Region VII | Cebu 4th DEO | On-Going | ₱9.6M | 76% | Medium risk48 | —-0.050 |
| 24 | 25HG0074CONCRETING OF BRGY. SAB-A TO BRGY. LIBAONG FMR (PHASE II) WITH BOX CULVERT, BRGY. SAB-A LIBAONG, SAN REMIGIO, CEBU | Region VII | Cebu 4th DEO | On-Going | ₱14.5M | 67% | Medium risk48 | Flagged0.006 |
| 25 | 24HD0015CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY CANHABAGAT, MEDELLIN, CEBU | Region VII | Cebu 4th DEO | Completed | ₱7.9M | 100% | Medium risk48 | —-0.094 |