93 projects on file, including joint ventures this contractor is part of.
Total projects
93
Total budget
₱509.7M
Average progress
98.0%
Completion rate
90.3%
Average risk score
28.0
Low risk on average, out of 100
Flagged as unusual
5
5.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region X | 75 | ₱445.6M | 25.0 | 0 | 99.8% |
| Region XIII | 18 | ₱64.1M | 40.6 | 5 | 90.4% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 67 | ₱355.6M | 21.5 | 0 | 99.6% |
| Roads | 13 | ₱98.4M | 37.0 | 0 | 100.0% |
| Water Provision and Storage | 5 | ₱16M | 27.3 | 1 | 81.0% |
| GAA 2025 SSP | 4 | ₱19.7M | 93.2 | 4 | 85.3% |
| Bridges | 2 | ₱10.3M | 31.8 | 0 | 100.0% |
| OTHER | 1 | ₱4.9M | 75.3 | 0 | 90.9% |
| Flood Control and Drainage | 1 | ₱4.9M | 38.2 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25NE0004CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER) BARANGAY CAYETANO, DINAGAT, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | On-Going | ₱4.9M | 74% | High risk95 | Flagged0.011 |
| 25NE0002REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY SANTO NIÑO, BASILISA, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | On-Going | ₱4.9M | 95% | High risk94 | Flagged0.005 |
| 25NE0066REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY CATADMAN, BASILISA, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | On-Going | ₱4.9M | 100% | High risk93 | Flagged0.001 |
| 25NE0065CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MAUSWAGON, DINAGAT, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | On-Going | ₱4.9M | 72% | High risk92 | Flagged0.011 |
| 25NE0020CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS DIEGAS-RITA GLENDA-BENGLEN ROAD LEADING TO GAAS INLET, BASILISA, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | On-Going | ₱4.9M | 91% | High risk75 | —-0.002 |
| 25NE0068CONSTRUCTION OF SOLAR WATER SUPPLY SYSTEM AT BRGY. DEL PILAR (DEL PILAR DAM), CAGDIANAO, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | On-Going | ₱4.9M | 13% | High risk61 | Flagged0.022 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25NE0068CONSTRUCTION OF SOLAR WATER SUPPLY SYSTEM AT BRGY. DEL PILAR (DEL PILAR DAM), CAGDIANAO, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | On-Going | ₱4.9M | 13% | High risk61 | Flagged0.022 |
| 25NE0065CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MAUSWAGON, DINAGAT, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | On-Going | ₱4.9M | 72% | High risk92 | Flagged0.011 |
| 25NE0004CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER) BARANGAY CAYETANO, DINAGAT, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | On-Going | ₱4.9M | 74% | High risk95 | Flagged0.011 |
| 25NE0002REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY SANTO NIÑO, BASILISA, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | On-Going | ₱4.9M | 95% | High risk94 | Flagged0.005 |
| 25NE0066REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY CATADMAN, BASILISA, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | On-Going | ₱4.9M | 100% | High risk93 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 20KA0115CONSTRUCTION OF MULTI PURPOSE BUILDING - CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BUKIDNON STATE UNIVERSITY,BRGY. POBLACION LANTAPAN, BUKIDNON | Region X | Bukidnon 1st DEO | Completed | ₱4.9M | 100% | Medium risk41 | —-0.094 |
| 27 | 25KA0022CONSTRUCTION OF MULTI-PURPOSE BUILDING,BARANGAY 9, MALAYBALAY CITY, BUKIDNON BARANGAY 9, MALAYBALAY CITY, BUKIDNON 2ND LD | Region X | Bukidnon 1st DEO | On-Going | ₱5.9M | 84% | Medium risk41 | —-0.052 |
| 28 | 24KA0025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY DALWANGAN, MALAYBALAY CITY, BUKIDNON, BARANGAY DALWANGAN, MALAYBALAY CITY, BUKIDNON 2ND LD | Region X | Bukidnon 1st DEO | Completed | ₱5M | 100% | Medium risk41 | —-0.095 |
| 29 | 20KC0104CONSTRUCTION OF MULTI-PURPOSE BUILDING, MUNICIPAL COMPOUND BRGY. KISOLON, SUMILAO, BUKIDNON | Region X | Bukidnon 3rd DEO | Completed | ₱5M | 100% | Medium risk41 | —-0.095 |
| 30 | 23KC0080CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY LUPIAGAN, SUMILAO, BUKIDNON | Region X | Bukidnon 3rd DEO | Completed | ₱5M | 100% | Medium risk41 | —-0.095 |
| 31 | 24KC0048CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY PUNTIAN, SUMILAO, BUKIDNON | Region X | Bukidnon 3rd DEO | Completed | ₱5M | 100% | Medium risk41 | —-0.095 |
| 32 | 23KC0096CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY LICOAN, SUMILAO, BUKIDNON | Region X | Bukidnon 3rd DEO | Completed | ₱5M | 100% | Medium risk41 | —-0.095 |
| 33 | 18KA0098CONSTRUCTION OF 3-STOREY, 9-CLASSROOM SCHOOL BUILDING AT SAN MARTIN AGRO-INDUSTRIAL NHS, MALAYBALAY CITY, BUKIDNONMALAYBALAY CITY, BUKIDNON | Region X | Bukidnon 1st DEO | Completed | ₱26.3M | 100% | Medium risk40 | —-0.040 |
| 34 | 19KC0106CONCRETING OF BRGY. POBLACION BRGY. CONCEPTION FMR BRGY. POBLACION, PANGANTUCAN, BUKIDNON | Region X | Bukidnon 3rd DEO | Completed | ₱10M | 100% | Medium risk40 | —-0.041 |
| 35 | 19KA0159CONCRETING OF BRGY. IMBAYAO FMR, BRGY. IMBAYAO, MALAYBALAY CITY, BUKIDNON, BRY. IMBAYAO, MALAYBALAY CITY, BUKIDNON 2ND LD | Region X | Bukidnon 1st DEO | Completed | ₱8.9M | 100% | Medium risk40 | —-0.040 |
| 36 | 25NE0067CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY CORTES, BASILISA, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | On-Going | ₱4.9M | 91% | Medium risk40 | —-0.053 |
| 37 | 22KA0111CONCRETING OF SITIO NALUMUSAN, BRGY. SILAE FMR, BRGY. SILAE, MALAYBALAY CITY, BUKIDNON, SITIO NALUMUSAN, BRGY. SILAE FMR, BRGY. SILAE, MALAYBALAY CITY, BUKIDNON 2ND LD | Region X | Bukidnon 1st DEO | Completed | ₱11.9M | 100% | Medium risk39 | —-0.036 |
| 38 | 18KC0138CONSTRUCTION OF 2STY 4CL WITH TOILET ATTACHED SCHOOL BUILDING LACOLAC ES, BAUNGON, BUKIDNON | Region X | Bukidnon 3rd DEO | Completed | ₱12.1M | 100% | Medium risk39 | —-0.050 |
| 39 | 22NG0059REHABILITATION OF SEAWALL, SITIO SABANG, BRGY. TAYAGA, CLAVER, SURIGAO DEL NORTE/BRGY. TAYAGA, CLAVER, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | Completed | ₱4.9M | 100% | Medium risk38 | —-0.066 |
| 40 | 25NE0011CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY MAGSAYSAY, DINAGAT, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | Completed | ₱4.9M | 100% | Medium risk37 | —-0.084 |
| 41 | 18KA0092CONSTRUCTION OF 1-STOREY, 5-CLASSROOM SCHOOL BUILDING AT KIBUDA ES,LANTAPAN, BUKIDNON | Region X | Bukidnon 1st DEO | Completed | ₱7.2M | 100% | Medium risk36 | —-0.048 |
| 42 | 17KH0040CONST/REHAB OF WATER SUPPLY/SEPTAGE & SEWERAGE/RAIN WATER COLLECTORS AND RWCS, VARIOUS BRGYS OF CDOC | Region X | Cagayan de Oro City 1st DEO | Completed | ₱3.1M | 100% | Low risk25 | —-0.038 |
| 43 | 25NE0071CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM | Region XIII | Dinagat Islands DEO | On-Going | ₱2.6M | 92% | Low risk21 | —-0.020 |
| 44 | 17KH0003CONCRETING OF ROAD - GUMAMELA EXTENSION (NOMING AREA), CARMEN, CAGAYAN DE ORO CITY | Region X | Cagayan de Oro City 1st DEO | Completed | ₱2M | 100% | Low risk20 | —-0.068 |
| 45 | 17KH0100CONSTRUCTION OF MULTI-STOREY TVL: 3STY6CL - CARMEN NHS, BRGY. CARMEN, CAGAYAN DE ORO CITY | Region X | Cagayan de Oro City 1st DEO | Completed | ₱13.5M | 100% | Low risk20 | —-0.026 |
| 46 | 20KA0024WIDENING OF BRIDGE - CASISANG BR (B01252MN) ALONG JCT SH IMPALAMBONG-OLD CASISANG ROADMALAYBALAY CITY, BUKIDNON | Region X | Bukidnon 1st DEO | Completed | ₱4.4M | 100% | Low risk18 | —-0.060 |
| 47 | 17KA0127CONSTRUCTION OF 1-STOREY, 5-CLASSROOM SCHOOL BUILDING @KIBALABAG ES, MALAYBALAY CITY BUKIDNONMALAYBALAY CITY, BUKIDNON | Region X | Bukidnon 1st DEO | Completed | ₱6.1M | 100% | Low risk18 | —-0.024 |
| 48 | 17KA0126CONSTRUCTION OF 1-STOREY, 5-CLASSROOM SCHOOL BUILDING @CANDIISAN ES, MALAYBALAY CITY BUKIDNONMALAYBALAY CITY, BUKIDNON | Region X | Bukidnon 1st DEO | Completed | ₱6.2M | 100% | Low risk18 | —-0.024 |
| 49 | 21KA0093CONSTRUCTION OF WATER SYSTEM, BARANGAY ST. PETER, MALAYBALAY CITY, BUKIDNON BRGY. ST. PETER, MALAYBALAY CITY, BUKIDNON 2ND LD | Region X | Bukidnon 1st DEO | Completed | ₱4.5M | 100% | Low risk16 | —-0.056 |
| 50 | 19KC0066CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD TANKULAN, MANOLO FORTICH, BUKIDNON | Region X | Bukidnon 3rd DEO | Completed | ₱2.5M | 100% | Low risk16 | —-0.092 |